McElroy v. the Snider Company, Unpublished Decision (6-29-2000)

CourtOhio Court of Appeals
DecidedJune 29, 2000
DocketNo. 76418.
StatusUnpublished

This text of McElroy v. the Snider Company, Unpublished Decision (6-29-2000) (McElroy v. the Snider Company, Unpublished Decision (6-29-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McElroy v. the Snider Company, Unpublished Decision (6-29-2000), (Ohio Ct. App. 2000).

Opinion

Plaintiff-appellant, Raymond McElroy, appeals the decision of the Cuyahoga County Court of Common Pleas granting the motion for summary judgment of defendant-appellee, The Snider Company. For the reasons that follow, we affirm.

In January 1996, appellee, an Ohio corporation engaged in the development of commercial and residential properties, contracted with Mraz Associates, Inc., a construction management company, to act as construction manager for the construction of two office buildings at separate construction sites.

As part of its construction management services, Mraz Associates hired appellant as project superintendent. In a letter to appellant dated March 1, 1996, Mraz Associates specified that appellant was being retained as an independent contractor to The Snider Company at the rate of $1,100 per week. The letter stated further that appellant's services [would] commence approximately mid-April and will be for the duration of the construction, approximately ten months later.

As project superintendent, appellant was responsible for the day-to-day operations at the construction sites, including supervising and coordinating the work of the various subcontractors on the projects, assisting the subcontractors in layout work and working with municipal inspectors and utility company representatives. Mraz Associates also designated appellant as Safety Officer for the projects, which involved conducting meetings regarding safety with the subcontractors and monitoring the work sites to ensure a safe work environment.

Appellant began working for appellee in May 1996. As the work progressed at the construction sites, David Snider, president of The Snider Company, and Bernard Mraz, president of Mraz Associates, who both periodically visited the construction sites, became concerned about appellant's job performance. On two occasions when he was visiting the construction sites, Snider observed appellant sleeping on the job. On another occasion, Snider observed a subcontractor excavating and grading one of the sites. When Snider asked appellant if he was checking the grades, appellant informed Snider that it was not his responsibility to do so.

Mraz also observed problems with appellant's job performance. On one occasion, Mraz saw a subcontractor pouring footers for the elevator pit, even though the architectural drawings called for a slab, instead of footers. According to Mraz, as project superintendent, appellant should have made sure the subcontractor was following the architectural drawings. Mraz also observed that the concrete poured by the subcontractor honeycombed because of the subcontractor's failure to use the proper equipment. Consequently, appellee incurred additional expense in hiring another company to test the strength of the concrete. According to Mraz, appellant should have made sure [the subcontractor] was using the proper equipment.

On another occasion, when one of the subcontractors was installing storm pipes and another subcontractor was preparing to excavate the site for a temporary driveway, Mraz observed that appellant did not have a transit on the site to verify the elevations for the installation of the pipes and the driveway excavation. When Mraz asked appellant where his transit was, appellant informed him it was at home. According to Mraz, as project superintendent, appellant should have had a transit on site to double-check the subcontractors' work.

According to Mraz, he also received many telephone calls from subcontractors on the project that made it pretty apparent that * * * [appellant] did not understand the [architectural] drawings or sequence of the project. In addition, Mraz Associates received an invoice from a surveying company that included charges for supplemental layout and engineering work that appellant, as project superintendent, should have performed himself.

Jeff Cardinal, who was hired by Mraz Associates in July 1996 to assist as construction manager for the projects, once observed a subcontractor working on the foundation while appellant sat in his truck, listening to the radio and exercising with weights.

On October 15, 1996, Mraz Associates terminated appellant's employment with appellee. Although he had not contacted OSHA prior to his termination, subsequent to the termination of his contract, appellant contacted the local OSHA office by telephone to report various safety violations at the construction sites and complain that his contract had been terminated in retaliation for enforcing OSHA regulations at the sites. Appellant later filed a written complaint with OSHA. OSHA subsequently dismissed appellant's complaint.

Appellant subsequently filed a three-count complaint against appellee and Mraz Associates, alleging breach of contract, termination in violation of public policy and intentional infliction of emotional distress.

Thereafter, the trial court granted the motions for summary judgment filed by appellee and Mraz Associates. Appellant timely appealed the trial court's decision granting summary judgment in favor of appellee. He did not appeal the judgment in favor of Mraz Associates.

Appellant's single assignment of error states:

THE TRIAL COURT ERRED IN GRANTING DEFENDANT, THE SNIDER COMPANY'S, MOTION FOR SUMMARY JUDGMENT BECAUSE MR. McELROY RAISED A GENUINE ISSUE OF MATERIAL FACT REGARDING THE PROPRIETY OF HIS TERMINATION.

Appellant contends that the trial court erred in granting appellee's motion for summary judgment because there are genuine issues of material fact regarding whether appellee terminated his employment without just cause, thereby breaching his employment contract.

As an initial matter, we note that appellee's motion for summary judgment addressed all three counts of appellant's complaint. On appeal, however, appellant challenges only the trial court's ruling regarding his breach of contract claim. Accordingly, we will not consider the trial court's ruling with respect to appellant's claim that he was terminated in violation of public policy or for intentional infliction of emotional distress.

This court reviews the lower court's grant of summary judgment de novo in accordance with the standards set forth in Rule 56(C) of the Ohio Rules of Civil Procedure. North Coast Cable v. Hanneman (1994), 98 Ohio App.3d 434, 440. Summary judgment is appropriate when (1) there is no genuine issue of material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) after construing the evidence most favorably for the party against whom the motion is made, reasonable minds can reach only a conclusion that is adverse to the non-moving party. Zivich v. Mentor Soccer Club, Inc. (1998), 82 Ohio St.3d 367, 369-370; Temple v. Wean United, Inc. (1977), 50 Ohio St.2d 317, 327. To obtain a summary judgment under Civ.R. 56(C), the moving party bears the initial responsibility of informing the court of the basis for the motion and identifying those portions of the record which support the requested judgment. Vahila v. Hall (1997), 77 Ohio St.3d 421, 430. If the moving party discharges this initial burden, the party against whom the motion is made then bears a reciprocal burden of specificity to oppose the motion. Id. See, also, Mitseff v. Wheeler (1988), 38 Ohio St.3d 112. Any doubts must be resolved in favor of the non-moving party. Murphy v. Reynoldsburg (1992),65 Ohio St.3d 356, 358-359.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zimmerman v. Eagle Mortgage Corp.
675 N.E.2d 480 (Ohio Court of Appeals, 1996)
North Coast Cable Ltd. Partnership v. Hanneman
648 N.E.2d 875 (Ohio Court of Appeals, 1994)
Dayton Rubber Mfg. Co. v. Brown
156 N.E. 136 (Ohio Supreme Court, 1927)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Mitseff v. Wheeler
526 N.E.2d 798 (Ohio Supreme Court, 1988)
Murphy v. City of Reynoldsburg
604 N.E.2d 138 (Ohio Supreme Court, 1992)
Vahila v. Hall
674 N.E.2d 1164 (Ohio Supreme Court, 1997)
Zivich v. Mentor Soccer Club, Inc.
696 N.E.2d 201 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
McElroy v. the Snider Company, Unpublished Decision (6-29-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcelroy-v-the-snider-company-unpublished-decision-6-29-2000-ohioctapp-2000.