McEvoy v. Gallagher

83 N.W. 633, 107 Wis. 331, 1900 Wisc. LEXIS 258
CourtWisconsin Supreme Court
DecidedSeptember 25, 1900
StatusPublished
Cited by1 cases

This text of 83 N.W. 633 (McEvoy v. Gallagher) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McEvoy v. Gallagher, 83 N.W. 633, 107 Wis. 331, 1900 Wisc. LEXIS 258 (Wis. 1900).

Opinion

Cassoday, C. <7.

This action was commenced August 18, 1898, against the supervisors of the town of Plymouth, and their agents, employees, or contractors, to restrain them from •diverting a creek, or any part thereof, running into the Baraboo river, from the plaintiff’s land. Such proposed diversion is admitted, but is sought to be justified on the ground that it was necessary in the proposed improvement of the public highway running north and south along the west side •of the plaintiff’s premises. It is conceded, in effect, that the creek came in from the west, and crossed the highway under •a bridge, and entered the plaintiff’s land, and then, after running in an easterly direction to a point on the plaintiff’s land about 150 feet from the center of the highway, turned and ran in a southerly direction for a short distance, and then turned and ran in a westerly direction, and recrossed the highway under a bridge about 150 feet south of the place where it first crossed the highway, and that said creek had so run on the land owned by the plaintiff from time out of mind.

At the time of the commencement of the action a preliminary injunction was granted by a court commissioner restraining the defendants from diverting from the plaintiff’s land any part of the water flowing in such creek.

August 24, 1898, the defendants answered by way of admissions, denials, and counter allegations. September 8, 1898, a supplemental injunction was issued by the county judge requiring the defendants to absolutely desist and refrain from diverting any part of the waters of said creek from the land of the plaintiff, and from filling in the bed of said stream, in whole or in part, at any place between its banks upon above plaintiff’s said lands, and from constructing or maintaining any ditch across the said bend of said river.” Subsequently the defendants moved to modify such injunctional orders, which the plaintiff opposed, and moved to punish the defendants for contempt for the [333]*333violation of such injunctional orders. Upon the hearing of such motions, and after considering the pleadings and affidavits upon which they were respectively based, the circuit court, on October 6, 1898, found, in effect, that the defendants and each of them was and is guilty of a technical violation of the injunction so issued by the county judge, in that piling and some material was put into the bed of said stream by the defendants after the service of the second in-junctional order, and that the defendants pay a fine of $1,. and the costs of such motion, taxed at $20, and the sheriff’s; fees in serving the order to show cause on which such matter was so founded, taxed and allowed at $15.70, and the-, clerk’s fees, taxed at $1.25, making in all the sum of $36.95.. Subsequently the cause was tried upon the merits, and, in-addition to the facts stated, the court found, in effect, that. August 1, 1898, the defendant supervisors entered into a. contract with the defendants Greutzmachers to repair such highway.by taking out both of the sixty-foot bridges, and replace the south bridge with a twelve-foot bridge, and fill up the bed of the stream at the north bridge with an embankment thirty-eight feet wide, and to place under such embankment eighteen-inch tiling, thirty-eight feet long, for the flow of the stream, and to cut a ditch on the west side of the highway opposite such lands, from the south bank of the stream west of the north bridge to the north bank of the stream west of the south bridge, such ditch to be dug deep enough so that the bottom of the north end thereof should be three feet above the then stage of water in such stream, which was then very low,” and the south end thereof to run to the level of the water in such stream; that the south bank of the river west of the north bridge was to-be protected by plank -and posts to a height of three feet from the bottom of such ditch down to the surface of said stream; that the defendants Greutzmachers commenced to do the work in accordance with such contract, August 15, [334]*3341898; that such stream was and is subject to annual rises of from four to six feet above the stage of water at the time ■of the taking out of such bridges, and the tiling so threatened and intended by the defendants to be put in the place of said north bridge would have been entirely insufficient to allow the water annually and usually flowing in •said stream to enter and flow across the lands of the plaintiff, as it had been wont to do from time out of mind; that if such work so contracted and so threatened to be done by' the defendants had been accomplished the result thereof would have been to divert from the plaintiff’s lands, and from their natural channel, the waters of said stream, to the permanent and irreparable injury and damage of the plaintiff; and, as conclusions of law, the court found, in effect, that the defendants had no right to divert such stream, or any portion thereof, from the lands of the plaintiff; that at •the time of the commencement of this action the plaintiff was entitled to the temporary injunctions mentioned, and was entitled to judgment perpetually enjoining and restraining the defendants from doing anything to obstruct the flow of the water in such stream upon and off his said lands, and ordered judgment accordingly, but without costs, except as therein stated. From the judgment so entered, the defendants bring this appeal. They also appeal from the order •so entered punishing them for contempt.

The order adjudging the defendants guilty of contempt, and all papers, affidavits, orders, interrogatories, and answers upon which it was based, are each and all entitled in this action. The contempt proceedings were instituted by and for the benefit of the plaintiff. The issue made up in such contempt proceedings was strictly between the parties, and was tried by the court in pursuance of the statutes. Secs. 3480-3482, 3487, 3488, Stats. 1898. Upon such trial the court •only found that the defendants were “guilty of a technical violation ” of such injunctional order so made by the county [335]*335judge, “in that piling and some material was put into the bed of said stream by the defendants after the service of ” that order, and also required the defendants to pay, for the, benefit of the plaintiff, $36.95 costs, in addition to the fine of gl.

The section of the statutes applicable to such a proceeding for a mere civil contempt provides that “if . '. . the ■court shall adjudge the defendant to have been guilty of the misconduct alleged, and that the misconduct was calculated to or actually did defeat, impede or prejudice the rights or remedies of any party in an action or proceeding pending in such court, it shall proceed to impose a fine or to imprison him, or both, as the nature of the case shall require.” Sec. 3189, Stats. 1898. The statute is mandatory, but the trial court made no such adjudication or finding. It was not the ■case of misconduct committed in the immediate view and presence of the court, and hence calling for summary punishment. Sec. 3478, Stats. 1898. Nor was it a case calling for an exercise of the inherent power of the court to punish as and for a criminal contempt. Sec. 2565; State ex rel. Att'y Gen. v. Circuit Court 97 Wis. 1. The proceedings were to enforce the civil remedy of the plaintiff, and to protect his rights in the action. But no finding or adjudication in his favor was made as required by the statute, and hence the order was made without authority. It affected the substantial rights of the defendants, and was made in a special proceeding, and is therefore appealable. State ex rel. Meggett v. O'Neill,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emerson v. Huss
106 N.W. 518 (Wisconsin Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
83 N.W. 633, 107 Wis. 331, 1900 Wisc. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcevoy-v-gallagher-wis-1900.