McKenzie v. Jacob

27 Ohio N.P. (n.s.) 57
CourtCourt of Common Pleas of Ohio, Hamilton County
DecidedJanuary 15, 1928
StatusPublished

This text of 27 Ohio N.P. (n.s.) 57 (McKenzie v. Jacob) is published on Counsel Stack Legal Research, covering Court of Common Pleas of Ohio, Hamilton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKenzie v. Jacob, 27 Ohio N.P. (n.s.) 57 (Ohio Super. Ct. 1928).

Opinion

Struble, J.

The plaintiff claims a mechanic’s lien upon the premises of the defendants, fully described in the petition, in the sum of $920, for labor and material for brick work in the construction of the dwelling upon the said premises.

The plaintiff was the sub-contractor as to this work of one Joseph I. Phillips, who was under contract with the defendants, Louis and Hilda Jacobs, to construct said dwelling according to certain plans and specifications, for the sum of $9,500.

The defendants deny the validity of this mechanic’s lien on the ground that the affidavit required by Section 8314, General Code of Ohio, to be filed for record with the county recorder of this county, was not filed within sixty days from the date the last of such material was furnished at the building or the last of the labor was performed, as required by the aforementioned section of the General Code.

The brick work was substantially completed on July 18, 1923.

The affidavit for the mechanic’s lien was not filed for [58]*58record until January 4, 1924, approximately five and one-half months after the substantial completion of this brick work.

The plaintiff, however, alleges in his petition and offers proof to support the same, “that the specifications for the erection of said building and under which and in accordance with which his work was done, required that as part of his work, when notified by the proper parties and at the proper time, he should return to the building and clean the brick work erected by him, and he says further that he with his employes, at the proper time, to-wit: on or about the 12th day of November, 1923, presented themselves at the building for the purpose of cleaning said brick work and thus completing his part of the work, but that the defendants, Louis E. Jacob and Hilda Jacob, refused to allow plaintiff to complete, his contract in that respect, although plaintiff has always been ready and willing to do so.”

The plaintiff claims that November 12, 1923, by force of the tender of the labor to finish this brick work, is to be considered as the date from which the sixty day period is to be counted for the filing of the affidavit for mechanic’s lien for record with the county recorder.

While the proof shows conclusively that the plaintiff did present himself at the residence of the defendants November 12, 1923, and make an offer to point up and clean the brick work, which offer the defendants refused to accept and denied him the privilege of doing, yet the testimony as a whole indicates quite clearly that this offer of plaintiff to complete this brick work was not made in the bona fide belief that there was any work there that (he was required to do, or that the defendants wished him to do, or would permit him to do.

This visit of the plaintiff on November 12, 1923, to the home of the defendants was to create an epoch, strike an attitude, to be pointed to as the date from which to calculate the sixty day period for filing the affidavit for mechanic’s lien with the Recorder.

The plaintiff had been to the home of the defendants a week previous and had been told by them then that the [59]*59work of pointing up and cleaning the brickwork had been done a month previous by themselves, and that there was nothing they wanted or would permit plaintiff to do to the brick work.

The head contractor, Phillips, had been requested, according to the testimony, some time before defendants had done this work themselves, to clean this brickwork, but Phillips refused to do so, claiming that the brick work had been finished and that the defendants by taking over the building had accepted the same as completed, and that he had no further responsibility as to the brick work or any other work in connection with this building.

It appears from the testimony that the defendants moved into this building in September, 1923, and as there is no proof that as a condition to moving in the head contractor was to do further work on this building, the fair inference to be drawn from this is that the defendants accepted this dwelling as complete.

The contractor did nothing after the defendants moved into this dwelling, and the proof is that they themselves pointed up and cleaned this brick work. This evidence is additional proof that when the defendants moved in they understood that they were accepting this dwelling as completed.

The testimony shows that the plaintiff was continually after Phillips, the head contractor, for the payment of his bill for this brick work from the time of the substantial' completion of the brick work, July 18, 1923, up until the time in November, when he began to make an effort to have the defendants pay his bill.

The proof further shows that the defendants did not know of plaintiff’s unpaid bill for brick work, or even that he had done this work until his visit to them about November 5, 1923.

A significant item of evidence is a letter dated November 8, 1923, written by Phillips to the plaintiff. This letter is as follows:

“Cincinnati, Ohio, November 8, 1922.
“Mr. A. C. McKenzie, Cinti., O.
Dear Sir:
Please send a man to clean a few spots on brickwork [60]*60you did at Bowman Terrace, also some parts of the brickwork require pointing up.
Yours truly,
Joseph Philips.”

The plaintiff testified that he asked Phillips to write him this letter, yet at the time, the proof shows that plaintiff knew defendants did not want him to do any work, nor would they permit him to do any work in the way of pointing up or cleaning this brick work, as they had told him that it had already been done by themselves, and Phillips had taken the position that there was none to be done by him, nor would he do any further work on this dwelling house, presumably on the ground that defendants had taken over this dwelling and by so doing had accepted the same as complete.

This letter cannot be accepted as bona fide proof that there was still work there necessary to be done by plaintiff to complete his brick work.

A necessary deduction from the proof is that when the defendants moved into this dwelling in September, 1923, that they accepted the same as completed, brick work and all.

This would leave July 18, 1923, the date of the substantial completion of this brick work, as the date from which to calculate the sixty day period for filing the affidavit for mechanic’s lien.

The acceptance by the defendants of this dwelling as complete, without- any reservation as to work yet to be done, would leave plaintiff entirely out of the picture, because his obligation to return after his substantial completion of the work July 18, 1923, was merely conditional and was required of him only when notified to do so by the proper parties and at the proper time.

The plaintiff admits this in his petition by this allegation on page 3 of the petition, to-wit:

“When notified by the proper parties and at the proper time, he should return to the building and clean the brick work erected by him.”

The letter of Phillips before mentioned was inspired by the plaintiff, according to his own testimony, to give [61]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Driscoll v. Bradford
50 N.E. 628 (Massachusetts Supreme Judicial Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
27 Ohio N.P. (n.s.) 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckenzie-v-jacob-ohctcomplhamilt-1928.