McElraevy & Hauck Co. v. St. Joseph's Home for Girls

143 N.Y.S. 235
CourtCity of New York Municipal Court
DecidedJuly 30, 1913
StatusPublished
Cited by1 cases

This text of 143 N.Y.S. 235 (McElraevy & Hauck Co. v. St. Joseph's Home for Girls) is published on Counsel Stack Legal Research, covering City of New York Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McElraevy & Hauck Co. v. St. Joseph's Home for Girls, 143 N.Y.S. 235 (N.Y. Super. Ct. 1913).

Opinion

CRAGEN, J.

These two actions, which were tried together, were brought to recover the sums of $300 and $370, respectively, and arise out of the following circumstances:

For a number of years prior to the year 1911, the defendant institution had in its Home at Flushing, L. I., two horizontal tubular boilers, used for heating the premises. In August, 1911, the Allsop Heating Company, plaintiff’s assignor, inspected the defendant’s premises with a view of making repairs to said boilers, and after suqh inspection the said Heating Company wrote to the defendant, submitting a proposition as to the cost of such repairs, with an alternative proposition for the removal of the poorer one of said boilers and the installation of a new boiler, to be connected with the remaining old one, and advising the defendant that the alternative proposition was the most advisable one to accept. This .proposition, as far as material to a disposition of this action, is as follows:

“We will disconnect and remove one of the old horizontal tubular boilers now on premises, furnish and erect one Allsop ‘Economy’ water tube safety steam boiler of 5,000 square feet capacity, cross-connecting same with the better of the twp old boilers, so that either one or both boilers can be used together or separately, with all necessary pipe and fittings, valves, gauge, damper regulator, fire tools, etc., complete, making repairs to the better one of the two horizontal tubular boilers as advised by the boiler inspector, all for net sum of thirteen hundred ($1,300) dollars.”

This proposition was accepted by the defendant, and the Heating Company in the fall of 1911 removed one of the old boilers, and caused a boiler of the name and make contained in its proposition to be duly installed, which was connected with the old remaining boiler. No mention is made in said proposition of securing insurance on the boiler, although the president of the Heating Company admitted on the stand that he had agreed to do so, and the fact that he did is borne out by his company’s letter of March 9, 1912. Subsequently the boiler was inspected by an inspector of the Fidelity & Casualty Company, and insurance refused, on the ground that the boiler was structurally defective. Much controversy was then had, between the Heating Company and the defendant, regarding the boiler; the defendant contending that the boiler was not as represented, in that it failed to perform the work or the results expected of it, and was insufficient in capacity, which controversy resulted in the defendant refusing to accept the boiler.

In the discussion regarding the merits of the boiler, the Heating Company maintained that the difficulty, if any, was due to the defects in the main and return piping, and the fact that the boiler could not show good results by reason of its being connected with the old remaining boiler. The controversy mentioned continued down to June, 1912, when the Heating Company submitted a further proposition to the defendant, for the removal of the remaining old and the installation of a second new boiler, and the erection of new piping, in place of what it contended was defective, for the sum of $1,107. This proposition was also entertained by the defendant. The evidence is not clear when the defendant made a payment on account, but in any event there was due $1,000 on the first contract when the second proposition [238]*238was submitted. Upon the acceptance of the second proposition, the Heating Company contends that it proceeded with the work, in the meantime having received the further sum of $700, which it credited on the first contract, leaving a balance of $300, to recover which the first action was brought.

The Heating Company never installed the second boiler, although it removed the second old one, and had the new one on the premises, preparatory to installation, when it contends the second contract was modified to the effect that it agreed to take back the second new boiler and cancel the second contract, in consideration of the defendant agreeing to pay the sum of $370, which the Heating Company claimed represented its outlay for material and labor to the date of cancellation, which sum is the subject of the second cause of action.

[1, 2] Considerable evidence was given on the -trial as to the capacity of the boiler installed, with the usual conflicting opinion of experts. Suffice to say, however, the evidence established that the boiler falls far short of producing the guaranteed 5,000 square feet of radiation. The testimony of Mr. Peterson and Mr. Murdock, two of the experts, which I consider the most reliable on the subject of capacity, and both of whom arrive at practically the same conclusion, is to the effect that, working the boiler under the most favorable circumstances, it nevertheless falls short approximately one-third of the guaranteed heating capacity. By reference to the pleadings, it will be seen that the theory upon which the first cause of action is predicated is that the Heating Company performed its contract; otherwise speaking, the plaintiff, as the assignor of the Heating Company, alleges full performance of the contract on the part of the Heating Company, and not substantial performance. Can it be said, under the circumstances, that the contract was performed? I think not. The defendant was entitled to have a complete boiler placed upon its premises of the guaranteed capacity and of insurance thereon, as agreed. Performance of a contract consists in doing the thing agreed to be done, and the burden is on the plaintiff, suing upon a contract, to show performance, and not upon the defendant to show that the plaintiff has not performed. Vernon v. Vulcanite Portland Cement Co., 119 App. Div. 39, 103 N. Y. Supp. 876. As was said by the Court of Appeals in a very recent case (Cameron-Hawn Realty Co. v. City of Albany, 207 N. Y. 377, at page 381, 101 N. E. 162, at page 163): I

“The contract establishes and determines the rights and liabilities of the parties. Their agreements create the obligations they are hound to fulfill and the court to enforce and fix the scope and limits thereof. * * * It is a well-settled rule of law that a party must fulfill his contractual obligations. Fraud or mutual mistake, or the fraud of one party, and the mistake of the other, or an inadvertence induced by the one party, and not negligence on the part of the other, may relieve from an expressed agreement, and an act of God or the law, or the interfering or preventive act of the other party, may free one from the performance of it; but if what is agreed to be done is possible and lawful, the obligation of performance must be met. Difficulty or improbability of accomplishing the stipulated undertaking will not avail . the obligor. It must be shown that the thing cannot by any means be effected. Nothing short of this will excuse nonperformance. The courts will not consider the hardship or the expense or the loss to the one party, or the meagerness or the uselessness of the result to the other. They will neither [239]*239make nor modify contracts, nor dispense with their performance. When a party by his own contract creates a duty or charge upon himself, he is bound to a possible performance of it, because he promised it, and did not shield himself by proper conditions or qualifications.”

[3, 4] Nor is it necessary for the defendant to plead a counterclaim to establish the fact of nonperformance. Ryan v. Brown (Sup.) 104 N. Y. Supp. 871.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
143 N.Y.S. 235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcelraevy-hauck-co-v-st-josephs-home-for-girls-nynyccityct-1913.