MCI WorldCom Communications, Inc. v. Public Utility Commission

826 A.2d 919, 2003 Pa. Commw. LEXIS 374
CourtCommonwealth Court of Pennsylvania
DecidedMay 29, 2003
StatusPublished
Cited by3 cases

This text of 826 A.2d 919 (MCI WorldCom Communications, Inc. v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI WorldCom Communications, Inc. v. Public Utility Commission, 826 A.2d 919, 2003 Pa. Commw. LEXIS 374 (Pa. Ct. App. 2003).

Opinion

OPINION BY

Judge PELLEGRINI.

MCI WorldCom Communications, Inc. and MCIMetro Access Transmission Services, LLC (collectively, MCI) appeal from a decision and order of the Pennsylvania Public Utility Commission (PUC) holding that due to an order of the Federal Communications Commission (FCC), a “change-in-law” provision in an Interconnection Agreement between MCI and Verizon Pennsylvania, Inc. (Verizon) “permitted” an amendment to their rate schedule.

The Interconnection Agreement that is at issue in this case was entered into as a result of The Telecommunications Act of 1996(Act), 47 U.S.C. §§ 251-261. That Act abolished exclusive communication franchises and allowed competing local telephone companies to enter the local telephone service market. Prior to the enactment of this Act, Verizon’s predecessor, Bell Atlantic-Pennsylvania, Inc., was the sole local telephone company providing service in Pennsylvania where it was authorized to do business. Section 251 of the Act, 47 U.S.C. § 251, required Verizon to provide MCI with non-discriminatory access to its network and services and required the parties to enter into interconnection agreements.1

MCI and Verizon entered into an Interconnection Agreement which the PUC approved. Under the Interconnection Agreement, MCI and Verizon agreed to bill and pay invoices for reciprocal compensation for calls to Internet Service Providers (ISPs), companies that provide their customers with the ability to obtain on-line information through the use of the Internet, pursuant to a rate schedule2 agreed [921]*921upon by the parties. The Interconnection Agreement also contained a provision that addressed circumstances when the rate schedule had to be amended to account for changes in the law. Specifically, Section 1.1 of Attachment 1 to the Agreement, the Price Schedule, provided, in relevant part:3

The rates or discounts set forth in Table 1 below may be subject to change and shall be replaced on a prospective basis (unless otherwise ordered by the FCC, the Commission, or the reviewing court(s)) by such revised rates or discounts as may be ordered, approved or permitted to go into effect by the FCC, the Commission or a court of applicable jurisdiction, as the case may be. Such new rates or discounts shall be effective immediately upon the legal effectiveness of the court, FCC, or Commission order requiring such new rates or discounts.

With the growth of the Internet, however, LECs, including Verizon, disputed whether reciprocal compensation should also apply to traffic going to an ISP. They contended that there was a disproportionate flow of one-way traffic which, in turn, led to the disproportionate payment of reciprocal compensation from the LEC of the end user to the LEC of the ISP.4 On April 27, 2001, the FCC issued an order (FCC Order)5 in which it determined that ISP calls were expressly excluded from the reciprocal compensation obligations of the Act because they were a form of interstate traffic. However, because carriers incurred costs when they exchanged calls to ISPs, the FCC concluded that inter-carrier compensation was necessary and established a new and interim inter-carrier compensation rate schedule for ISP traf[922]*922fic.6 The new rate schedule was intended to replace the current system of reciprocal compensation unless parties were entitled to take advantage of change-of-law provisions that would provide for the immediate implementation of the new rates.7 The reciprocal compensation rates for the termination of ISP calls were to be capped and phased out over a three-year period, but only if the LEC offered to exchange all traffic subject to Section 251(b)(5) at the same rate. Regarding the applicability of the FCC Order to existing interconnection agreements, the FCC stated the following:

The interim compensation regime we establish here applies as carriers re-negotiate expired or expiring interconnection agreements. It does not alter existing contractual obligations, except to the extent that parties are entitled to invoke contractual change-of-law provisions. (Bold added.)

(Paragraph 82 of FCC Order.)

Because Verizon and MCI could not agree on whether the FCC Order “permitted” Verizon to implement the new rate schedule, Verizon filed a petition with the PUC for a determination. Verizon contended that the FCC Order “permitted” it to invoke the change-of-law provision in the Interconnection Agreement and implement the new rate schedule as of June 14, 2001, and once the FCC released its order and provided for the interim inter-carrier compensation schedule, that order permitted new rates to go into effect. MCI, however, argued that Section 1.1 of the Attachment to the Agreement did not apply because nothing in the FCC Order either required or permitted a change in rates, and that if the language of the existing Interconnection Agreement did not [923]*923mandate a change, then only new agreements were required to implement the changes. It also filed a counterclaim for the payment of reciprocal compensation at the old contract rates for ISP calls during the months of June through October 2001, which Verizon had withheld. Verizon filed an answer and affirmative defenses to the counterclaim.

Without holding an evidentiary hearing because the parties agreed there were no material facts in dispute,8 the Administrative Law Judge (ALJ) issued a decision concluding that the FCC Order was not intended to apply to existing interconnection agreements because neither the FCC, the PUC nor the courts had ordered any changes to the rates on the rate schedule, and that MCI had no contractual obligation to agree to the new rates because no provision of the Interconnection Agreement had been rendered unlawful. In her decision, the ALJ stated:

The change-of-law provisions at issue here do not apply because the FCC in its ISP Remand Order did not intend the Order to alter existing agreements, or to mandate application of the interim compensation regime either as of the effective date of the Order or at any other definite time. Had it done so, there is no question that the interconnection agreement would have to be revised accordingly. The FCC could have done exactly this; the fact that it did not indicates that the FCC recognized that operating under the reciprocal compensation regime is appropriate until “expired or expiring” agreements are renegotiated, so that the interim compensation regime can be prospectively applied.

(ALJ’s November 16, 2001 decision at 10.) The ALJ further found that any amendment to the Interconnection Agreement had to be negotiated by the parties and approved by the PUC to be effective. The ALJ then ordered Verizon to pay past due reciprocal compensation under the rate structure the parties agreed to in their Interconnection Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowers v. T-NETIX
837 A.2d 608 (Commonwealth Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
826 A.2d 919, 2003 Pa. Commw. LEXIS 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-worldcom-communications-inc-v-public-utility-commission-pacommwct-2003.