MCKNIGHT CONSTRUCTION COMPANY INC v. SURECRETE LLC

CourtDistrict Court, M.D. Georgia
DecidedSeptember 26, 2025
Docket7:24-cv-00112
StatusUnknown

This text of MCKNIGHT CONSTRUCTION COMPANY INC v. SURECRETE LLC (MCKNIGHT CONSTRUCTION COMPANY INC v. SURECRETE LLC) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCKNIGHT CONSTRUCTION COMPANY INC v. SURECRETE LLC, (M.D. Ga. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF GEORGIA VALDOSTA DIVISION

MCKNIGHT CONSTRUCTION : COMPANY, INC., : : Plaintiff, : : v. : CASE NO.: 7:24-CV-112 (LAG) : SURECRETE, LLC and FRONTIER : BONDING SERVICES, LLC d/b/a THE : SURETY GROUP AGENCY f/k/a : LEXON INSURANCE COMPANY, : : Defendants. : : ORDER Before the Court is Defendant Lexon Insurance Company’s Motion to Dismiss. (Doc. 14). For the reasons below, Defendant’s Motion is GRANTED. BACKGROUND The dispute in this case arises from a contract between Plaintiff McKnight Construction Company Inc., and the United States Army Corps of Engineers (USACE) and a related subcontract with Defendant SureCrete LLC (SureCrete).1 (Doc. 5 ¶¶ 1, 8). Defendant Lexon Insurance Company (Lexon) acted as the Surety on a related performance bond. (Id. ¶ 10). On or about September 2020, USACE issued a Request for Proposal for constructing a combined hangar/HMU facility and aircraft parts store at Moody AFB (the Project). (Id. ¶ 6). Plaintiff bid on and received the contract award for $23,606,712.00. (Id. ¶ 7). On October 13, 2020, Plaintiff, as the general contractor, awarded a subcontract to Defendant SureCrete. (Id. ¶¶ 1, 8; Doc. 5-1). On March 1, 2021, the subcontract was fully executed for $3,405,000.00. (Doc. 5 ¶ 8). During performance, Plaintiff issued additional

1 On a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), the Court accepts all facts alleged in Plaintiff’s Amended Complaint (Doc. 5) as true. See Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555–56 (2007); Anderson v. Wilco Life Ins., 17 F.4th 1339, 1344 (11th Cir. 2021) (citation omitted). orders to Defendant SureCrete, “increasing the subcontract value to $6,248,383.82.” (Id. ¶ 13). The scope of Defendant SureCrete’s work included “demolition, erosion control, site utilities (water/sewer/storm), asphalt paving and stone, concrete paving and stone, and building concrete including stone.” (Id. ¶ 9). The contract between Plaintiff and Defendant SureCrete required Defendant SureCrete to “provide payment and performance bonds for the Project[,]” and Defendant Lexon “provided Performance Bond No. LICX1166556 for $3,335,000.00.” (Id. ¶ 10; Doc. 5-2). The Performance Bond provides, in pertinent part, Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligation under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. (Doc. 5-2 at 4 ¶ 11). The subcontract “detailed the default termination procedure[.]” (Doc. 5 ¶ 12). In the event of a default, Plaintiff could complete the work at Defendant SureCrete’s expense and “would receive its actual costs plus 15% as overhead and profit.” (Id.). Article 6.1 of the subcontract provides, in relevant part: Except as otherwise provided in the Subcontract, in the event that [Defendant SureCrete] fails to comply[] . . . with the provisions herein as to character or time of performance, and the failure is not corrected within 24 hours after written notice by [Plaintiff] to [Defendant SureCrete], [Plaintiff], may, without prejudice to any other right or remedy against [Defendant SureCrete] or its surety, [Defendant Lexon,] take over and complete the performance of this Subcontract, or any part of it, at the expense of [Defendant SureCrete], or without taking over the work, may furnish the necessary materials and/or employ the workmen necessary to remedy the situation at the expense of [Defendant SureCrete]. (Doc. 5-1 at 20). Plaintiff alleges that during performance, Defendant SureCrete breached the subcontract by failing to “complete approved submittals, . . . complete daily reports, . . . maintain certified payroll records, . . . provide compliant materials, . . . properly manage the Project to advance the work, . . . provide qualified superintendents and quality controls, and . . . maintain a schedule.” (Doc. 5 ¶¶ 14, 15). Because Defendant SureCrete was not paying its vendors, vendors delayed or refused performance, and Plaintiff decided to pay Defendant SureCrete’s vendors directly to continue advancing the Project. (Id. ¶¶ 16–17). On July 29, 2022, Plaintiff provided notice of the deficiencies to Defendant SureCrete and requested that it “cure and resolve the issues.” (Id. ¶ 18). When Defendant SureCrete failed to do so, Plaintiff terminated Defendant SureCrete on October 25, 2022, for default pursuant to Article 6.1 of the subcontract. (Id. ¶ 19; Doc. 5-3; see Doc. 5-1 at 20). That same day, Plaintiff sent a Bond demand to Defendant Lexon, notifying Defendant Lexon that Defendant SureCrete was terminated and demanding that Defendant Lexon complete Defendant SureCrete’s remaining scope of work. (Doc. 5 ¶ 20; Doc. 5-4). Plaintiff did not receive a substantive response to its Performance Bond demand. (Doc. 5 ¶ 21). As of October 25, 2022, Plaintiff had paid Defendant SureCrete $3,687,491.82 for the work completed. (Id. ¶ 22). Plaintiff paid an additional $3,584,619.82 to Defendant SureCrete’s former subcontractors to continue the work. (Id. ¶¶ 23, 27). The total cost to complete the Project with the contractual overhead, minus the balance of funds, resulted in completion costs of $5,019,887,52, not including additional project management time, supervision, and delays. (Id. ¶¶ 25–26). Plaintiff alleges that Defendant Lexon, “as the surety, was obligated to either complete the work, obtain bids for completion secured by the bonds, or pay [Plaintiff] the amounts over the contract balance.” (Id. ¶ 35). Plaintiff further alleges that Defendant “Lexon failed and refused to provide a timely response to [Plaintiff’s] termination notice, default notice, and demand for performance.” (Id. ¶ 36). Thus, Plaintiff maintains that Defendant Lexon is “in breach of the performance bond requirements[.]” (Id. ¶ 38). On October 24, 2024, Plaintiff filed an initial complaint against Defendant SureCrete and Defendant Lexon. (Doc. 1). On November 21, 2024, Plaintiff filed an Amended Complaint, which is identical to the original complaint with the exception of paragraph 3. (See Doc. 5). Paragraph 3 in the original complaint states: “Plaintiff is informed and believes that Lexon Insurance Company (“Lexon’’) is a foreign corporation with a principal place of business in Tennessee and is in the surety and insurance business[;]” whereas Paragraph 3 in the Amended complaint states: “Frontier Bonding Services, LLC d/b/a The Surety Group Agency f/k/a Lexon Insurance Company (“Lexon”) is a Texas Corporation that may be served through its registered agent, CSC Lawyers Incorporating Service Company, 211 E. 7th Street, Suite 620, Austin, TX 78701. Its principal place of business is 155 NE 100th Street, Suite 201, Seattle, WA 98125.” (Doc. 1 ¶ 3; Doc. 5 ¶ 3). Service of the Amended Complaint was perfected on November 26, 2024. (Doc. 18). The original complaint was never served. (See Docket; Doc. 24 at 3). On January 14, 2025, Defendant Lexon filed the subject Motion to Dismiss. (Doc. 14). After requesting and receiving an extension, Plaintiff responded on February 11, 2025. (Docs. 22, 24; see Docket). Defendant Lexon replied on February 25, 2025. (Doc. 27). Thus, the Motion to Dismiss is now ripe for review. See M.D. Ga. L.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Prime, Inc.
602 F.3d 1276 (Eleventh Circuit, 2010)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Ragan v. Merchants Transfer & Warehouse Co.
337 U.S. 530 (Supreme Court, 1949)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Diana Arias v. Joseph T. Cameron
776 F.3d 1262 (Eleventh Circuit, 2015)
Vanessa Anderson v. Wilco Life Insurance Company
17 F.4th 1339 (Eleventh Circuit, 2021)
McFarland v. McFarland
105 S.E. 596 (Supreme Court of Georgia, 1921)
George v. Southern Railway Co.
218 S.E.2d 447 (Court of Appeals of Georgia, 1975)
Moody v. Gilliam
637 S.E.2d 759 (Court of Appeals of Georgia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
MCKNIGHT CONSTRUCTION COMPANY INC v. SURECRETE LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcknight-construction-company-inc-v-surecrete-llc-gamd-2025.