Mechanical Contractors Ass'n of Cincinnati v. University of Cincinnati

2002 Ohio 3506, 119 Ohio Misc. 2d 109
CourtOhio Court of Claims
DecidedMay 20, 2002
DocketNo. 98-07122
StatusPublished
Cited by2 cases

This text of 2002 Ohio 3506 (Mechanical Contractors Ass'n of Cincinnati v. University of Cincinnati) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mechanical Contractors Ass'n of Cincinnati v. University of Cincinnati, 2002 Ohio 3506, 119 Ohio Misc. 2d 109 (Ohio Super. Ct. 2002).

Opinion

J. Warren Bettis, Judge.

{¶ 1} On February 20, 2001, the Tenth District Court of Appeals reversed this court’s May 22, 2000 judgment that had denied plaintiffs’ claims for damages and attorney fees and remanded the case to this court for a determination of the nature and extent of plaintiffs’ damages. That court’s opinion states:

{¶ 2} “In denying all damages, the Court of Claims summarily held that ‘[biased upon the evidence presented, * * * plaintiffs are not entitled to any relief beyond’ the injunctive relief granted. The court cited, without discussion, two cases: Hardrives Paving & Constr., Inc. v. City of Niles (1994), 99 Ohio App.3d 243, 247 [650 N.E.2d 482]; and, an Eighth Appellate District case, Cavanaugh Bldg. Corp. v. Bd. of Cuyahoga Cty. Commrs. (Jan. 27, 2000), Cuyahoga App. No. 75607, 2000 WL 86554.

{¶ 3} “ ‘In Hardnves Paving & Constr., the Eleventh Appellate District held:

{¶ 4} “ ‘Injunctive relief should not ordinarily be granted unless irreparable injury will result. * * * Stated otherwise, “[a]n injunction is proper only where there is no adequate remedy at law. Fodor v. First Natl. Supermarkets (1992), 63 Ohio St.3d 489, 491 [589 N.E.2d 17] * * *. It would appear that if monetary damages for lost profits were an available remedy, damages would provide an adequate remedy at law and injunction would not be appropriate. Thus, the fact that injunctive relief is available generally indicates that a monetary award is not available for lost profits.

{¶ 5} “ ‘Furthermore, other policy considerations militate against allowing monetary damages. The intent of competitive bidding is to protect both the public and the bidders themselves. See Cedar Bay Constr. [v. City of Fremont (1990)], 50 Ohio St.3d [19] at 21 [552 N.E.2d 202] * * *. Thus, if we were to allow appellant to receive monetary damages, only the bidders would be protected because the public would have to pay the contract price of the successful bidder plus the lost profits of an aggrieved bidder. However, if injunction is the sole remedy, both the public and the bidders themselves are protected.’ Id. at 247-248 [650 N.E.2d 482],

{¶ 6} “At first blush, the above rationale upon which monetary damages are denied is logical and pragmatic. However, we are troubled by the reality that the limited relief granted results in a public entity’s potential ability to violate laws intended to benefit the public without fear of any meaningful reprisal which might deter such violations in the future. In addition, we are mindful of the fact that the plaintiffs who pursue such litigation and prevail in attaining a declaratory [113]*113judgment favorable to all taxpayers might have no recourse in recouping financial losses incurred in the process.

{¶ 7} “The minimal case law addressing this dilemma suggests that the remedies of injunction and declaratory judgment on the one hand, and money damages on the other, are necessarily mutually exclusive. Under the circumstances of this case, we cannot sustain the trial court’s holding that, as a matter of law, these plaintiffs are entitled to no further relief than injunction.

{¶ 8} . “This litigation has been ongoing for years. The plaintiffs have unceasingly attempted to compel the university to comply with the law and, based upon this record, have had good reason to anticipate that they might eventually, at the very least, recoup in the form of damages a portion of the extraordinary efforts and funds expended. Ultimately, if this court sustains the damages holding, these plaintiffs win only a very expensive, hollow victory in the form of a retrospective, virtually inconsequential wrist-slap to the university and a prospective cautionary declaration. The latter should certainly benefit the public; however, if plaintiffs are not granted more than a hollow victory, an understandable chilling effect would ensue upon future similarly situated would-be plaintiffs.

{¶ 9} Upon review of the case file, the opinion of the court of appeals, and the briefs submitted by the parties, this court makes the following determination.1

{¶ 10} Promissory estoppel is an equitable doctrine that is designed to prevent harm which results from reasonable and detrimental reliance upon improper representations. An essential element of an action predicated upon promissory estoppel is the detrimental reliance of the promisee upon false representations of the promisor. Karnes v. Doctors Hosp. (1990), 51 Ohio St.3d 139, 555 N.E.2d 280.

[114]*114{¶ 11} Defendant argues that plaintiffs cannot recover damages on a theory of promissory estoppel because defendant did not represent in any of its bid documentation that it would comply with the public bidding requirements of R.C. Chapter 153. However, that argument lacks merit. Since defendant is a state university, it should have been complying with the provisions of R.C. Chapter 153 from the beginning of the construction project. The court finds that it would be reasonable for a bidder on the project to have relied on the representation that defendant, a state university, would be bound by the public works regulations contained in R.C. Chapter 153. Therefore, the court finds that if plaintiffs prove that they would have been awarded a subcontract if R.C. Chapter 153 had been followed, they may state a claim for damages under the equitable theory of promissory estoppel. However, those damages must be limited to the cost of the bid preparations. A plaintiff who would not have obtained a contract in the first instance has no legal entitlement to compensation because its bid estimates cannot be linked to the alleged mistake in the awarding of the contract to another bidder. See Midwest Serv. Mgt., Inc. v. Licking Valley Local Bd. of Edn. (2001), 144 Ohio App.3d 443, 760 N.E.2d 837. The court will analyze each party’s claim individually, as follows:

1. RPC Mechanical, Inc. (“RPC”)

{¶ 12} Majid Samarghandi, President of RPC, testified that RPC submitted a bid for the heating, ventilation and air conditioning (“HVAC”) on February 19, 1998, and a bid for additional tenant improvements on March 13, 1998. RPC was not awarded a contract for either bid. RPC asserts a claim for lost profits in the amount of $580,000 and bid preparation costs in the amount of $32,310. Defendant contends that even if bidding for the HVAC subcontract would have been performed pursuant to R.C. Chapter 153, RPC would not have been selected because it was not the lowest responsive and responsible bidder on that subcontract. RPC’s initial bid form was incomplete, containing only the base price of $3,081,000. Upon determining that RPC and Peck, Hannaford & Briggs (“PHB”) were the two most responsive and responsible bidders, defendant allowed both companies to file revised bids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mechanical Contractors Ass'n v. University of Cincinnati
788 N.E.2d 670 (Ohio Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Ohio 3506, 119 Ohio Misc. 2d 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mechanical-contractors-assn-of-cincinnati-v-university-of-cincinnati-ohioctcl-2002.