McMullin Enterprises, Inc. v. Altemose Construction Co.

46 Pa. D. & C.2d 521, 1968 Pa. Dist. & Cnty. Dec. LEXIS 36
CourtPennsylvania Court of Common Pleas, Montgomery County
DecidedOctober 23, 1968
Docketnos. 68-1323 and 68-1516
StatusPublished

This text of 46 Pa. D. & C.2d 521 (McMullin Enterprises, Inc. v. Altemose Construction Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Montgomery County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMullin Enterprises, Inc. v. Altemose Construction Co., 46 Pa. D. & C.2d 521, 1968 Pa. Dist. & Cnty. Dec. LEXIS 36 (Pa. Super. Ct. 1968).

Opinion

Smillie, J.,

The matter herewith comes before the court on the petition of McMullin Enterprises, Inc., to vacate or in the alternative to modify or correct an award of arbitrators and to open and/or strike judgment. The petitions were dismissed by orders of the court en banc, dated June 28,1968.

The facts are as follows:

On August 11, 1965, Alternóse Construction Company and McMullin Enterprises, Inc. entered into a contract under which Alternóse was to build a restaurant and motel known as the Tankard Inn for McMullin in West Conshohocken, Pennsylvania, for $125,000. [522]*522The contract was the standard form of agreement between owner (McMullin) and contractor (Alternóse) prepared by the American Institute of Architects. The standard form contract incorporates by reference the general conditions of the contract for the construction of buildings. Among the general conditions, and part of the contract, is a clause providing for arbitration of contractual disputes, as follows:

“All disputes, claims or questions subject to arbitration under the Contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of The American Institute of Architects, and the Agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other”.

The agreement further provided that “final payment shall be due 30 days after substantial completion of the work provided the work be then fully completed and the contract fully performed”. (Article 5 of the standard form).

Alternóse substantially completed work on the building on December 4,1965,14 days ahead of schedule and the Tankard Inn was opened for business by McMullin on December 8,1965.

A few days after Alternóse notified McMullin that the building had been completed, Robert F. Linden, McMullin’s architect, prepared a checklist of minor items that were not yet completed. The insignificant irregularities were completed or repaired by Alternóse, but later in December, Roger Alternóse, one of the owners of the business, was notified by Mr. Linden that the roof leaked in several places. Alternóse tried un[523]*523successfully to repair the roof leakage, which was of such small proportions that three or four hours of rain would result in dampness that could be easily sponged away.

While the leak never caused the Tankard Inn to cease operations, McMullin claimed the water leakage and several other minor construction defects gave him the right to refuse payment of the last instalment of the contract price of $12,500.

After five months of unsuccessfully demanding payment of the last instalment from McMullin, Roger Alternóse went to the Tankard Inn on Sunday, June 19, 1966, when the establishment was closed, and removed three air conditioner compressors. The following day, Alternóse called McMullin and informed him that he would not return the air conditioning units unless McMullin directed the bank to release the funds owed Alternóse under the contract. McMullin continued to resist payment, and obtained a writ of replevin for the three compressors. A search by the sheriff of Montgomery County of the Alternóse office and warehouse failed to uncover the units, and Mc-Mullin subsequently purchased three replacements.

Having failed to resolve the dispute, Alternóse on July 14, 1966, filed a complaint in equity, asking the court to “order defendant to name an arbitrator and to proceed diligently under the compulsory arbitration provisions” of the contract. McMullin’s preliminary objections were sustained by the Honorable Robert W. Honeyman, who directed by order dated October 21, 1966 that the action be certified over to the law side of the court. Alternóse took no further steps, however, to advance the prosecution of the suit.

During the pendency of the equity proceeding, Alternóse again attempted to repair the leaking roof. In August, 1966, Alternóse hired a new roofing subcontractor who tore up portions of the old roof with jack[524]*524hammers and installed new roofing material. The new roof continued to leak and McMullin continued to resist payment. Finding resolution of the contractual dispute impossible, Alternóse, on January 31, 1967, instituted a proceeding before the American Arbitration Association to seek recovery of $13,390.10, due under the contract. McMullin resisted the demand for arbitration, contending that the matter was not arbitrable for the following reasons:

1. Court action was still pending;

2. Alternóse had abrogated the arbitration clause by its breach of contract in removing the three air conditioning units from the Tankard Inn.

The American Arbitration Association, after, reviewing the contentions of the parties, ruled that an issue as to arbitration existed which must be determined by an arbitrator. Pursuant thereto, the association scheduled a hearing on June 15 and 16,1967, before an arbitration panel of S. Harry Galfand, attorney; J. Frank Haws, architect; and Paul Restall, general contractor.

At the hearing, McMullin again pressed his contention that the matter was not arbitrable but, in the event that the arbitrators found to the contrary, advanced a counterclaim for expenses and losses by reason of Altemose’s alleged nonperformance of the contract.

Following four hearings, during which almost six hundred pages of testimony were taken, the arbitrators, on December 29, 1967, found that the matter was arbitrable and awarded Alternóse the sum of $12,757.10, plus interest thereon at the rate of six percent per year from January 4, 1966. The counterclaim of McMullin was.denied in its entirety.

On January 29, 1968, McMullin filed a petition for order vacating or in the alternative modifying or correcting an award of arbitrators. On February 1, 1968, the prothonotary, upon praecipe, entered judgment in [525]*525favor of Alternóse for $14,469.09, rendering moot Mc-Mullin’s original petition to vacate the arbitration award. Five days later, McMullin filed a petition to open or strike the aforesaid judgment.

The basis of McMullin’s attack upon the judgment is the argument he has advanced throughout the proceeding — that the arbitrators were without jurisdiction. McMullin contends that Alternóse effected a waiver of the arbitration clause of the contract by engaging in acts inconsistent with arbitrability. More particularly, it is alleged that Alternóse, by its breach of contract in entering the premises of McMullin, and without authorization removing the three compressors, engaged in conduct so antithetical to the contract as to preclude Alternóse from taking advantage of the arbitration clause of the contract.

Both parties agree that the arbitration provision in the contract dictates arbitration at common law rather than statutory arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harwitz v. Selas Corp. of America
178 A.2d 617 (Supreme Court of Pennsylvania, 1962)
Harleysville Mutual Insurance v. Medycki
244 A.2d 655 (Supreme Court of Pennsylvania, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
46 Pa. D. & C.2d 521, 1968 Pa. Dist. & Cnty. Dec. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmullin-enterprises-inc-v-altemose-construction-co-pactcomplmontgo-1968.