McLaughlin v. Emera Maine

Superior Court of Maine·Decided February 17, 2017·No. CUMbcd-cv-15-14·Unpublished

Opinion

STATE OF MAINE BUSINESS AND CONSUMER COURT Cumberland, ss.

JAY McLAUGHLIN, Plaintiff

V. Docket No. BCD-CV-15-14

EMERA MAINE, f/k/a Bangor Hydro-Electric Company, and HAWKEYE, LLC

Defendants

DECISION

This case involves an action by Jay McLaughlin ["Plaintiff' or "Mr. McLaughlin"], the owner of a large woodlot in Greenbush, Penobscot County, Maine, against Emera Maine ["Emera"], an electric utility company, and Hawkeye, LLC ["Hawkeye"], Emera's construction contractor, for damages arising out of injury and loss to roads, land, trees and vegetation on Plaintiffs property.

Plaintiff McLaughlin's Amended Complaint asserts six counts against both Defendants, except where indicated: Count I (Breach of Contract, License Agreement) against Emera only; Count II (Negligence); Count III (Injury to Land -- 14 M.R.S.A. §7552); Count IV (Trespass -­ 14 M.R.S.A. §7551-B); Count V (Promissory Estoppel -Breach of Contract), and Count VI (Defendants regarding building of the "Spur Road" -Trespass).

Both Defendants answered, denying liability and asserted affirmative defenses. In addition, Emera Maine filed a cross-claim against Hawkeye, asking that Hawkeye indemnify Emera against any damages assessed against Emera and for Emera's attorney's fees and costs incurred in the defense of this action.

As a result of Defendants' motions for summary judgment, Hawkeye was granted summary judgment on the breach of contract claim in Count I of the Amended Complaint, and both Defendants were granted summary judgment on the promissory estoppel claim in Count V. The remaining counts went to trial.

The case was tried to the court over the course of nine days in April 2016, with part of one trial day dedicated to a view of the property. The parties together submitted hundreds of exhibits in binders occupying a half dozen file boxes, most of which were admitted into evidence. After the trial, the parties submitted a total of 184 pages of proposed findings of fact and conclusions of law and responses to each other's post-trial filings. The last filing is dated June 17, 2016, at which point the court took the case under advisement.

Based on the entire record, the court hereby adopts the following findings of fact and conclusions oflaw and renders judgment on the Amended Complaint and Emera's Cross-claim as set forth below. Unless otherwise stated, all findings are made based on a preponderance of the evidence.

Background efthe Parties and the Property 1. Plaintiff Jay McLaughlin is the owner of a S,200-acre parcel of mixed forest land located in Greenbush, Maine ("the Property" ). Mr. McLaughlin also owns and operates a commercial logging company as well as a commercial mill.

2. Defendant Emera is the owner of a transmission line, known as Line 64, located in a corridor running through the Property. Defendant Hawkeye is a utility construction company engaged by Emera to rebuild the Line 64 transmission line.

S. The Property was purchased by Mr. McLaughlin from the Greenbush Timber Company on December S 1, 1997 for $490,000.00. At the time of the purchase, a number of established unpaved wood roads were used to access the Property in conjunction with forest

harvesting operations. One of these, the Taylor Road, runs most of the length of the Property and has been the main means of vehicle access over the property.

4. Access to the Property from the nearest public road is over a 1,400-foot approach road owned by the Town of Greenbush. It runs from the public road and connects with the Taylor Road at Mr. McLaughlin's northern property boundary. Mr. McLaughlin has a deeded easement to use the Town's approach road to go between the Property and the public road.

5. After pmchasing the Property in 1997, Mr. McLaughlin made a number of improvements, including rebuilding Taylor Road, using proper materials, ditches and crowning.

6. Mr. McLaughlin also engaged in extensive harvesting of wood on the Property.

According to Chris Stevens, Plaintiffs forestry expert, Plaintiff harvested wood on about half of the acreage on the Property between 2001 and 2009, leaving timber still standing on the Property with an approximate market value of $626,000 as of 2009. Aerial photographs of the Property indicate forestry harvesting operations had taken place to varying degrees throughout the Property, leaving a network of skidder trails. Defendant Hawkeye Exhibits 66, 67 and 69.

7. Before any of the events g1vmg nse to this dispute, the past logging activities conducted by the Plaintiff on the Property involved environmental violations that resulted in the imposition of fines and penalties by the Maine Department of Environmental Protection. (Defendant Hawkeye Exhibits 5, 6, 7 and 8). However, none of the environmental violations that apparently occurred during the Plaintiffs logging activity prior to 2011 has any material bearing on the issues presented, so they are not considered further.

8. The main means of access across the Property, Taylor Road, was a seasonal dirt and gravel road capable of supporting heavy equipment only during summer months and

winter months. Taylor Road was unusable by trucks and other heavy vehicles during spring mud season and the fall rainy season.

9. As of 2011, the road had not been compacted through five freeze/thaw cycles. As a result of the lack of compaction, the passage of vehicles had begun to displace the road material toward the center and to erode the shoulder of the road in places. There were depressions that resulted in puddling during rainy periods and spring thaw. In other words, the Taylor Road was in reasonably good condition, but not excellent condition, as of the beginning of 2011.

The Line 64 Rebuild Project and the SOCA 10. At the time of the events described herein, Emera Maine was known as Bangor Hydro-Electric Company (BHE). Sometime before February 2010, BHE decided to undertake an upgrade to its electrical service by rebuilding the Line 64 transmission line. The project became known as "the Line 64 Rebuild Project."

11. The project consisted of the rebuilding of the existing transmission line for a distance of 44 miles from Veazie to Chester and included the installation of more than' .300 new towers as well as associated conductors and hardware.

12. BHE's principal contractor for the Line 64 Rebuild Project was Hawkeye. On or about February 12, 2010, Hawkeye and BHE entered into a Supplier of Choice Agreement ("SOCA") delineating the terms and conditions of the work to be performed by Hawkeye in connection with the Line 64 Rebuild Project. Defendant Emera Maine 1s Exhibit .32 .

1.3. The SOCA between BHE and Hawkeye stated, among other things, that

1[Hawkeye] agrees to adhere to and comply with [BHE 1s] Environmental Guideline for 1

Construction and Maintenance Activities on Transmission Line and Substation projects ... adhere to and comply with the Environmental Specifications for Line 64 Rebuild ... [and] be responsible for ensuring all employees, sub-suppliers, agents and representatives of [Hawkeye]

comply with all federal, state and local health, safety and environmental statutes, regulations, policies, guidelines and all health, safety and environmental rules as prescribed by [BHEJ." Defendant Emera Maine's Exhibit 32 at 6.

14. By virtue of entering in the SOCA with BHE, Hawkeye committed itself to following specific standards and requirements in a variety of areas, including safety and environmental protection, and to "promptly correct defective deficiencies in products and services" in the course of its work on the Line 64 Rebuild Project.

15. The SOCA also required Hawkeye to use approved access roads in order to move equipment and materials to the transmission line where the work was to be performed.

Free access — add to your briefcase to read the full text and ask questions with AI

McLaughlin v. Emera Maine, (Me. Super. Ct. 2017).

McLaughlin v. Emera Maine (McLaughlin v. Emera Maine) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Langley v. Pacific Indemnity Co.
217 S.E.2d 369 (Court of Appeals of Georgia, 1975)
Long v. Jim Letts Oldsmobile, Inc.
217 S.E.2d 602 (Court of Appeals of Georgia, 1975)
Devine v. Roche Biomedical Laboratories, Inc.
637 A.2d 441 (Supreme Judicial Court of Maine, 1994)
In Re Estate of Lipin
2008 ME 16 (Supreme Judicial Court of Maine, 2008)
Medeika v. Watts
2008 ME 163 (Supreme Judicial Court of Maine, 2008)
Wandishin v. Wandishin
2009 ME 73 (Supreme Judicial Court of Maine, 2009)
Poussard v. Commercial Credit Plan, Incorporated of Lewiston
479 A.2d 881 (Supreme Judicial Court of Maine, 1984)
Robert Flaherty v. Helen Muther
2013 ME 39 (Supreme Judicial Court of Maine, 2013)
Patricia Grant v. Foster Wheeler, LLC
2016 ME 85 (Supreme Judicial Court of Maine, 2016)
Marie J. (Marchiori) Eremita v. Cristiano A. Marchiori
2016 ME 160 (Supreme Judicial Court of Maine, 2016)
4-One Box Machine Makers v. Wirebounds Patents Co.
163 A. 167 (Supreme Judicial Court of Maine, 1932)
DeCambra v. Carson
2008 ME 127 (Supreme Judicial Court of Maine, 2008)
Cookson v. Liberty Mutual Fire Insurance
2012 ME 7 (Supreme Judicial Court of Maine, 2012)