McKenzie-Hague Co. v. Carbide & Carbon Chemicals Corp.

73 F.2d 78, 1934 U.S. App. LEXIS 2601
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 3, 1934
DocketNo. 9927
StatusPublished
Cited by8 cases

This text of 73 F.2d 78 (McKenzie-Hague Co. v. Carbide & Carbon Chemicals Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKenzie-Hague Co. v. Carbide & Carbon Chemicals Corp., 73 F.2d 78, 1934 U.S. App. LEXIS 2601 (8th Cir. 1934).

Opinion

BOOTH, Circuit Judge.

This is an appeal from a judgment on the pleadings in an action for damages brought by the McKenzie-Hague Company against appellee.

For convenience, the parties will be referred to as plaintiff and defendant, as in the court below.

The action may be classified as an action for deceit. It arises out of certain contracts under which plaintiff performed work [79]*79for defendant in the way of dredging and filling in the Kanawha river at Blaine Island, in tho stats of West Virginia.

Tho main question to bo determined on this appeal is whether, upon the facts well pleaded in tho complaint, together with the facts alleged in the answer and not denied in the reply, the court erred in rendering judgment for defendant.

The salient facts disclosed by the complaint are that in May, 1929, defendant invited bids for the work, and that plaintiff made a bid which was accepted. A formal contract was entered into by the parties dated September 23, 1929. This is known as the “Original Contract,” Exhibit A. The' complaint alleges that false representations in several pai tieulars were made by defendant, for the purpose of inducing plaintiff to bid on said work and enter into said contract; that defendant falsely, fraudulently, and negligently stated and represented to the plaintiff that the material to be dredged from said river consisted of approximately 10 per cent, gravel and the balance sand; that there existed in said river, within certain indicated limits adjacent to said island, a sufficient quantity, to wit, at least two million,, cubic yards, of such material; that defendant was then engaged in constructing an embankment on said island with material taken from said river; that tho material in said river which was to be dredged and used as fill by plaintiff was of the same kind and character as the material then being dredged and used for said embankment; that defendant had previously had made a hydrographic survey of said river adjacent to Blaine Island and had ascertained the character, location, and amount of such material; that defendant furnished to plaintiff a print or map purporting to show the results of said survey, whereon certain areas of file river bottom were inclosed or encircled with orange crayon lines and other sections were, marked off with red crayon lines, and certain figures appeared within the said sections; that defendant further falsely, fraudulently, and negligently stated and represented to plaintiff that within areas or sections marked off with red, there existed the number of cubic yards of the specified material to be dredged (10 per cent, gravel and the balance sand) which were indicated by the figures, all of which would bo available lo plaintiff for fill, except as hereinafter stated; that defendant further represented and stated to the plaintiff that the Ohio Dredging Company (hereinafter designated “Ohio Company”) was then employed by the defendant in dredging the specified material from said river for dikes and embankments on said island; that the material in areas encircled or inclosed. by orange crayon lines was reserved to the Ohio Company; that defendant further falsely and fraudulently stated and represented that in the event plaintiff undertook said proposed work, defendant would reserve for plaintiff all materials in said river within the indicated limits, except the 500,000 cubic yards to be removed by said Ohio Company, and that the defendant would restrict the operations of tho Ohio Company to the removal of material from the areas so indicated by the orange lines and would not permit said Ohio Company to dredge or remove material from other areas of said river within indicated limits, but that the same would be reserved to plaintiff.

The complaint further alleges that the representations were made for the purpose of having plaintiff rely on them and that plaintiff did rely on them in making the original contract.

The complaint further alleges that shortly after the making of the contract, plaintiff diseovex-ed that the Ohio Company had dredged outside the areas allotted to it and complained of this to defendant; that thereupon a modification of the original contract was made on October 23, 1929, which, among other things, increased somewhat tho compensation to bo paid plaintiff.

Tho complaint further alleges that, plaintiff proceeded with the work but soon found that the Ohio Company had removed most of tho sand and gravel from certain sections allotted to plaintiff, especially sections 6 and 7, and that only coarse gravel and large rocks remained; that plaintiff complained to defendant of this state of affairs and of the financial straits in which plaintiff found itself, and stated that it would be unable to go on with the work unless defendant would loan it the sum of $20,000, and increase tho compensation to be paid plaintiff; that defendant renewed its representations as to the quantity and quality of the material in sections other than 6 and 7; that thereupon another contract was entered into between the parties on April 1, 1930, which is known as “Supplemental Contract,” Exhibit B. This contract reduced the amount of fill to.be made by plaintiff, raised somewhat the price to be paid for the filling, extended the time for completing the work, and provided for a loan of $20,000 from defendant to plaintiff.

[80]*80The work proceeded. Further complaints were made by plaintiff to defendant relative to the character and amount of the material, and to the representations made by defendant in reference thereto, both those prior to the making of the original contract, as well as those prior to the making of the Supplemental Contract.

Plaintiff contended that all the available material had been removed from the bottom of the river, yet the filling had not been completed.

Finally, on January 23, 1931, a new contract known as “Second Supplemental Contract,” Exhibit C, was entered into by the parties. This contract provided, among other things, for the purchase of new land (known as “Joplin Branch Bottom Area”) for the purpose of supplying further material; the purchase price to be shared by plaintiff and defendant. By this contract, the areas to be filled were further modified.

These provisions were carried out and the work proceeded until some time in May, 1931.

The complaint alleges that the terms of this Second Supplemental Contract were not carried out by defendant in respect to the slope to be allowed in the dredging operations and in respect to the areas in the Joplin Branch Bottom from which material might be dredged.

In May, 1931, there was an exchange of telegrams and the passing of a letter between plaintiff and defendant. In accordance with these communications, the areas to be filled were still further curtailed; about $1,000 of the loan was to be canceled by defendant; and the remaining work was to be completed, if possible, by June 1, 1931.

In July, 1931, defendant made out and sent to plaintiff a statement of account of the total work showing a balance due plaintiff of about $4,709. A deduction was made of about $766 on account of interest on the loan, leaving a balance of about $3,945. A cheek for this last amount was sent to plaintiff; . also the promissory note and a release of the chattel mortgage which had been given m connection with the loan. On the cheek was a voucher notation reading as follows:

“For

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gribbin v. Gribbin
499 So. 2d 858 (District Court of Appeal of Florida, 1986)
State v. Woods
357 N.E.2d 1059 (Ohio Supreme Court, 1976)
Bennett v. Mahon
180 F.2d 224 (Eighth Circuit, 1950)
Whitmarsh v. Pennsylvania R.
61 F. Supp. 850 (E.D. Pennsylvania, 1945)
Harris Trust & Savings Bank v. Keig
98 F.2d 952 (Seventh Circuit, 1938)
In Re Prima Co.
98 F.2d 952 (Seventh Circuit, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
73 F.2d 78, 1934 U.S. App. LEXIS 2601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckenzie-hague-co-v-carbide-carbon-chemicals-corp-ca8-1934.