McKee v. City of Cohoes Board of Education

99 A.D.2d 923, 473 N.Y.S.2d 269, 1984 N.Y. App. Div. LEXIS 17332
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 23, 1984
StatusPublished
Cited by10 cases

This text of 99 A.D.2d 923 (McKee v. City of Cohoes Board of Education) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKee v. City of Cohoes Board of Education, 99 A.D.2d 923, 473 N.Y.S.2d 269, 1984 N.Y. App. Div. LEXIS 17332 (N.Y. Ct. App. 1984).

Opinion

Appeal from that part of an order of the Supreme Court at Special Term (Hughes, J.), entered December 27, 1982 in Albany County, which granted plaintiff’s motion to dismiss the first and second affirmative defenses, and denied defendant’s cross motion for summary judgment dismissing plaintiff’s first and second causes of action. In the fall of 1977, defendant City of Cohoes Board of Education began consideration of the feasibility of constructing a new elementary school. On June 13, 1978, defendant voted to appoint plaintiff as engineer for the construction of said structure. On January 9, 1979, defendant authorized appropriation of the sum of $25,000 for engineering and survey services in connection with the proposed elementary school. A public informational hearing was held on March 28, 1979 at which plaintiff presented preliminary plans for the school. A second public meeting was scheduled to be held on April 4, 1979, but was postponed because of [924]*924uncertainties in available State funding. The hearing was never rescheduled, however, and construction was never begun on the new school. On April 4, 1979, then school Superintendent Gerald Amyot signed a contract with plaintiff which purported to retain plaintiff as engineer for the elementary school project at a rate of 6% of the cost of construction of said school. The cost of the project was estimated at $3.6 million. Plaintiff maintains that on prior projects undertaken by him for defendant, the practice had always been for the school superintendent to sign on behalf of defendant. In late August, 1979, plaintiff submitted a voucher for $20,000 to cover the cost of preliminary work on the project. By check dated August 30,1979, payment of that $20,000 was made to plaintiff out of the $25,000 appropriation. On September 18, 1979, a story appeared in a local newspaper to the effect that even though the proposed elementary school would not be built, plaintiff had already provided over $100,000 worth of services with respect thereto and would seek payment thereof. According to the newspaper account, plaintiff stated that he had only billed the school district for $20,000 because defendant had not yet appropriated the rest of the money. At its September 18,1979 meeting, defendant voted to direct plaintiff to suspend any and all work on the plans for the new school, and plaintiff was so notified by telephone on September 19,1979 and by letter dated September 20,1979. Additionally, defendant voted to retain an attorney to determine the school district’s legal rights with respect to all matters pertaining to the proposed new school. The attorney reported to defendant at its November 20, 1979 meeting and, after discussing the matter, defendant decided that it would not make further payments to plaintiff. Plaintiff states that he never received formal notice that defendant would not honor the alleged contract and that it was not until he read a newspaper article dated November 21, 1979, discussing the November 20, 1979 meeting, that he discovered that defendant intended to make no further payments to him. On February 18, 1980, plaintiff served a notice of claim upon defendant board seeking $300,000 for services rendered. Plaintiff commenced an action against defendant on August 14,1980, which was dismissed without prejudice because of plaintiff’s failure to timely serve a complaint. Defendant had also moved to dismiss the action for failure to timely serve a notice of claim pursuant to subdivision 1 of section 3813 of the Education Law. In dictum, Special Term noted that a factual issue existed as to when precisely plaintiff’s claim accrued. Plaintiff thereafter commenced the instant action in June, 1982, asserting causes of action for breach of contract,, fraud and quantum meruit. Defendant answered raising five affirmative defenses. The first affirmative defense alleges that plaintiff’s action is barred by his failure to present a verified claim to defendant within three months of accrual of the claim as is required by section 3813 of the Education Law. The second affirmative defense charges that the action is barred by the applicable Statute of Limitations. The third, fourth and fifth affirmative defenses basically allege that defendant only retained plaintiff to the extent of the January 9,1979 appropriation and that the contract which plaintiff purportedly entered into with former Superintendent Amyot was illegal and, therefore, unenforceable, since entering into such was an ultra vires act on Amyot’s part. Plaintiff moved to dismiss the first and second affirmative defenses. Defendant thereafter cross-moved for summary judgment. Special Term dismissed both the first and second affirmative defenses, holding that plaintiff’s notice of claim had been timely filed and that plaintiff’s causes of action were not time barred. The court also granted summary judgment dismissing plaintiff’s third cause of action in quantum meruit. Defendant’s cross motion for summary judgment dismissing the complaint was in all other respects denied. This appeal by defendant ensued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Swamp Conservancy Inc. v. Town of Lenox
2021 NY Slip Op 03094 (Appellate Division of the Supreme Court of New York, 2021)
Elia v. Highland Central School District
78 A.D.3d 1265 (Appellate Division of the Supreme Court of New York, 2010)
Garner v. CORRECTIONAL SERVS.
889 N.E.2d 467 (New York Court of Appeals, 2008)
Bianchi Industrial Services, LLC v. Village of Malone
41 A.D.3d 999 (Appellate Division of the Supreme Court of New York, 2007)
Lawrence L. Smith Associates, P. C. v. Board of Education
285 A.D.2d 583 (Appellate Division of the Supreme Court of New York, 2001)
Guild of Administrative Officers of Suffolk County Community College v. County of Suffolk
126 A.D.2d 725 (Appellate Division of the Supreme Court of New York, 1987)
Dziadiw v. 352 State Street Corp.
107 A.D.2d 1003 (Appellate Division of the Supreme Court of New York, 1985)
State of New York v. Gordon
102 A.D.2d 990 (Appellate Division of the Supreme Court of New York, 1984)
Commericial Credit Corp. v. CYC Realty, Inc.
102 A.D.2d 970 (Appellate Division of the Supreme Court of New York, 1984)
Crane v. New York Council 66 of American Federation of State Employees
101 A.D.2d 682 (Appellate Division of the Supreme Court of New York, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
99 A.D.2d 923, 473 N.Y.S.2d 269, 1984 N.Y. App. Div. LEXIS 17332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckee-v-city-of-cohoes-board-of-education-nyappdiv-1984.