McFarland v. McKee

41 So. 2d 574, 252 Ala. 434, 1949 Ala. LEXIS 447
CourtSupreme Court of Alabama
DecidedJune 23, 1949
Docket3 Div. 535.
StatusPublished
Cited by1 cases

This text of 41 So. 2d 574 (McFarland v. McKee) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McFarland v. McKee, 41 So. 2d 574, 252 Ala. 434, 1949 Ala. LEXIS 447 (Ala. 1949).

Opinion

FOSTER, Justice.

The substance of the question involved on this appeal is whether the director of the Highway Department can so bind himself by contract with a highway construction contractor or by promulgating a rule applicable to such contract as to prevent him from agreeing with such contractor by supplemental agreement as to a matter which is a cause for a reasonable difference of opinion.

It is necessary to state enough of the facts to understand the question.

After pursuing the customary method calling for bids on a piece of highway construction, the contract was awarded to appellee. He was to receive twenty-seven and one-half cents per cubic yard for 392,600 cubic yards of common excavation It was supposed that it would all be classed as common excavation.

The standard specifications had the following provisions:

“208.02. Classification. Roadway and Drainage Excavation shall include all materials, of whatever nature encountered except .water or other liquid and will be paid for under the item of Unclassified Excavation or such of the pertinent classified items of Solid Rock Excavation, Common Excavation, Stripping Excavation, Channel Excavation, as are listed in the Proposal, which' classifications are, for the purpose of estimating and payment, defined as fol* lows:

*436 “(1) Solid Rock Excavation. This Classification shall include all rock in ledges, bedded deposits and unstratified masses, in its original position, that in the opinion of the engineer cannot be excavated without the continuous use of explosives and/or by the proper use of a current model power shovel of one cubic yard or more capacity ; and shall also include detached boulders and rock measuring thirteen cubic feet or more in volume. It shall not include material surrounding such boulders that is designated in the Common Excavation Classification.

“(2) Common Excavation. This Classification shall include all loam, sand clay, chert, gravel (loose or cemented), shale, slate, decomposed rock, old gravel, chert, or broken stone surfacing, and all other material encountered that are not included in the Solid Rock Excavation Classification as above defined.”

■ It was not anticipated that solid rock would be found to be excavated under the contract. There was a provision for “extra work”, as follows:

“1.27. Extra Work. Work or material, the performance or furnishing of which is found necessary for proper completion of ■the improvement and, which in principle is an obligation of the contractor, but which is not covered by any item in the bid schedule in the Proposal and for which no means of payment, direct or indirect, has been provided in the contract, and which is an obligation for which special remuneration, by an ‘Extra’ price or by other consideration, in any case to be duly negotiated, or by 'Force Account’, shall be paid to the contractor.”

There was a special provision inserted in this contract, as follows :

“All lime rock, shell rock or Selma chalk common in this vicinity, encountered on construction, shall be classified as and paid for as common excavation.”

During the progress of the work the contractor found formations which in his judgment, although they were lime rock, shell rock or Selma chalk, they were not common in that vicinity, but required explosives and/or the use of a current power shovel of one cubic yard or greater capacity, which he claimed was not stipulated in the contract for payment, but ■ which in principle the contractor was obligated to remove, and for which special remuneration should be paid as an “extra”.

Although the sufficiency of the petition on demurrer is before the Court, we prefer to go at once to the real issue of law and fact as set up in the answer. It denies that the formations of lime rock, shell rock and Selma chalk encountered were not such as were common in that vicinity. It admits that 4076 cubic yards of solid rock were encountered and were paid for at a dollar and a half per cubic yard, but denies that 24,287 of socalled “hard material” should have been included in the supplemental agreement at seventy cents or any other price. The answer made the following allegations:

“Defendant denies that said, ‘supplemental agreement’ was authorized in the premises by the said ‘standard specifications,’ in law or in fact, and for answer says that said ‘supplemental agreement’ was entered into without the signature, approval, endorsement, knowledge, or consent of the State Construction Engineer, towit, Mr. Marvin Taylor, who now holds and has held such office at all times material to matters herein involved and who expressly refused to approve the said ‘supplemental agreement,’ and for further answer says that paragraph 4.04 of said ‘standard specifications’ provides in pertinent part that ‘extra work shall be done under the supervision of the engineer and his decision shall be final and binding. The plan of the work to be followed, the equipment to be used, and the amount and character of labor to be employed shall meet with his approval’, whereas paragraph 1.06 of said ‘standard specifications’ defines the noun ‘Engineer’, as used in said specifications as: ‘The State Construction Engineer for the Director, or his authorized representative, acting within the scope of the authority and/or the particular duties entrusted to him’. Defendant further denies that ‘the State Highway Department directed the plaintiff to proceed with the excavation of said masses’, as alleged in paragraph 4 of said petition, and denies that there was any agreement at that time that unit prices for ‘un *437 classified excavation’ would later be agreed upon ‘in the light of actual experience’, and defendant demands strict proof of that allegation and averment, and for answer says that paragraph 9.04(D) of the said ‘standard stipulations’ provides that ‘no extra work will be paid for unless unit prices or wages have been agreed upon in writing before such work is started.’ ”

A demurrer was sustained to the answer, and defendant then plead the general issue to the petition.

The highway director allowed and paid the claim of the contractor, but upon complaint by the chief examiner of accounts, he deducted the amount of the same from other sums due the contractor, the correctness of which is not disputed.

The director is the party to whom the mandamus is directed, but his evidence was favorable to the contractor evidencing a belief that the contractor’s claim is just.

As referred to in the answer, the contention is that the State construction engineer is the only authority under the specifications and contract to determine whether the claim of the contractor for extra work was just and reasonable, and that such determination could not be made by the director with the approval of the governor.

The term engineer in the specifications is “the State construction engineer for the director, or his authorized representative”. That was Marvin Taylor.

The specifications provided that “extra work shall be done under the supervision of the engineer and his decision shall be final and binding,” and section 5.01 was as follows:

“5.01. Authority of the Engineer. All the work shall be done under the direct supervision of the engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rainer v. Tillett Bros. Construction
381 So. 2d 36 (Supreme Court of Alabama, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
41 So. 2d 574, 252 Ala. 434, 1949 Ala. LEXIS 447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcfarland-v-mckee-ala-1949.