MDR Construction Co., Inc. v. Veterans Construction LLC

CourtDistrict Court, D. Massachusetts
DecidedFebruary 16, 2024
Docket1:22-cv-10238
StatusUnknown

This text of MDR Construction Co., Inc. v. Veterans Construction LLC (MDR Construction Co., Inc. v. Veterans Construction LLC) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MDR Construction Co., Inc. v. Veterans Construction LLC, (D. Mass. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

_______________________________________ ) MDR CONSTRUCTION CO., INC., ) ) Plaintiff, ) ) Civil Action No. v. ) 22-10238-FDS ) VETERANS CONSTRUCTION, LLC, ) and GREAT MIDWEST INSURANCE ) COMPANY, ) ) Defendants. ) _______________________________________)

MEMORANDUM AND ORDER ON PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT, DEFENDANT VETERANS CONSTRUCTION’S MOTION FOR PARTIAL SUMMARY JUDGMENT, AND PLAINTIFF’S MOTION TO STRIKE

SAYLOR, C.J. This is an action for payment for work performed by plaintiff MDR Construction Co., Inc. at the Bedford Plains Veterans Affairs campus in Bedford, Massachusetts. MDR, the primary subcontractor for the project, has brought suit against Veterans Construction, LLC, the general contractor, and Great Midwest Insurance Company, the surety. MDR alleges that Veterans has failed to pay MDR $71,333.55 for its work on the contract, and that Great Midwest has breached its duty to make payment under the payment bond that it provided. According to MDR, it completed all work in a timely matter and complied with its contractual obligations. Indeed, it is undisputed that Veterans certified to the Department of Veterans Affairs that (with one minor exception) all work on the project was complete, and that it intended to pay MDR in full from the payment made to it by the VA. The VA then paid Veterans in full. It is also undisputed that Veterans withheld payment from MDR in the amount of $71,333.55. MDR alleges that the failure of Veterans arises out of a personal dispute between the president of Veterans, Frank Kemp, and Michael Saccone, his counterpart at MDR. In fact, Kemp freely acknowledged in his deposition that he did not make payment to MDR because he felt that Saccone had “denigrated” him in front of his employees.

Veterans, however, now claims that the reason it did not pay MDR is because it has not received a complete set of as-built drawings. It is undisputed that MDR provided as-built drawings directly to the VA. MDR contends that it did so because Veterans instructed it to; Veterans contends that the contract requires submission of the drawings to it, and that any instruction to the contrary cannot modify MDR’s contractual obligations. It further contends that in any event the drawings were incomplete and inadequate. Not surprisingly, MDR contends that those stated reasons were fabricated after the fact. MDR has moved for partial summary judgment on its breach of contract claim. Veterans has cross-moved for partial summary judgment on the claims against it for fraud and violation of Mass. Gen. Laws ch. 93A, § 11. In addition, MDR has moved to strike the motion for partial

summary judgment and portions of the affidavit of Ken Duquette, a Veterans employee. Unfortunately for MDR, this matter involves disputed issues of material fact that preclude summary judgment in its favor. There is, to be sure, substantial evidence that Veterans deliberately breached the contract for purposes of personal spite, and not due to any material breach by MDR. If MDR can successfully prove that claim, it may be entitled, among other things, to treble damages and attorney’s fees under Mass. Gen. Laws ch. 93A. Under the circumstances, however, the Court has no alternative but to deny summary judgment as to the breach of contract claim. The cross-motion of Veterans for partial summary judgment will likewise be denied, on the ground that it was not filed until nearly three weeks after the court-ordered deadline, without leave of court and without good cause shown. The motion of MDR to strike the affidavit is without merit and will be denied. Accordingly, and for the following reasons, the motion of MDR for summary judgment

will be denied, the motion of Veterans for summary judgment will be denied, and the motion of MDR to strike will be denied. I. Background The following facts are undisputed unless otherwise noted. A. Factual Background On March 21, 2019, the Department of Veterans Affairs (“VA”) entered into a contract with Veterans Construction, LLC to upgrade hot water and plumbing at the Bedford Plains VA campus in Bedford, Massachusetts. (Plaintiff’s SUF ¶ 1). MDR Construction Co., Inc., entered into a subcontract agreement with Veterans concerning the project on May 29, 2019. (Id. at Exhibit 10). The original subcontract sum was $4,284,928.65. (Id. at ¶ 3). It later increased, after change orders, to $8,359,478.53. (Id.).

The subcontract provided in part as follows: “[T]he Contractor will pay the Subcontractor within seven days after receipt of payment by the Contractor from the owner. When the Subcontractor’s Work is substantially completed in accordance with the contract documents and accepted by the Architect/Engineer and Owner, the Contractor will, on the Subcontractor’s application, apply to the Owner for a reduction of retainage. All amounts paid by the Owner to the Contractor for the Subcontractor’s Work shall be paid to the Subcontractor less amounts determined for incomplete Work and unsettled claims as provided in the Contract Documents. Final retainage shall be paid within seven days after the Contractor receives it from the Owner.” (Id. at ¶ 39). In addition, the prime contract between Veterans and the VA “expressly prohibits a contractor from requesting payment for any amount withheld from a subcontractor.” (Id. at 37). Over the course of the project, Veterans periodically billed the VA. (Id. at ¶ 6). On November 19, 2021, it made its final payment request to the VA for the “remaining $30,688.51

of the $9,197,337.22 total contract price, minus . . . $1,000 of uncompleted work.” (Id. at ¶ 7; Id. at Exhibit 3). In its final request, Veterans made at least four representations to the VA: (1) that all of the work in each of the seven phases of the project was 100% complete (Id. at Exhibit 3, pp. 2-4); (2) that there remained only $1,000 of “uncompleted” work (Id. at Exhibit 3, 1); (3) that it had already paid MDR from the previous payments received under the contract and would timely pay MDR in full from the proceeds of the payment covered by the certification (Id.); and (4) that the request for payment did not include any amounts that Veterans “intend[ed] to withhold or retain” from MDR. (Id.). Veterans thereafter received final payment from the VA. (Id. at ¶ 12). It is undisputed that it was paid in full on the project; that it represented to the VA that all project work was

complete; that it affirmed that it would not seek a “lesser amount for itself by virtue of any legitimate withholding”; and that it had previously made periodic payments to MDR. Nonetheless, it still withheld $71,333.55 from MDR. (Plaintiff’s SUF ¶ 11-13, 18, 40, 45; Id. at Exhibit 12). According to MDR, the nonpayment stems from a personal dispute between the president of Veterans, Frank Kemp, and his counterpart at MDR, Michael Saccone. During his deposition, Kemp testified: “I stopped payment when Mr. Saccone denigrated me in front of one of his employees.” (Docket No. 51, Exhibit A, 15). Kemp also agreed that he did not “resume payments after that point in time” because he “didn’t want to pay someone was going to say negative things about [him].” (Id. at 15-16). Veterans contends that it is withholding payment from MDR due to MDR’s “refusal to provide Veterans with an adequate and complete set of As-Built Drawings as required by the Subcontract Agreement.” (Docket No. 52, 7). It is undisputed that Article 7 of the subcontract

expressly states that “[f]inal payment shall be due only when the Subcontractor shall furnish the Contractor . . . as-built drawings, maintenance manuals and warranties for the Subcontractor’s work.” (Docket No. 51, Exhibit D).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Teragram Corporation v. MarketWatch.com,Inc.
444 F.3d 1 (First Circuit, 2006)
Moringlane-Ruiz v. Trujillo-Panisse
232 F. App'x 8 (First Circuit, 2007)
Abraham Alvarado-Morales v. Digital Equipment Corp.
843 F.2d 613 (First Circuit, 1988)
Milissa Garside v. Osco Drug, Inc.
895 F.2d 46 (First Circuit, 1990)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Patrick J. O'COnnOr v. Robert W. Steeves
994 F.2d 905 (First Circuit, 1993)
Bose Corporation v. Ejaz
732 F.3d 17 (First Circuit, 2013)
Ward v. American Mutual Liability Insurance
443 N.E.2d 1342 (Massachusetts Appeals Court, 1983)
ZURICH AMERICAN INSURANCE COMPANY v. Watts Regulator Co.
796 F. Supp. 2d 240 (D. Massachusetts, 2011)
Ross-Simons of Warwick, Inc. v. Baccarat, Inc.
182 F.R.D. 386 (D. Rhode Island, 1998)
Rivera-Aponte v. Gomez Bus Line, Inc.
62 F.4th 1 (First Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
MDR Construction Co., Inc. v. Veterans Construction LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mdr-construction-co-inc-v-veterans-construction-llc-mad-2024.