McKenzie v. Neale Construction Co.

294 P.2d 355, 75 Wyo. 175, 1956 Wyo. LEXIS 9
CourtWyoming Supreme Court
DecidedFebruary 28, 1956
Docket2700
StatusPublished
Cited by5 cases

This text of 294 P.2d 355 (McKenzie v. Neale Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKenzie v. Neale Construction Co., 294 P.2d 355, 75 Wyo. 175, 1956 Wyo. LEXIS 9 (Wyo. 1956).

Opinion

*179 OPINION

Blume, Chief Justice.

Allen McKenzie and Farrin Frazier, doing business as F & M Ready Mix Concrete Company, hereinafter referred to as plaintiffs, brought this action against Neale Construction Company, Inc., hereinafter referred to as defendant.

Plaintiffs alleged that they were residents of Casper, Wyoming, and that defendant was a Kansas corpora *180 tion, authorized to do business in Wyoming-; that between the dates of November 5, 1952 and February 3, 1953, defendant, through its duly constituted agent, Orvel Curns, ordered and took delivery of ready-mix concrete and chloride of the fair and reasonable market value of |2962.95 which, after crediting $1049.25 left a balance allegedly due plaintiffs from defendant of $1913.70.

Defendant answered, denying the allegations of the petition, except as to the status of the parties, and alleged that Curns was performing concrete work for the construction of sidewalks along CY Avenue in Casper as a subcontractor of the defendant who had the contract for laying telephone lines and cable necessitating the replacement of such sidewalk; that upon partial completion of such subcontract and in accordance therewith, defendant mistakenly paid to plaintiffs $1649.25, while the contract provided for joint payment to plaintiffs and Curns; that Curns failed to complete his contract and left the job; that part of the construction Curns had done was defective and was rejected; and defendant was compelled to expend $2526.89 to rectify the defalcation of Curns which was in addition to the aforementioned payment on the subcontract of $1649.25.

Plaintiffs generally denied the allegations of the answer in their reply and filed a demand for jury. The action came on for trial before the court, sitting with a jury, on November 30, 1954. Motions for a directed verdict were made by defendant at the close of the evidence of plaintiffs and at the close of all the evidence, both were overruled. The jury returned a verdict in favor of plaintiffs and against the defendant in the amount of $1913.70. Defendant filed a motion for judgment, notwithstanding the verdict, which was overruled by the court. Judgment was entered by the court. Defendant filed its motion for a new trial which was *181 overruled by the court upon the condition that plaintiffs file a remittitur in the amount of $600 which was done. From the judgment, the defendant has appealed to this court by direct appeal.

The facts are substantially as follows: Defendant had a contract with Mountain States Telephone and Telegraph Company to put a conduit under the sidewalks along CY Avenue in Casper. That operation necessitated the tearing up and replacing the sidewalks. Curns wanted that job and contacted McKenzie, one of the plaintiffs, to see about getting cement for it. McKenzie told Curns that plaintiffs would have to have something from defendant to the effect that defendant would pay for the concrete. Curns thereupon entered into a contract with defendant and later took the contract to McKenzie. The contract is as follows:

“This agreement entered into this 5th day of November, 1952, between Orvel Curns, Cement Finisher, Neale Construction Company, hereinafter called Owner, and represented under this contract by Neale Construction Company, shall read as follows:
“The cement finisher agrees to handle, place and finish all concrete, and set all forms required of the City of Casper for the project at Casper, Wyoming, for the sum of $3298.50. This contract is for the finishing of 15, 970 sq. ft.
“It is further agreed that the cement finisher agrees to do this work in a workmanlike manner, and unless satisfactory work is being performed, this contract shall be in force for the entire project. If work is found to be unsatisfactory, then the Owner reserves the right to cancel this contract.
“The Owner agrees to do all grading and covering of concrete if necessary. If calcium chloride is necessary, the Neale Construction agrees to pay for it at the rate of 70c per yard of concrete.
“The Neale Construction Company will pay one half of the contract price on the completion of three blocks. The Neale Construction Company shall make the pay *182 ments payable to The F. & M. Ready-Mix Concrete Company and Orvel Curns jointly.
“/s/ Orvel Curns
Orvel Curns, Cement Finisher
The Neale Construction Company
By /s/ Edwin Westwick
Supt. for Neale Construction Co.”

Before any concrete was delivered, McKenzie had a conversation with Westwick, defendant’s superintendent. McKenzie told Westwick that plaintiffs would look to defendant for payment under the contract. Some detailed facts in this connection will be mentioned later. All of the cement delivered to the sidewalk job was ordered by Curns. A log of truck deliveries of concrete was kept by plaintiffs showing when and where each load went. The log shows delivery of the cement to Curns designated as “purchaser” on the CY sidewalk. The delivery tickets show the concrete in question was delivered to Orvel Curns. No statements were signed or received by Westwick from plaintiffs, nor did defendant ever receive any invoices or billings from plaintiffs. When half of the work was completed, Curns billed the defendant for $1649.25, according to the contract. This included the amount then due the plaintiffs, as well as the amount due Curns for his part of the work. The statement for this amount was sent to the home office of defendant. The bookkeeper made out a check for the foregoing amount, but by mistake made it payable to plaintiffs instead of making it payable to the plaintiffs and to Curns jointly as provided in the foregoing contract. The check was sent to West-wick who delivered it to Curns. Curns delivered it to McKenzie. McKenzie almost sent the check back because it was not according to the agreement and might mess up plaintiff’s books. McKenzie had Curns endorse the check and gave him the difference between the amount of the check and the concrete then delivered *183 to that time. Plaintiffs paid Curns $600 out of the check received. Curns’ brother and one or two other men were employed on the sidewalk job. These men were not hired by defendant, discharged by defendant nor paid by defendant. Neither Westwick nor anyone in the employment of defendant supervised the work of Orvel Curns. Westwick was occasionally present when the concrete was delivered. His duties were grading, making ditch and laying line; he was on the front end of the job. Curns did not complete his job, but abandoned it between February 1 and 10. Part of his job was unfinished when he left and the city turned down part of the job for poor workmanship. There was a defect in the concrete furnished. It was a very poor mix. Defendant spent $2526,89, in addition to the aforementioned payment of $1649.25, to complete the contract of Orvel Curns and lost money on the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roussalis v. Wyoming Medical Center, Inc.
4 P.3d 209 (Wyoming Supreme Court, 2000)
Toland v. Key Bank of Wyoming
847 P.2d 549 (Wyoming Supreme Court, 1993)
BHP Petroleum Co., Inc. v. Okie
836 P.2d 873 (Wyoming Supreme Court, 1992)
Flying J, Inc. v. Booth
773 P.2d 144 (Wyoming Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
294 P.2d 355, 75 Wyo. 175, 1956 Wyo. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckenzie-v-neale-construction-co-wyo-1956.