McKenzie v. United States

96 F. Supp. 944, 119 Ct. Cl. 435, 1951 U.S. Ct. Cl. LEXIS 41
CourtUnited States Court of Claims
DecidedMay 1, 1951
DocketNo. 48999
StatusPublished
Cited by2 cases

This text of 96 F. Supp. 944 (McKenzie v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKenzie v. United States, 96 F. Supp. 944, 119 Ct. Cl. 435, 1951 U.S. Ct. Cl. LEXIS 41 (cc 1951).

Opinion

Howell, Judge,

delivered the opinion of the court:

The defendant has demurred to the plaintiff’s petition on the ground that it does not state facts sufficient to constitute a cause of action and has filed a counterclaim.

Plaintiff, as trustee in bankruptcy for the Graves-Quinn Corporation, brings this action against the United States under the War Contract Hardship Claims Act, otherwise known as the Lucas Act.1 Plaintiff’s petition and the accompanying exhibits which were made a part thereof, allege that on September 14, 1940, the Graves-Quinn Corporation entered into a lump-sum contract with the United States for the construction of temporary housing facilities at various locations in Massachusetts, Maine, and Khode Island (Contract No. W6101 qm-131 O. I. No. 66). The contract was duly completed and the work finally accepted by the Government in February 1941. At the conclusion of the contract some 11 claims were submitted by the contractor to the contracting officer, including the claim here in suit of $366,-640.20, which claim plaintiff alleges is of the character contemplated by the Lucas Act.2

[438]*438In support of its demurrer, defendant makes two contentions: (1). That the requests for equitable relief filed by the contractor with the contracting agency were dated prior to the passage of the First War Powers Act of December 18, 1941,3 and, therefore, could not have been claims which sought a remedy under that Act; (2) that m any event the request made by the contractor was for an increase in the contract price as a matter of right under the contract and not for the extra-legal relief contemplated by the First War Powers Act and the Lucas Act, citing Fogarty v. United States, decided by the Supreme Court on November 6,1950.4

With respect to the defendant’s first contention, it is true that the contractor’s original requests for relief with respect to the matter in suit were made prior to the effective date of the First War Powers Act. However, neither the First War Powers Act nor the Lucas Act specifically requires that requests for relief must have been filed after December 18, 1941, the date of the passage of the First War Powers Act. The First War Powers Act refers to contracts “heretofore [439]*439or hereafter made.” Executive Order 9001 (December 27, 1941, 6 F. It. 6787) implementing that Act, provides in part:

3. The War Department, the Navy Department, and the United States Maritime Commission may by agreement modify or amend or settle claims under contracts heretofore or hereafter made * * *. Amendments and modifications of contracts may be with or without consideration and may be utilized to accomplish the same things as any original contract could have accomplished hereunder, irrespective of the time or circumstances of the making of or the form of the contract amended or modified, or of the amending or modifying contract, and irrespective of rights which may have accrued under the contract, or the amendments or modifications thereof.

With respect to the Lucas Act, the only requirements regarding the time when the request for relief must have been filed are that the request must have been filed on or before August 14, 1945, and be with respect to work, supplies, or services furnished between September 16,1940, and August 14,1945, The work and services set forth in the contract were furnished by the contractor within the time specified in the Lucas Act and the requests for relief were filed prior to August 14,1945. In view of the fact that the First War Powers Act specifically contemplated relief under contracts “heretofore made,” i. e., prior to December 18,1941, and the Lucas Act refers to work performed after September 16,1940, we believe that the contractor’s requests for relief dated October 25,1940, November 11, 1940, and April 18, 1941, attached to plaintiff’s petition, relating as they did to work performed after September 16, 1940, were timely and could have been considered undei either act unless they were defective in some other respect.

In any event, two further requests for relief are attached to plaintiff’s petition with respect to this same matter, which were made subsequent to the passage of the First War Powers Act. On December 30,1941, the attorneys for the trustee in bankruptcy of the contractor wrote to the Chief of Engineers stating that they had received on behalf of the trustee various claims made by the contractor, including the one now in issue; that they had been directed by the court to continue attempts to make adjustment of those claims; that an appointment was desired with officials in Washington for the [440]*440purpose of obtaining “just consideration of the claims.” On May 12, 1942, the same attorneys wrote to the Secretary of War appealing from the contracting officer’s denial of Claim No. 11 (the claim in suit) and Claims Nos. 1 and 4 (in part), asking that a review of the claims be made “to the end that an equitable adjustment may be allowed.” The letter further states that the detailed basis of the claims had previously been set forth in full. It is our opinion that these two letters renew the requests previously made and incorporate by reference the matters referred to in the letters written prior to December 18,1941, so that even under defendant’s view of the case these requests were timely.

We now come to defendant’s second contention that the relief requested by the contractor was not the sort of extralegal relief contemplated by the First War Powers Act and held by the Supreme Court in the Fogarty decision to be a prerequisite to relief under the Lucas Act. The Graves-Quinn contract was a lump-sum building construction contract. After the bids were accepted, but prior to the commencement of work thereunder, the Government let a number of cost-plus-a-fixed-fee contracts in the immediate vicinity of the Graves-Quinn project. Because of the “cost-plus” nature of their contracts, these contractors were able to offer employment to local labor with the guarantee of considerable overtime, thus drawing that labor away from Graves-Quinn whose fixed-price contract only permitted a limited amount of overtime pay. The “cost-plus” contractors had a similar advantage in the materials market. In order to meet the competition thus created and to complete its work according to the contract, Graves-Quinn incurred considerable excess labor and material costs over and above the amount contemplated in its bid, and it was for the resulting loss that the contractor requested relief. According to plaintiff’s petition, at least two requests for relief from this condition were made during the course of the contract on October 25 and on November 11, 1940. Copies of these letters to Chief of Construction in the Quartermaster General’s Office are not attached to the petition,5 but the decision of the War Contract [441]*441Hardship Claims Board for the Army (made a part of plaintiff’s petition) characterizes these letters as advices to the Chief of Construction that plaintiff was losing money on the contract. In a letter to the War Department dated April 4, 1941 (attached to the petition), after the contract had been completed, Graves-Quinn described the above events and made the following statement with respect to its claim:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Depew Paving Co. v. United States
104 F. Supp. 94 (Court of Claims, 1952)
Humphrey v. United States
101 F. Supp. 759 (Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
96 F. Supp. 944, 119 Ct. Cl. 435, 1951 U.S. Ct. Cl. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckenzie-v-united-states-cc-1951.