McGillis v. Hogan

60 N.E. 91, 190 Ill. 176
CourtIllinois Supreme Court
DecidedApril 18, 1901
StatusPublished
Cited by1 cases

This text of 60 N.E. 91 (McGillis v. Hogan) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGillis v. Hogan, 60 N.E. 91, 190 Ill. 176 (Ill. 1901).

Opinion

Mr. Chief Justice Boggs

delivered the opinion of the court:

Plaintiff in error, McGillis, who lived in Kankakee, Illinois, and defendant in error James E. Hogan, in 1882 became partners under the name of McGillis & Co. The firm entered into a written -contract with the Western Air Line Construction Company, by which said McGillis & Co. contracted to grade and complete forty-six miles of the road-bed of the Indiana, Illinois and Iowa railroad at prices stipulated in the contract. The contract provided the^ measurements and estimates of the engineers of the construction company should be conclusive on the contracting parties. McGillis & Co. performed a portion of the work and refused to proceed further in the performance of their contract, on the ground (as they alleged) the engineer of the construction company had fraudulently made too low an estimate upon the work they had done, and that by reason of such fraud the amount due them was estimated by the engineer at a sum $55,000 less than they were entitled to receive. The construction company, acting under a clause in the contract authorizing- that course to be taken in the event McGillis & Co. should make default, completed the work at an expense, as the construction company claimed, of $22,000 in excess of the amount it would have had to pay for the work under the contract with McGillis & Co.About this time the defendant in error Hogan, a member of the firm of McGillis & Co., squandered a considerable sum of money of the firm in gambling houses in Chicago. The defendant in error Cooper, an attorney at law in Chicago, was employed by the firm to recover, and did so recover, a considerable portion of the money so lost by Hogan. McGillis & Co. were indebted to various parties for labor performed and material furnished in and about the work performed by them under the contract with the construction company. The construction company was a non-resident corporation and had no tangible property in this State. An agreement was made between the firm and Cooper, their attorney, by which McGillis, the first party, and Hogan, the second party, executed an instrument assigning to Cooper, the third party, as trustee, all their rights under said contract. Cooper accepted the trust in writing. The instrument gave Cooper full control of the controversy between McGillis & Co. and the construction company, authorized him to sue upon their claim, to settle and compromise all said matters and to bind McGillis & Co. in relation thereto. The instrument imposed upon Cooper the following directions as to the disposition of the funds when collected:

“First—Out of any moneys or funds derived from a settlement or a decree or judgment relating to the matters in controversy,—that is to say, out of any moneys or funds derived for work done or materials furnished or damages incurred by said first and second parties on the' line of the Indiana, Illinois and Iowa railroad,—the said Cooper, as such trustee, shall pay and deduct the reasonable costs, fees and expenses of such settlement or litigation.

“Second—He shall next pay the amount due by said first and second parties for work done or materials furnished on the line of said railroad by other persons, as the same is shown upon the books and papers of said firm, composed of said first and second parties hereinbefore referred to.

“Third—He shall divide the remainder of such money or funds so derived between the said first and second parties hereto, in accordance with the interest that each has in said co-partnership, the same being an equal interest, but the partnership accounts between said first and second parties not having yet been settled.”

Thereafter, Cooper brought an attachment suit in the circuit court, of Kankakee county against the construction company upon said claim. Defendant procured the removal of the cause to the United States Circuit Court. A trial was had in Chicago before Judge Bunn and a jury, occupying some ten days, and resulted in a verdict for plaintiffs for about $17,000. A motion for a new trial was made by the defendant, and argued at Madison, Wisconsin, and granted upon defeudant paying the costs and $500 to plaintiffs.^, A second trial of about eight days’ length was had. before'Judge Gresham and a jury, and plaintiffs had a verdict for $24,165.57. A motion for a new trial was argued and denied, and judgment rendered. A writ of error to the Supreme Court of the United States was sued out and made a supersedeas. Upon application to that court the supersedeas was set aside but the writ of error was retained. John Allison & Co., creditors of McGillis & Co., sued the latter and got judgment. That matter was then adjusted, by consent of McGillis & Co., by the assignment to Allison & Co. of $8800 of said judgment against the construction company. Thereafter, Cooper settled with the construction company for $20,000 in cash, he first agreeing that the fees of himself and his assistant, Gen. Stiles, should be scaled down seventeen per cent, and also procuring Allison & Go. to accept $7900 in full of their judgment.

In all this litigation Cooper acted as the main attorney for McGillis & Co., assisted at the trial by Gen. Stiles and some younger lawyers. The litigation was expensive for plaintiffs. It was a matter of great difficulty to prove their case. The grading had been done on an old roadbed constructed eleven years before McGillis & Co. began work. After McGillis & Co. quit, the construction company at once went ón and finished the work. The construction company’s engineer, in making estimates for McGillis & Go., had assumed that the original road-bed was a complete and perfect structure of a certain height and length. McGillis & Co. claimed it was washed out and destroyed in many places, which they had filled and for which they should be paid. It was a matter of much difficulty and expense, and required the aid of experienced engineers, to ascertain and prove how much Mc-Gillis & Co. had done upon this road-bed, finished, as it was, before the’ first trial and containing the work of three different sets of contractors, and especially to overcome the estimates made while McGillis & Co. were at work, by the engineers of the construction company, whose decisions were by the- contract made final. Money was therefore called for by Cooper frequently, and in large sums. When Hogan went into the firm he borrowed considerable sums of money of defendant in error Eames, of Ashland, Massachusetts, which Hogan claims he put into, the firm business. When Hogan was called upon- to advance funds for the prosecution of the suit against the construction company he was unable to do so. He thereupon assigned his interest in the contract and suit to Eames, and the latter advancéd money, mainly for the first trial. He paid $700 directly to Cooper, and paid $410 at the request of Cooper to procure the attendance of Hogan and his brother, who were unable or unwilling to come to the trial unless their expenses were paid. He thus advanced $2110. McGillis advanced over $4000, mostly for the expenses of the second trial. McGillis also paid claims against McGillis & Co. for labor and material to the amount of $2696.35, prior to the settlement with the construction company.

After Cooper received the $20,000 he distributed it on December 10, 1888. At that time he paid the remaining expenses of the suit, except certain amounts aggregating $592, which he overlooked and has since paid out of his own moneys; paid Allison & Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kenealy v. Glos
89 N.E. 289 (Illinois Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.E. 91, 190 Ill. 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgillis-v-hogan-ill-1901.