McLeod v. Lee

17 Nev. 103
CourtNevada Supreme Court
DecidedApril 15, 1882
DocketNo. 1105
StatusPublished
Cited by24 cases

This text of 17 Nev. 103 (McLeod v. Lee) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLeod v. Lee, 17 Nev. 103 (Neb. 1882).

Opinion

By the Court,

Hawley, J.:

The action of Lee et al. v. McLeod, 12 Nev. 280, was brought to recover damages for an alleged unlawful diversion of the waters of Walker river by defendant, on or about the fourth of August, 1876, and to enjoin him from diverting the same to the injury of plaintiffs.

The right of plaintiffs to erect and maintain a dam in the .river was dependent upon a parol license claimed to have Been given by the defendant, and, when the cause was tried upon its merits, a judgment was rendered in favor of defendant, and this judgment was affirmed by this court. (15 Nev. 158.)

The present action was instituted, during the pendency of the other suit, by the plaintiff (defendant in the former action), against the defendants (plaintiffs therein), to recover damages for the destruction of his crops and injury to his lands by an overflow of the waters of Walker river, in the months •of June and July, 1876, alleged to have been caused by reason of the wrongful erection and maintenance of the dam by the defendants, and for an injunction. (14 Nev. 398.)

In the case of Lee et al. v. McLeod, there were thirty-three special questions submitted by plaintiffs, and thirty-five by defendant. The jury was unable to answer several of the questions, but all that were answered were favorable to the defendant and justified the judgment rendered therein. The jury, among other things, decided "that the defendant McLeod gave the plaintiffs permission to erect a temporary dam of eighteen inches in height, or sufficient in extent and size to back the water of the river eighteen inches;” that "the understanding was that the plaintiffs should construct a temporary dam of brush, etc., that would wash out at any freshet;” that in case of high water and danger of the defendant’s ranch [111]*111being overflowed, “the plaintiffs should cut the dam, in case it was not washed out;” that at no time between the spring of 1875 and the fourth day of Aug-ust, 1876, “was the dam in question less than three feet in height;” that in the spring of 1875 it was about five feet high, and in the spring of 1876 from four to five feet; that the deposit of sand in plaintiffs’ ditch was occasioned by the dam; that the dam caused “unusual deposits of sand in the channel of Walker river, above said dam,” and thereby occasioned “ an overflow of said defendant’s land;” that “the defendant was the owner in fee of the land described in the answer.”

After the trial and rendition of judgment in Lee et al. v. McLeod, the plaintiff' in this action filed a supplemental complaint alleging the trial and decision in the former action, and,, among other things, averred “that the issues presented in that-case were the same as presented in this case, with the single-exception of the amount of damages;” that the parties to said action * *. * were the same parties in this case; that “the dam and ditch concerning which said adjudication was bad and made in the findings and judgment in said action * * * were, and are, the same dam and ditch as are mentioned and described in the supplemental answer in this cause and in the complaint in this action;” that it was adjudged and determined in said action ‘ ‘ that the said dam * * * was the • cause of the overflow of the plaintiff’s land described in the complaint herein,” and that “the plaintiff was the owner of the real estate'described in the complaint herein.” It is further alleged that ‘ ‘ the time referred to in the complaint in this action, and in the amended answer herein, covers the same period of time as mentioned in the * * * pleadings., in said cause.”

In their answer to this supplemental complaint the defendants denied that the issues in the two suits were the same ; denied “ that there was any-adjudication whatever concerning any dam or ditch belonging or claimed by the defendants in. this action;” denied .“that any question involving said dam or ditch, or defendants’ title thereto, was raised in said action or put in issue therein;” denied that it was. adjudicated or determined therein ‘ ‘ thg,t the said dam was the cause of the [112]*112overflow of plaintiff’slancl described in tire complaint-herein;”’ denied that it was- adjudged that plaintiff “ was-the owner of the real estate described in the complaint herein;” and alleged. “ that in the' said cause the issues presented in this, cause were-not raised, and were not within the scope of the-pleadings in this, action.”

1. The' general principle'that a judgment of a court of competent jurisdiction between the same parties and upon the same issues is, as a plea, a bar, or as evidence conclusive, is-too well settled to require discussion. Such a judgment is not only conclusive of the right which it establishes, but of the-facts which it directly decides.

Whenever a cause has been once fairly tried and finally determined, by a competent tribunal, the same questions, as, between the same parties, ought not to be tried over again.. They should be considered as forever settled.

This rule is necessary for the repose of society. It is in the-interest of the public that there should be an end of litigation.

It is easy to understand the- beneficial results, which flow from a strict observance of this, principle, and to realize the injury which might arise by any relaxation of the rule. In a. proper case for its application, courts of justice ought not to permit the rule to be called in question by any supposed hardship which might exist in any particular case, but should, inflexibly adhere to it, regardless, of consequences.

In the present case- it is argued that the issues- in the former-suit were upon an entirely different subject, and this, argument, is sought to be maintained principally upon the ground that the original complaint in each of these actions describes, the-locus in quo of the dam in question at different points. If there were, in fact, two dams in Walker river, each located as, described in the respective complaints, the argument would have great force. But the evidence shows, that there was but one dam. The plaintiff testified ‘ ‘ that he knew the dam and ditch described in the pleadings, in the case of Lee, Mills and. Mills against McLeod, and also the dam and ditch described-in this- ease, and tliat it is the same dam and ditch described in tbe pleadings in both cases. ”

This, testimony is not controverted by the- record; but, in [113]*113this connection, it is earnestly contended that the court erred in permitting any testimony relative to the identity of the-dam, because there is no ambiguity or uncertainty in the descriptions in the pleadings.

We are, however, of opinion that the ruling of the court, in admitting this testimony, was not prejudicial to the defendants.

In the action of Lee v. McLeod, the point where the dam was erected in Walker river was described in the original complaint as being “ at the quarter section corner, between sections 11 and 12, township 13 north, range 25 east, Mount Diablo base and íperidian.”

In this action it is described, in the original complaint, as being 1 ‘ at or near the southeast corner of the northeast quarter of the northeast quarter of * * * section 10, and on the section line between sections 10 and 11 of said-township and range.”

These points are about one mile apart.

In an amended complaint — erroneously designated as a supplemental complaint- — filed in the action of Lee v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Fogliani
425 P.2d 794 (Nevada Supreme Court, 1967)
Reno Club, Inc. v. Harrah
260 P.2d 304 (Nevada Supreme Court, 1953)
Agricultural Insurance Co. of Watertown v. Biltz
64 P.2d 1042 (Nevada Supreme Court, 1937)
Zasucha v. Allen
51 P.2d 1029 (Nevada Supreme Court, 1935)
Paterson v. Condos
30 P.2d 283 (Nevada Supreme Court, 1934)
Crayne v. Crayne
13 P.2d 222 (Nevada Supreme Court, 1932)
Ross v. Clark County
45 S.W.2d 31 (Supreme Court of Arkansas, 1932)
Silverman v. Silverman
283 P. 593 (Nevada Supreme Court, 1930)
Bralis v. Flanges
199 P. 475 (Nevada Supreme Court, 1921)
McLeod v. Miller & Lux
153 P. 566 (Nevada Supreme Court, 1917)
Fitchett v. Henley
31 Nev. 326 (Nevada Supreme Court, 1909)
State ex rel. Holley v. Boerlin
30 Nev. 473 (Nevada Supreme Court, 1908)
Gulling v. Washoe County Bank
29 Nev. 257 (Nevada Supreme Court, 1907)
Maloney v. King
76 P. 4 (Montana Supreme Court, 1904)
Quinn v. Quinn
74 P. 5 (Nevada Supreme Court, 1903)
Sweeney v. Hjul
49 P. 169 (Nevada Supreme Court, 1897)
Thomson v. Crane
73 F. 327 (U.S. Circuit Court for the District of Nevada, 1896)
Tyler Mining Co. v. Sweeney
54 F. 284 (Ninth Circuit, 1893)
Winter v. Fulstone
21 P. 687 (Nevada Supreme Court, 1889)
Young v. Brehe
19 Nev. 379 (Nevada Supreme Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
17 Nev. 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcleod-v-lee-nev-1882.