McHarg-Barton Co. v. Maritime Dredging Co.

161 A.D. 921, 145 N.Y.S. 1093

This text of 161 A.D. 921 (McHarg-Barton Co. v. Maritime Dredging Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McHarg-Barton Co. v. Maritime Dredging Co., 161 A.D. 921, 145 N.Y.S. 1093 (N.Y. Ct. App. 1914).

Opinion

Scott, J.:

Plaintiff contracted with the United States to furnish all the labor and material required for the construction of a storage dock at Fort Wood in New York harbor, including dredging, etc. Plaintiff subcontracted with the defendant to do the dredging in the above contract for the lump sum of $21,000. The work was to be done as per plans and specifications issued by the constructing quartermaster at said Fort Wood, and to the satisfaction of said constructing quartermaster. The plans and specifications required that the basin and channel should be dredged to the uniform depth of eighteen feet at mean low water. Estimates were to be made monthly on the twenty-fifth of each month, and ninety per cent of the amount of each estimate was to be paid before the tenth of the next month. The two significant clauses of the contract between plaintiff and defendant, so far as concerns this appeal, are the third and fifth, reading as follows: “ Third. Should any dispute arise respecting the true construction or meaning of the drawings or specifications or quality of work clone, the same shall be decided by the Constructing Quartermaster, Fort Wood, N. Y. H., and his decision shall be final and conclusive.” “Fifth. It is agreed that if the party of the second part should encounter ledge rock or hard-pan in the execution of this contract, that this material is not to be removed under [922]*922the terms of this contract.” The defendant concededly did not complete the contract, but, after working at it for some time, discontinued work. This action is for damages suffered by plaintiff by reason of defendant’s fault. Defendant attempts to justify its discontinuance by the assertion that it encountered “ hard-pan” which it was not required to remove, and that it did in fact remove everything taut hard-pan. The issue as to whether hard-pan was encountered went to the jury, which found in defendant’s favor. On motion, the court set aside the verdict and ordered anew trial “on the grounds that said verdict is against the weight of evidence and as a matter of judicial discretion.” The verdict was clearly against the evidence. Certainly the defendant did not sustain the burden of justifying its default. For this reason, if for no other, the orders should be affirmed. It is not necessary to pass upon the many exceptions taken during the trial, except to éxpress the opinion that the provision in clause 3 of the contract, providing that the constructing quartermaster should pass on the “ quality of work done,” did not impose upon him the duty or authority to decide, as between plaintiff and defendant, whether the material which defendant failed to excavate was or was not “ hard-pan.” That was not a question as to the “ quality of work done.” The orders should be affirmed, with costs to respondent. Ingraham, P. J., McLaughlin, Laughlin and Hotchkiss, JJ., concurred. Orders affirmed, with costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
161 A.D. 921, 145 N.Y.S. 1093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcharg-barton-co-v-maritime-dredging-co-nyappdiv-1914.