McWilliams Dredging Co. v. United States

105 F. Supp. 582, 1952 U.S. Dist. LEXIS 4197
CourtDistrict Court, E.D. Louisiana
DecidedJune 18, 1952
DocketNo. 1206. In Admiralty
StatusPublished
Cited by2 cases

This text of 105 F. Supp. 582 (McWilliams Dredging Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McWilliams Dredging Co. v. United States, 105 F. Supp. 582, 1952 U.S. Dist. LEXIS 4197 (E.D. La. 1952).

Opinion

THOMAS, District Judge.

This cause involves a collision, and is a libel brought on the principles of an in rem proceeding under the provisions of the Suits in Admiralty Act, 46 U.S.C.A. § 741 et seq. The libelant seeks to recover for damage done to the discharge pipe line of one of its dredges, and for work stoppage occasioned thereby, when the line was struck by a tanker which, though under Norwegian registry, was owned by the United States.

The cause was argued on respondent’s motion to dismiss for lack of jurisdiction; on libelant’s motion to strike respondent’s supplemental and amended answer; on libelant’s exceptions to certain requests for admissions; and on the question of liability vel non. It was then taken under .submission on testimony heard in court, and on depositions, exhibits, and briefs.

The circumstances surrounding the collision were as follows:

On May 30, 1946, the tank ship “Kirkenes” departed from Port Arthur, Texas, about 9:15 a. m. (C. S. T.) en route to sea. She was manned by a Norwegian crew and master, but was being conned by Don Allien, a branch pilot for the Sabine District. Such pilots are compulsory between Port Arthur and the sea buoy.

■In going from Port Arthur to the sea buoy, it is necessary that vessels move through Sabine Pass. On the west bank [584]*584of Sabine Pass, near channel Station 130, is the United States Quarantine Station. On May 30, and for several days prior thereto, the dredge “G. A. McWilliams” was working in the vicinity of the Quarantine Station. The channel at this point was 500 feet wide, and adjoining the eastern boundary of the channel proper was an anchorage basin of equal depth with the channel. The “G. A. McWilliams”, on the morning of May 30, lay with her bow downstream, and her port side along the center line of the channel, about 250 feet from the west bank. Her discharge pipe line led directly astern for a distance of approximately 100 feet, and then, turning to the east at a right angle, extended 2300 feet in a straight line across the channel and the anchorage basin, and into the spoil disposal area on the eastern edge of the anchorage basin.

The pipe line thus formed an “L”, the first length of which was 100 feet long, leading up-stream directly astern of the dredge; the second length of which led off at a 90° angle to the right and extended eastward for a distance of 2,300 feet. This second length was of dual character. The westernmost 550 feet floated on pontoons which were not anchored, and it could thus be opened to permit passage of ships; the easternmost 1,750 feet rested on pontoons which were anchored, and it was thus immovable.

For convenience the entire length of pipe line will herein be designated into three segments, Segment No. 1 being the 100-foot length leading astern of the dredge; Segment No. 2 being the '550-foot flexible section; and Segment No. 3 being the 1,750-foot stationary section."

Segment No. 1 and Segment No. 2 were connected by a flexible elbow joint at a 90° angle to the right. This elbow joint was securely anchored and thus immovable. Segment No. 2 consisted of three separate lengths of pipe, the first being 250 feet long, the second 250 feet long, and the third, fifty feet long. All three of these sections were connected by ball joints at a 180° angle. Segment No. 2 and Segment No. 3 were connected by a ball joint at a 180° angle. The easternmost end of the pipe line at low tide rested on the ground A wooden walkway, fitted with a hand rail, extended along the top of the line for its entire length.

At the location of this pipe line, the anchorage basin had a width of 800 feet, adjacent to the eastern boundary line of the 500-foot channel. The dredge was working under contract with the War Department of the United States, cleaning out and deepening the channel and the anchorage basin. The anchorage basin extended up-stream some 4,000 feet north of the pipe line, and the basin had a constant width of 1,300 feet (including the 500-foot width of the channel) for a distance of approximately one-half mile north of the pipe line.

On May 1 and 24, 1946, the United States Engineer Office had issued navigation notices to the effect that the “G. A. McWilliams” was working in the Port Arthur Canal and Sabine Pass Channel, and would continue to do so throughout the month of May. The notice given on May 24 read as follows:

“During the progess of the work in its present location in Sabine Pass Channel (near the U. S. Quarantine Station) the plant’s discharge pipeline will extend to the east bank across the channel. The discharge line will be opened upon proper signal to allow for the passage of all vessels. Small craft which can safely pass on the west side of the dredge are expected to do so. The usual signal for passing should be given in sufficient time to enable the dredge operator to give the proper reply and to open the discharge line without delay.
“Vessel operators are directed to exercise the proper precaution in approaching the plant and pass in accordance with applicable regulations.”

Pilot Don Allien, during the progress of this dredging work, had taken a number of vessels in and out of Port Arthur; and on seven previous occasions it had been necessary that the pipe 'line be opened for the passage of vessels he was piloting.

At 10:44 a. m. (C.S.T.), on May 30, the “Kirkenes” struck the pipe line at the point [585]*585where the ball joint - connected the two above-described 250-foot sections of Segment No. 2, causing the whole segment to become disconnected from both Segment No. 1 and Segment No. 3. The disconnected Segment No. 2 was then carried downstream about 1,000 feet.

There was a great deal of testimony introduced from members of the crew of the “G. A. McWilliams”, all generally giving the same version as to how the accident occurred. The only testimony on the merits offered by the Government was that of Pilot Don Allien.

War Department regulations applicable to craft engaged in dredging operations in Sabine-Neches waterway, as well as Pilot Rules for Inland Waters, in effect on May 30, 1946, provided, among other things, as follows:

“When the pipe line from a dredge crosses the channel in such a way that an approaching vessel, owing to excessive draft or for other reasons, cannot pass around the pipe line or dredge, a signal shall be given from the vessel by sounding 4 blasts of the whistle, which shall be answered by a like signal from the dredge. The pipe line shall then be opened for the passage of the vessel as soon as practicable; when the line is open ready for passage, the dredge shall so indicate by sounding the usual passing signal, and the approaching vessel shall promptly pass the dredge.”

The testimony offered by the libelant was to the effect that three danger signals were sounded by the dredge, the first at 10:35 a. m., the second at 10:37 (or 10:38), and the third at 10:42 a. m. The collision occurred at 10:44.

Only two members of the crew of the “G. A. McWilliams” testified that they heard any signal ever given by the “Kirkenes”. Deck Captain John W. Eagleson testified that at 10:41 the “Kirkenes” gave two blasts (which was the signal for passing to the port side of the dredge). John Acy, Civil Engineer on the dredge, testified he heard two blasts from the “Kirkenes” about a minute before he blew the third danger signal from the dredge. None of the other members of the crew of the “G. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
105 F. Supp. 582, 1952 U.S. Dist. LEXIS 4197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcwilliams-dredging-co-v-united-states-laed-1952.