MDK Sociedad v. Proplant

25 F.4th 360
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 9, 2022
Docket21-20207
StatusPublished
Cited by114 cases

This text of 25 F.4th 360 (MDK Sociedad v. Proplant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MDK Sociedad v. Proplant, 25 F.4th 360 (5th Cir. 2022).

Opinion

Case: 21-20207 Document: 00516196970 Page: 1 Date Filed: 02/09/2022

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED February 9, 2022 No. 21-20207 Lyle W. Cayce Clerk

MDK Sociedad De Responsabilidad Limitada,

Plaintiff—Appellant/Cross-Appellee,

versus

Proplant Incorporated (Texas); Proplant Incorporated (Nevada),

Defendants—Appellees/Cross-Appellants.

Appeal from the United States District Court for the Southern District of Texas USDC No. 4:18-CV-485

Before Jones, Higginson, and Duncan, Circuit Judges. Stephen A. Higginson, Circuit Judge: MDK Sociedad de Responsabilidad Limitada (“MDK”), a Bolivian entity, and Proplant, Inc., a Texas-based corporation, jointly pursued a lucrative operations and maintenance contract with Bolivia’s state-owned energy company. After the deal fell through, MDK sued Proplant under both breach of contract and tort theories. Before discovery was complete, the Case: 21-20207 Document: 00516196970 Page: 2 Date Filed: 02/09/2022

No. 21-20207

district court granted Proplant’s motion for summary judgment. We AFFIRM. 1 I. MDK’s complaint alleges that Proplant provided MDK with a proposed contract for subcontractor services in October 2016 (“the October Document”). MDK alleges that as of November 11, 2016, it had not executed the October Document. The district court found that MDK never signed the October Document, and nothing in the record indicates otherwise. MDK alleges that, in November 2016, Proplant told MDK that Proplant would provide the bid and performance bonds for a “potential contract in Bolivia.” Proplant allegedly waited until the final days before the due date before asking for more time to provide the bond. On December 13, 2016, Proplant allegedly informed MDK that, because of complexities relating to sending money overseas, it could not submit the bond. Proplant allegedly asked MDK to submit the bond instead. MDK allegedly replied that it would only submit the bond if Proplant signed a contract promising to pay MDK for the bond. The record indicates that on December 13, 2016, MDK and Proplant executed a “Commitment Agreement.” The Commitment Agreement explained that Yacimientos Petroliferos Fiscales Bolivianos (“YPFB”), Bolivia’s state-owned energy company, was soliciting bids for an operations and maintenance (“O&M”) contract. The Commitment Agreement

1 On the same day that the district court granted Proplant’s summary judgment motion, it also granted MDK’s motion to dismiss Proplant’s counterclaims against MDK. Proplant filed a notice of cross-appeal but stated in its brief that it “waives its cross-appeal in the event this Court issues an opinion affirming the district court’s summary judgment in favor of Proplant.” Because we affirm the district court’s summary judgment in favor of Proplant, we do not consider Proplant’s cross-appeal.

2 Case: 21-20207 Document: 00516196970 Page: 3 Date Filed: 02/09/2022

provided that MDK would assist Proplant with its efforts to obtain this O&M contract by collecting and filing certain documents for Proplant and by tendering to YPFB a bid bond of $500,000. In return, Proplant promised to furnish MDK with certain documents. Proplant also promised to take several other actions if it were “awarded” the O&M contract. Specifically, Proplant promised (1) “to execute the O&M agreement with YPFB pursuant to the terms set forth in” certain documents; (2) to pay MDK $500,000, plus bank charges, if it “decides not to execute the O&M agreement”; (3) “to subcontract MDK to provide all the services as set forth in” a separate document; and (4) to pay MDK $1 million from its “profits resulting from the execution of the Project.” The parties agree 2 that on December 14, 2016, Proplant bid on the YPFB project for the first time. They further agree that after YPFB declared the project deserted on December 30, Proplant bid on the YPFB project for a second time on January 19, 2017. MDK alleges that it submitted a $500,000 bid bond to YPFB and that Proplant assured MDK that it would “issue the contract bond if the bid is awarded.” The parties agree that a Proplant representative and an MDK representative met with YPFB on March 20, 2017. Mike Antony, an owner of Proplant, submitted a declaration stating that at this meeting, YPFB agreed to incorporate thirty technical and commercial changes into the parties’ bid. Antony further declared that YPFB requested that Proplant submit certain documents and a performance bond. MDK alleges that on March 22, 2017, YPFB awarded Proplant the O&M contract. MDK further alleges that, after being awarded the contract,

2 In response to a court order, the parties submitted a “Joint Agreed Timeline” to the district court.

3 Case: 21-20207 Document: 00516196970 Page: 4 Date Filed: 02/09/2022

Proplant was required to tender certain documents to YPFB and to deliver a performance bond. Proplant allegedly tendered the documents late and never provided the bond. On April 18, 2017, Proplant allegedly informed MDK that it would not submit the bond. The record indicates that on April 3, 2017, an MDK representative named Pablo Miya sent a WhatsApp message to a Proplant representative named Murthy Chitturi stating, “I just received a call from these guys saying that weird things are happening inside YPFB and that please we have to hurry up with the documents and sign the contract ASAP.” Then on April 4, Miya messaged Chitturi, “ypfb deadline will be thursday 14th. If we dont sign the contract and submit the 2 bonds by that date. Legal area will cancell the bidding process and executing the bid bond.” The parties agree that on April 5, “Techna sent a Letter of Transparency complaining about the bid process.” Miya later messaged Chitturi, “Everything happened because Tecna [sic] sent that letter.” Antony declared that on April 6, he travelled with Miya to YPFB’s office in Bolivia to personally deliver the requested documents. However, Antony continued, because YPFB’s contract manager did not show up to receive the documents, Antony and Miya left the documents with the manager’s secretary. Antony further explained that after again trying and failing to deliver the documents to YPFB several days later, Proplant representatives emailed the documents to YPFB. Antony concluded his declaration by stating that YPFB “failed to ever provide Proplant with a contract to execute.” The parties agree that on April 21, 2017, “YPFB declared the project deserted.” The parties further agree that they jointly sought legal advice from Bolivian lawyers, who advised them that because YPFB had deserted the project, it was legally obligated to return the bid bond to MDK. The

4 Case: 21-20207 Document: 00516196970 Page: 5 Date Filed: 02/09/2022

Bolivian lawyer stated in an email to Proplant, “YPFB is being abusive and its actions are politically driven.” The lawyer suggested two legal avenues that the parties could pursue, but he suggested that because “[t]he counter party is the Bolivian State (YPFB),” “any legal action could be seriously undermined by the current political scenario in our country.” Proplant forwarded the email to MDK, explaining that the Bolivian lawyer had proposed “two options to counter the politically driven decision by YPFB with no fault of us.” In February 2018, MDK sued Proplant. MDK’s complaint raises six causes of action. First, MDK claims that Proplant breached the October Document. Second, MDK claims that Proplant committed common law fraud by promising MDK in November 2016 that it would provide a bid bond even though it did not intend to do so. Third, MDK claims that Proplant breached the Commitment Agreement. Fourth, MDK claims that Proplant made negligent misrepresentations related to the Commitment Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
25 F.4th 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mdk-sociedad-v-proplant-ca5-2022.