McMillen v. Jarmul (In Re Jarmul)

150 B.R. 134, 1993 Bankr. LEXIS 123
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedJanuary 29, 1993
Docket17-10643
StatusPublished
Cited by6 cases

This text of 150 B.R. 134 (McMillen v. Jarmul (In Re Jarmul)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMillen v. Jarmul (In Re Jarmul), 150 B.R. 134, 1993 Bankr. LEXIS 123 (Pa. 1993).

Opinion

*136 MEMORANDUM OPINION

BERNARD MARKOVITZ, Bankruptcy Judge.

Plaintiff Russell McMillen seeks a determination that a debt purportedly owed to him by debtors is not dischargeable pursuant to 11 U.S.C. section 523(a)(2)(A). 1

I

FACTS

Plaintiff is a general contractor and is in the business of constructing houses.

On April 1, 1990, plaintiff and debtor Edward Jarmul (“Mr. Jarmul”) executed an agreement whereby plaintiff was to erect a pre-fabricated building which debtors intended to use as their personal residence. The total contract price was $66,528.00. The pre-fabricated materials to be used by plaintiff were provided by Deck House, Inc. Debtor Eileen Jarmul (“Mrs. Jarmul”) was not a signatory to the agreement.

Both debtors, plaintiff, and Landmark Savings Association (“Landmark”) executed a construction loan agreement on May 22, 1990. Landmark agreed to lend debtors $124,000.00 to finance the project. Plaintiff was to be paid by Landmark in four (4) installments (or “draws”) upon certification that the work for which payment was sought had been completed. The first, draw was in the amount of $9,979.00. The second and third draws, respectively, were in the amount of $19,958.00 each. The fourth draw was in the amount of $16,-633.00. The balance remaining after plaintiff had been paid was to be used to pay Deck House for the materials it supplied.

Plaintiff began working on the project shortly thereafter. When work on the project began to lag behind schedule, plaintiff and Mr. Jarmul orally agreed late in July of 1990 that plaintiff would complete only the structure and the exterior for $41,-362.00 and that Mr. Jarmul personally would complete the interior of the building.

Plaintiff is a customer of W.T. Leggett Company (“Leggett”), a wholesale distributor of kitchens and bathrooms that does business only with contractors. Mr. Jar-mul represented to Leggett that he had been sent by plaintiff and ordered materials from it costing $5,703.20 for use in completing the interior of the house. Mr. Jarmul charged the materials to plaintiffs account with Leggett without plaintiffs permission.

Plaintiff also is a customer of Wattman Supply Company (“Wattman”). Mr. Jarmul represented to Wattman that he had been sent by plaintiff and ordered electrical supplies from it costing $787.00 for use in completing the interior of the house. Mr. Jarmul charged the materials to plaintiffs account with Wattman without plaintiffs permission.

Mr. Jarmul has not paid either Leggett or Wattman for the materials he purchased from them.

On August 9, 1990, Landmark inspected the project and certified that all work required for payment of the first draw had been completed and authorized payment of $9,979.00 to plaintiff. A check in that amount payable to plaintiff was issued on September 4, 1990. Plaintiff negotiated the check shortly thereafter.

Work on the project continued to lag behind schedule. On October 15, 1990, Mr. Jarmul informed plaintiff that he intended to get another contractor to complete the job. It was agreed at that time that plaintiff would be paid $30,000.00 for work he had performed less the cost to have the roof and siding installed by another contractor. It further was agreed that plain *137 tiff would receive the second draw from Landmark and would remit the balance to Mr. Jarmul after plaintiff had been paid for work performed to that point.

When Mr. Jarmul was unable to find another contractor to complete the roof on such short notice, plaintiff and Mr. Jarmul agreed on October 18, 1990 that plaintiff would install the roof and was to be paid $30,000.00 for work performed less the cost to have the siding installed by another contractor. Plaintiff began to install the roof the next day and finished on November 9, 1990.

Mr. Jarmul made arrangements late in October of 1990 to have Hank Kenyon do the siding and other work on the project. Kenyon began working on November 1, 1990.

On November 19, 1990, Mr. Jarmul once again notified plaintiff that he was terminating plaintiff as general contractor. Mr. Jarmul also notified Landmark that all future draws for work on the project were to be made jointly to Mr. Jarmul and to Kenyon.

Landmark inspected the project on November 19, 1990 and certified that all work required for payment of the second draw had been completed and authorized payment. On November 30, 1990, Landmark issued a check payable to Mr. Jarmul and to Mr. Kenyon in the amount of $19,958.00. Plaintiff was not listed as a payee and received nothing from the second draw. Mr. Jarmul paid Kenyon $5,000.00 from the draw and retained the balance of $14,-958.00, ostensibly to complete the interior portion of the dwelling which the parties agreed was no longer the obligation of plaintiff.

Plaintiff received nothing from the third or fourth draws. Kenyon received a portion of these draws while the balance was retained by plaintiff.

Debtors filed a voluntary joint chapter 7 petition on April 14, 1992. Schedule D, Creditors Holding Secured Claims, lists plaintiff and Leggett as holding statutory liens in the amount of $18,500.00 and $5,803.00 respectively.

On July 17, 1992, plaintiff commenced the adversary action which is before the court at this time. Trial on the matter was held on January 6,1993, at which time both sides were permitted to offer any evidence they considered appropriate.

No evidence was offered relating to the propriety of the above-mentioned statutory liens. Accordingly, the court has no basis for determining their legal existence and whether they survive debtors’ discharge.

II

ANALYSIS

Plaintiff asserts that debtors “committed fraud” in two respects. According to plaintiff, debtors fraudulently misrepresented to him when he was rehired on October. 18, 1990 that he would be paid for his services when in fact they had no intention at the time of ever paying him. In addition, plaintiff maintains that debtors “committed fraud” in charging materials purchased from Leggett and Wallman to plaintiffs accounts when they did not have his permission to do so.

Section 523(a)(2)(A) provides in pertinent part as follows:

(a) A discharge under section 727 ... of this title does not discharge any individual from any debt—
(2) for money, property, services, or an extension renewal or refinancing of credit, to the extent obtained by—
(A) false pretenses, a false representation, or actual fraud, other than a statement respecting the debtor’s or an insider’s financial condition ...

11 U.S.C. § 523.

In order for the debts at issue here to be nondischargeable plaintiff must establish that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skinner v. Skinner (In re Skinner)
532 B.R. 599 (E.D. Pennsylvania, 2015)
Coleman v. Miller (Miller)
270 B.R. 303 (D. Kansas, 2001)
Gehlhausen v. Olinger (In Re Olinger)
160 B.R. 1004 (S.D. Indiana, 1993)
Seiler v. Farley (In Re Farley)
156 B.R. 486 (W.D. Pennsylvania, 1993)
Hash v. Reed (In Re Reed)
155 B.R. 169 (S.D. Ohio, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
150 B.R. 134, 1993 Bankr. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmillen-v-jarmul-in-re-jarmul-pawb-1993.