McNair v. M. L. Virden Lumber Co.

4 So. 2d 684, 193 Miss. 232
CourtMississippi Supreme Court
DecidedNovember 24, 1941
DocketNo. 34694.
StatusPublished
Cited by6 cases

This text of 4 So. 2d 684 (McNair v. M. L. Virden Lumber Co.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McNair v. M. L. Virden Lumber Co., 4 So. 2d 684, 193 Miss. 232 (Mich. 1941).

Opinion

Roberds, J.,

delivered the opinion of the court.

In the fall of 19391 Mr. and Mrs. Steve McNair procured plans and specifications for the erection of a residence some four miles from Clarksdale, in Coahoma County. They invited bids for the construction of the residence in accordance with those plans .and specifications. They *242 considered all bids too high. They had the plans revised, and again asked for bids according to the revised plans. Mr. H. B. Dunn was the lowest bidder. He was awarded the contract. It was written and dated November 8, 1939. It set out what Dunn was to do, but also expressly stated that certain parts of the job, such as electric work, were not in- the contract, and would be done by the Mc Nairs themselves. But Dunn’s bid included the plumbing. Dunn proceeded with the work, and the McNairs moved into the new home December 12,1939.

On February 13, 1940, appellee, Virden Lumber Company, Inc., gave Mr. McNair written notice that it had furnished to Dunn lumber which went into the construction of the building, and that the balance owing to it by Dunn was $549.09, and on April 10, 1940, it gave a like notice to Mrs. McNair. These notices were under section 2274, Code 1930:

About May 8, 1940, Virden filed a petition, in accordance with said section, in the county court of Coahoma County, making defendants thereto Dunn, the contractor, and the McNairs, the owners, and Hill, who had done plumbing work in the house, asking (1) that any balance owing by McNair to Dunn be impounded in the hands of McNair and be applied to the payment of-the balance of its account against Dunn; (2) that a lien be impressed on the property to secure the payment of its balance; and, (3) for a personal judgment against Dunn.

The McNairs answered this petition, admitting the contract with Dunn, the receipt of the notice to Mr. McNair, and that they owed Dunn a balance of $326.80 on the contract, offered to tender this amount into court, and asked that all claims of laborers and materialmen be brought into court and adjudicated.

Hill answered, claiming (1) that his contract was direct with the McNairs, and that he had a first lien on the house to secure payment of his account of $325, and was entitled to a personal judgment against the McNairs; but that if *243 mistaken in this, (2) he was entitled to share pro rata with all other unpaid laborers and materialmen in the balance owing by the owners to the contractor.

About August 15,1940, Memphis Sash & Door Company gave written notice to the McNairs that it had furnished materials which went into construction of the house and had not been paid, claiming a balance of $178.62. On or about August 16, 1940, this concern intervened in the pending case by filing a petition therein, claiming that its contract was direct with the McNairs, and it was entitled to a personal judgment against them and a lien on the house for its unpaid balance, but, if mistaken in this, that it was entitled to share, pro rata, with the other laborers and materialmen in the balance owing by the owners to the contractor.

No written notice was ever given the owners by Hill, unless the filing of the petition in this case constituted such notice.

The judgment of the county court was that the McNairs owed Dunn, the contractor, on February 13,1940, the date Mr. McNair received the Yirden notice, a balance of $548.57; that neither Hill nor the Memphis Sash & Door ■Company had a contract direct with the McNairs, but were sub-materialmen under the contractor, and that Yirden, having given the first notice to the owners, was ■entitled to full payment of its balance out of the fund's ■owing by the McNairs to Dunn, after payment of costs, and, if after such full payment there remained any balance, this would next be applied to the debt of Memphis Sash & Door Company, and any balance would then he applied to the debt to Hill, the plumber. In other words the county court held that priority of notice conferred priority of right of payment.

The judgment of the county court was affirmed by the •circuit court, from which the McNairs and Hill appeal. Memphis Sash & Door Company did not appeal.

In determining the amount owing by the McNairs to the contractor the lower court charged the McNairs with *244 $162.50' which they paid to Dunn after receiving the stop notice February 13th and gave the McNairs credit for $16. It found that the first item was paid for re-papering work defectively done by the contractor, which defects it was the contractor’s duty to remedy, and for which he was not entitled to extra pay, but that the second item was the- sum necessary to do other work to complete the contract. The McNairs assign this as error. The testimony supports the finding of the lower court, and we approve the finding of fact and conclusion of law.

Hill says the lower court was in error in finding that he had no contract direct with the McNairs. It would unnecessarily lengthen this opinion to detail the testimony on this point. We have examined it carefully, and we find it not only supports the finding of the lower court but that the preponderance thereof is in favor of such finding.

The most important question is whether, under the facts of the case, and under section 2274, Code of 1930', priority of notice confers priority of right as between those in the same class, or whether they share ratably regardless of the time of giving notice, or whether any notice is given at all. We are not considering a case where the owner pays the balance to the one giving notice before he receives such notice from others, or before others assert their claims in court. That is not this case. We will deal with that when and if such situation arises.

Section 2274, Code 1930, is as follows: “When any contractor or master workman shall not pay any person who may have furnished materials used in the erection, construction, alteration, or repair of any house, building, structure, fixture, boat, water craft, railroad, railroad embankment, the amount due by him to any subcontractor therein, or the wages of any journeyman or laborer employed by him therein, any such person, subcontractor, journeyman or laborer may give notice in writing to the *245

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amerihost Dev., Inc. v. Bromanco, Inc.
786 So. 2d 362 (Mississippi Supreme Court, 2001)
Amerihost Development, Inc. v. Bromanco, Inc.
Mississippi Supreme Court, 1998
Chancellor v. Melvin
52 So. 2d 360 (Mississippi Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
4 So. 2d 684, 193 Miss. 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcnair-v-m-l-virden-lumber-co-miss-1941.