McKee Builders, Inc. v. Knight (In Re Knight)

377 B.R. 590, 2007 Bankr. LEXIS 3400, 2007 WL 2910157
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedOctober 2, 2007
DocketBankruptcy No. 05-53681, Adversary No. 06-5003
StatusPublished
Cited by1 cases

This text of 377 B.R. 590 (McKee Builders, Inc. v. Knight (In Re Knight)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKee Builders, Inc. v. Knight (In Re Knight), 377 B.R. 590, 2007 Bankr. LEXIS 3400, 2007 WL 2910157 (Tenn. 2007).

Opinion

MEMORANDUM

MARCIA PHILLIPS PARSONS, Bankruptcy Judge.

In this adversary proceeding, the plaintiff McKee Builders, Inc. seeks a determination of nondisehargeability under 11 U.S.C. § 523(a)(2). The trial of this adversary proceeding was held on September 13, 2007. The record before the court consists of 13 exhibits introduced into evidence, together with the testimony of Jeffrey McKee, the president and sole shareholder of the plaintiff, and debtors Louis and Sherry Knight, the defendants herein. This is a core proceeding. See 28 U.S.C. § 157(b)(2)(I).

I.

On September 23, 2005, Louis and Sherry Knight filed a petition under chapter 7 initiating the underlying bankruptcy case. *593 Subsequently, on January 3, 2006, the plaintiff filed its complaint commencing this adversary proceeding, seeking a denial of discharge under 11 U.S.C. § 727(a)(2)(A), (4), and (5) and a determination of nondischargeability under § 523(a)(2). By order entered August 25, 2007, this court granted in part the debtors’ motion for summary judgment, dismissing the § 727(a)(2)(A) and (4) claims. At the close of trial, the plaintiff withdrew its § 727(a)(5) cause of action. Thus, the only issue before the court is the § 523(a)(2) claim.

The parties’ contractual relationship began when they entered into a contract on February 28, 2003, for the construction by the plaintiff of a personal residence for the debtors. Article IV of the contract provides:

The Owners shall pay the Contractor the sum, which is equal to Fifteen percent of the entire construction project. The estimated costs of materials and labor necessary to construct the structure based on the modified Plan N.2020 drawn by Atlanta Plan Source is $240,500.00. It is understood that this is an estimate and may vary up or down as construction proceeds. It is agreed that the contract price is partially based on certain allowances extended to the owners by the contractor as specified on Addendum I. The owners may adjust these allowances.

(Tr. Exh. 9.) Attached to the contract as Addendum I was the list of allowances for fixtures, etc., as referenced in Article IV.

The parties disagreed at trial as to whether the $240,500 purchase price included the contractual 15% contractor fee. The debtors indicated that it did while McKee stated that the contractor fee was an additional amount. Moreover, the debtors disputed the language in the contract which stated that the $240,500 amount was an estimate. Mr. Knight stated in his deposition that the $240,500 amount was a round figure that McKee put into the contract to get the job rolling while the debtors testified at trial that the quoted price was $212,000 and that McKee placed the higher amount in the contract so that the debtors could obtain a larger construction loan.

The debtors obtained a construction loan from Bank of Tennessee in the amount of $256,860 and construction began in April 2003. As is often the case in residential construction, changes were made to the originally planned structure. Three feet was added to the back of the house to make it wider in order to meet the lender’s demands that the house be larger so that an appraisal would justify the construction loan; a bay window was added to the ground floor; dormers were added to the front; and the entire second floor, which originally was only going to be framed in, was finished as a bonus room and a half bath. As to the additional square footage on the back and the bay window, the debtors indicated that these changes were included in the original contract, assertions McKee disputed. It is undisputed that the debtors exceeded their Addendum I allowances. The debtors paid the subcontractors and materialmen directly so they were aware as the construction proceeded that materials and labor were costing more than originally estimated.

In November or December 2003, the debtors began to run out of money. Sometime in December 2003, McKee gave the debtors a job summary that listed the allowance for the various items, the actual cost, and the reason for the overage. According to the summary, the overages totaled $58,458.69.

By letter dated January 23, 2004, the debtors advised plaintiff that they were rescinding and terminating the contract *594 because of “what we consider to be deceitful and fraudulent acts on your part prior to and during the construction of our home.” The letter forbade McKee or anyone on his company’s behalf from entering onto the property without the debtors’ written consent and asked McKee to contact the debtors to negotiate a settlement of what was owed. At this time the construction was almost complete, with the hardwood flooring and tile having already been laid.

The plaintiff ceased work on the residence in response to the letter and on February 9, 2004, filed a notice of lien against the debtors’ property. On March 6, 2004, the debtors moved into the residence. Construction was complete at that time except for the yard and landscaping work. Several subcontractors and suppliers remained unpaid, including 84 Lumber Company which was threatening to file its own notice of lien on the residence, and the default in payment to the subcontractors and materialmen was hindering the plaintiffs ability to work on other projects since these debts were in plaintiffs name. And, although Bank of Tennessee had increased the construction loan to $283,500, the bank was refusing to release to the debtors the remaining draw of $23,000 because of the lien on the property and unpaid debts.

In order to resolve the dispute, the debtors and McKee met in the office of the plaintiffs attorney, Christopher Raines, on March 8, 2004. As a result of the meeting, the parties executed that day a handwritten agreement drafted by Raines. In the agreement the debtors agreed to assign the remaining construction loan draw of $23,000 to the plaintiff in partial satisfaction of debts owed to 84 Lumber Company, Customer Gas Services, Sears, Wine-gar Floor Covering, Dors Johns, and Ralph Hawkins. The debtors further agreed to place the American Lighting debt in their name and to execute a promissory note for the balance due plaintiff in the amount of $16,823.38, less a credit for the American Lighting debt once it was transferred into their name. To generate funds sufficient to pay the note, the debtors agreed to apply for refinancing of the residence within 30 days of the filing of a final deed of trust by the Bank of Tennessee, with refinancing to be complete within 120 days. In return for the foregoing, the plaintiff agreed to release its lien that it had placed on the debtors’ residence.

On April 6, 2004, McKee and the debtors met at the Bank of Tennessee to carry out the March 8, 2004 agreement. The bank released the final $23,000 draw, cutting checks directly to 84 Lumber Company, Sears Commercial One, and Winegar & Sons Flooring. McKee executed a release of the lien. The debtors were presented with the note to execute on behalf of the plaintiff but balked at signing it when they saw that it contained an attorney fee provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rebekah v. Crownover (In Re Crownover)
417 B.R. 45 (E.D. Tennessee, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
377 B.R. 590, 2007 Bankr. LEXIS 3400, 2007 WL 2910157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckee-builders-inc-v-knight-in-re-knight-tneb-2007.