This text of 5 A.D.3d 854 (McEntee v. Ace Homes, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Appeal from an order of the Supreme Court (Nolan, Jr., J.), entered May 7, 2003 in Saratoga County, which, inter alia, denied plaintiffs’ motion for summary judgment.
Plaintiffs cancelled a contract to purchase a modular home from defendant before the manufacturer had commenced work on the home. When defendant refused to return any part of their $12,800 deposit, plaintiffs commenced this action and defendant counterclaimed for damages allegedly sustained as a result of the cancellation. Both parties eventually moved for summary judgment. Supreme Court found a threshold factual issue as to whether plaintiffs’ cancellation was justified by unreasonable delays or was an anticipatory breach and, accordingly, did not reach the other issues asserted by the parties. Plaintiffs’ appeal focuses on the issues not addressed by Supreme Court. We agree with Supreme Court that there is a factual question on the threshold issue of whether there has been any breach and we discern no reason to address the other issues at this juncture.
Crew III, J.P., Carpinello, Rose and Kane, JJ., concur. Ordered that the order is affirmed, with costs.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
5 A.D.3d 854, 772 N.Y.S.2d 633, 2004 N.Y. App. Div. LEXIS 2229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcentee-v-ace-homes-inc-nyappdiv-2004.