McLean Contracting Co. v. Waterman Steamship Corp.

131 F. Supp. 2d 817, 2001 A.M.C. 1975, 2001 U.S. Dist. LEXIS 2179, 2001 WL 214178
CourtDistrict Court, E.D. Virginia
DecidedMarch 1, 2001
DocketCiv.A. 2:00CV525
StatusPublished
Cited by2 cases

This text of 131 F. Supp. 2d 817 (McLean Contracting Co. v. Waterman Steamship Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLean Contracting Co. v. Waterman Steamship Corp., 131 F. Supp. 2d 817, 2001 A.M.C. 1975, 2001 U.S. Dist. LEXIS 2179, 2001 WL 214178 (E.D. Va. 2001).

Opinion

. OPINION & ORDER

DOUMAR, District Judge.

This matter is before the Court on Defendant Waterman Steamship Corporation’s (“Waterman”) Motion for Summary Judgment. For the reasons that follow, Defendant’s motion is DENIED.

I. Factual and Procedural Background

In 1998, Plaintiff McLean Contracting Company (“McLean”), acting pursuant to a contract with the State of North Carolina, replaced the Newport River Railroad Bridge in Morehead City, North Carolina. Specifically, McLean replaced the old wooden trestle and track support with a new structure consisting of concrete piles, a pre-cast concrete cap, and a pre-stressed concrete superstructure unit to support the new track. The old wooden trestle was replaced in sections. Unfortunately for McLean, a portion of this work took place during the height of the Atlantic hurricane season, and, from August 26 through August 28, Hurricane Bonnie struck the coast of North Carolina, including the Port of Morehead City. On August 27, at the height of the hurricane, a barge owned by Waterman broke free from its moorings in the Port of Morehead City and allided with McLean’s work-in-progress on the trestle. In the instant lawsuit, McLean alleges that Waterman was negligent in its control and care of the barge, causing the barge to break free from its moorings and damage the work-in-progress on the trestle.

As a result of the allision, McLean expended $17,562.33 in labor, materials, and equipment to repair damage to newly installed concrete T-beams on the trestle. At the time of the allision, McLean’s work on the Newport River Railroad Bridge project was not completed, accepted, or paid for by the State of North Carolina. In addition, although it is undisputed that McLean did not own the trestle, McLean’s contract with the State included a provision entitled “Contractor’s Responsibility for Work,” § 107-18, which stated that McLean shall have “charge and care” of the project and shall “rebuild, repair, restore, and make good all injuries or damages to any portion of the work” before final acceptance by the State, unless such damage was caused by an Act of God, in which case the State agreed to subsequently reimburse McLean for the cost of said repairs. See Rich Aff. ¶ 5, Pl.’s Ex. B. 1

On July 18, 2000, McLean filed the instant suit against Waterman to recover its repair costs of $17,562.33. McLean alleges that Waterman was negligent under the circumstances, thereby causing the allision. Waterman answered raising various defenses, including Act of God. On January 31, 2001, Waterman filed the instant motion, seeking to dismiss this case on the grounds that McLean has no ownership *819 interest in the Newport River Railroad Bridge and thus does not have standing to sue for the costs of repairs necessitated by the allision of Waterman’s barge with McLean’s work-in-progress regardless of any alleged negligence on the part of Waterman. McLean answered Waterman’s motion on February 12, 2001, and Waterman filed its rebuttal memorandum on February 15, 2001. Accordingly, the issues raised by Waterman’s Motion for Summary Judgment have been fully briefed and the matter is now ripe for disposition.

II. Summary Judgment Standard

Rule 56(c) of the Federal Rules of Civil Procedure provides that summary judgment should be granted where “the pleadings, depositions [and] answers to interrogatories ... show that there is no genuine issue as to any material fact and that the moving party is entitled to summary judgment as a matter of law.” The Supreme Court has construed Rule 56(c) to “mandate the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an essential element to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The Celotex Court explained that, “[i]n such situation, there can be no genuine issue as to any material fact, since a complete failure of proof concerning an essential element of the nonmoving party’s case renders all other facts immaterial.” Id. at 323, 106 S.Ct. 2548; see also Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 254, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The nonmoving party must demonstrate that there are specific facts that would create a genuine issue for trial. See Anderson, 477 U.S. at 250, 106 S.Ct. 2505. ‘Where ... the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, disposition by summary judgment is appropriate.” United States v. Lee, 943 F.2d 366, 368 (4th Cir.1991).

III. Analysis

In the case at bar, the material facts necessary to adjudicate the instant motion are not in dispute. Rather, the instant motion presents the legal issue of whether, in admiralty, a contractor has standing to bring suit against an alleged tortfeasor for damages caused to a trestle that is not owned by the contractor but is in the contractor’s charge and care and over which the contractor has a duty to make repairs for any damage. 2 Waterman, citing the U.S. Supreme Court’s decision in Robins Dry Dock & Repair Co. v. Flint, 275 U.S. 303, 48 S.Ct. 134, 72 L.Ed. 290 (1927), asserts that under general maritime law a party cannot recover damages in tort for purely economic losses sustained as a result of damage to property owned by another person. McLean, in response, argues that the rationale of Robins Dry Dock does not apply to the case at bar due to the fact that McLean had a sufficient proprietary interest in its work-in-progress so as to have standing to sue Waterman for its repair. Since the resolution of this issue turns on the scope of the Supreme Court’s decision in Robins Dry Dock, the Court’s analysis necessarily begins with a discussion of that case.

A. The Robins Dry Dock Decision

In Robins Dry Dock, the Supreme Court held that where a vessel was placed in dry dock for repairs, and the repairs were delayed due to the negligence of the shipyard, the vessel’s time charterer did not have a cause of action against the shipyard for profits that would have been earned but for the shipyard’s negligence and delay. See id. at 308, 309, 48 S.Ct. *820 134. The Robins Dry Dock Court attempted to restrict the recovery of damages in admiralty so that potential claims are not limitless. Importantly, the claimant in Robins Dry Dock

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G & G Steel, Inc. v. Sea Wolf Marine Transportation, LLC
380 F. App'x 103 (Second Circuit, 2010)
Maersk Line Ltd. v. Care
271 F. Supp. 2d 818 (E.D. Virginia, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
131 F. Supp. 2d 817, 2001 A.M.C. 1975, 2001 U.S. Dist. LEXIS 2179, 2001 WL 214178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclean-contracting-co-v-waterman-steamship-corp-vaed-2001.