McEnanny v. Kyle

14 Daly 268, 8 N.Y. St. Rep. 358
CourtNew York Court of Common Pleas
DecidedJune 6, 1887
StatusPublished
Cited by1 cases

This text of 14 Daly 268 (McEnanny v. Kyle) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McEnanny v. Kyle, 14 Daly 268, 8 N.Y. St. Rep. 358 (N.Y. Super. Ct. 1887).

Opinion

Allen, J. —

This is an appeal from a judgment in favor of the plaintiff against the defendant James Kyle entered upon a verdict and also from an order denying a motion for a new trial.

The action was brought to recover damages for personal injuries. The defendants James, Robert, and John M. Kyle were partners engaged in business as builders and real estate agents, and the defendant John Bannon was a mason and contractor. The defendants Kyle were the owners of the building No. 232 East 45th Street in this city, which at the time of the accident to the plaintiff was in the process of construction and had progressed to about the fifth story, the front being partly up.

The defendant James Kyle prepared the plans and specifications of the building, and they were approved by the building department, and the defendant Bannon by an agreement in writing contracted to do the mason work according to the plans in a workmanlike manner. The contract for the carpenters’ work was made with Watkins Brothers, who agreed to furnish and put up all the materials called for in the carpenters’ plans and specifications.

It was shown that the defendant Bannon was in good standing as a contractor and mason, and had been known to the defendant for seven or eight years, and that the carpenters were competent contractors extensively engaged in [270]*270business, and had been known to the defendant Kyle for about ten years. The defendant Kyle testified that he had full confidence in their doing the work.

The mason Bannon, for the purpose of raising brick to the upper floors for use in the building, had hired a hoisting machine which was' worked by men in his employ, and was in use on the 25th day of March, 1884, the day of the accident, for raising brick, mortar, and stones to the fifth story.

On the morning of the 25th day of March, 1884, the defendant James Kyle employed the plaintiff to clear out some rubbish from the cellar. He had previously been in the employ of Bannon on this building and was dismissed the day before the accident. About five o’clock in the afternoon of the 25th day of March, the plaintiff and a fellow-workman were filling a barrow in the cellar, a few feet from the light shaft near the westerly side of the building, when a mass of brick, stone, and timber fell upon them, and the plaintiff was injured and his fellow-workman killed. The carriage way from the fifth story to the cellar was broken down between the trimmer beams on the west side of the well-hole.

Inspector Osborne, of the building department, who examined the building every day when it was in the process of erection, testified that he found nothing in the carpenters’ work to criticise or find fault with; that the work was properly done and the timbers properly supported. 'About eleven o’clock on the morning of the accident he visited the building and found about fifteen hundred brick or more on the beams of the fifth story, and a few stones. He told the men who were hoisting the brick and stones, in the presence, of the foreman of the defendant 'Bannon, “ not to overload the beams; if they did, they would have them in the cellar.” He also testified that the cause of the accident was the overloading the fifth story with brick, and that he could account for it in no other way.

The witness Hine went upon the fifth story in the morning, and saw the machine hoisting the brick, and the brick dumped alongside the well-hole, and told the laborers that [271]*271if they kept on that way they would break the house down. He went there also in the afternoon, and estimates the number of the brick on the platform as between three or four-thousand, weighing about three tons. He spoke to "Bannon’s brother, who was the foreman, and said to him, “ Don’t you pile too many brick here; if you do, you will have this broken down.” Bannon then said something about the expense of hoisting them, and then said, “ we want to get rid of this hoisting machine, which costs us ten dollars a day. We want to get rid of it to-day, if we can hoist brick enough to put up our front.”

At the close of plaintiff’s case, and also at the close of all the testimony, the defendants Kyle moved to dismiss the complaint, on the ground that there was no evidence showing negligence on their part, or notice or knowledge of omission on the part of Bannon to properly perform his contract, and that it appeared from the evidence that the only authority Kyle had over the work was to see that the masons’ and carpenters’ work was done according to the contract.

The relation existing between the plaintiff and the defendant Kyle was that of master and servant. The duty of Kyle to the plaintiff as such master was to exercise ordinary and reasonable care in furnishing a safe and proper-place in which to prosecute the work which he was engaged to perform, and competent fellow-workmen.

The contract which the law implies between master and servant does not make the master an insurer of the servant’s safety, or the safety of the place in which he is to do his work. He is bound only to the exercise of ordinary and reasonable care in that respect, and if the master has failed in his duty in 'this regard, and in consequence of such failure the servant has been injured, he may recover of the master, provided he is without fault on his part, and has not, voluntarily and with knowledge or competent means of knowledge of th.e danger, assumed the risks or the consequences of his master’s negligence.

The defendant Kyle’s liability in this case to the plaintiff, [272]*272depends, therefore, upon the decision of the question whether the defendant Kyle complied with Ms duty to the plaintiff in accordance with the principles of law above stated. '

It is conceded that the accident which caused the plaintiff’s injuries occurred from one of two causes : either from insufficient support of the beams in the fifth story, or from the extraordinary load of brick and stone which was placed upon these beams. It seems almost a certainty, as testified to by the inspector of the building department, that the accident was caused solely by improperly overloading the place near the edge of the carriage way with brick and stone by the defendant Bannon and his workmen. As the accident was brought about in the manner above stated, the defendant Kyle’s liability must depend upon some negligence on Ms part connected with the cause of the accident as above stated. No other neglect or omission of duty is shown.

The defendant Bannon, and the carpenters Watkins Brothers, cannot be deemed the servants of the defendant Kyle; they were independent contractors. The written contracts in evidence in the case show tlris. They were to do the brick work and the carpenter work of the house respectively, according to the plans and specifications, and no right of control or direction of the work by the owner was reserved in the contract. They employed and discharged their own servants, and represented their employer only as to the results. Kyle had the undoubted right to examine the building as the work progressed to see that proper materials were used, and that the work was done in accordance with the contract. Bannon testifies that Kyle never directed the work to be done different • from his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rotter v. Goerltiz
12 N.Y.S. 210 (New York Court of Common Pleas, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
14 Daly 268, 8 N.Y. St. Rep. 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcenanny-v-kyle-nyctcompl-1887.