McDowell v. Allied Building Products Corp.

230 P.3d 552, 235 Or. App. 12, 2010 Ore. App. LEXIS 411
CourtCourt of Appeals of Oregon
DecidedApril 21, 2010
Docket040606718; A134348
StatusPublished
Cited by3 cases

This text of 230 P.3d 552 (McDowell v. Allied Building Products Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDowell v. Allied Building Products Corp., 230 P.3d 552, 235 Or. App. 12, 2010 Ore. App. LEXIS 411 (Or. Ct. App. 2010).

Opinion

*15 HASELTON, P. J.

Plaintiff appeals a limited judgment, challenging the dismissal of his claims concerning alleged asbestos exposure against defendants as a sanction for his violation of a court order. 1 Among other things, plaintiff contends on appeal that, because he was unable to comply with the court’s order, the trial court abused its discretion by dismissing his case. As amplified below, we affirm.

The material facts are procedural. Plaintiff filed his complaint in 2004, alleging claims concerning asbestos exposure against defendants. Two attorneys, Shadduck and Niebling, from the law firm representing plaintiff were involved in the various hearings that led to this appeal.

Plaintiffs case was one of several on the trial court’s August 2006 asbestos docket. On August 21, the trial date for all cases on the August docket, the court held a hearing with the parties’ attorneys to consider various pretrial matters, including scheduling issues and motions in limine. Among those motions were several that requested that the court conduct OEC 104 hearings outside the presence of the jury to determine the admissibility of expert testimony and other scientific evidence. 2

During the August 21 hearing, two decisions were made that are pertinent to the issues raised on appeal. First, the court deferred ruling on the motions in limine until the trial in each case had actually begun. Second, the court and the parties agreed to the “48/24” rule — that is, the parties agreed to disclose the identity of each expert 48 hours before the expert testified and to provide opposing counsel with each expert’s file 24 hours before the expert testified.

Three days later, on August 24, the court held another hearing concerning plaintiffs case. By that time, plaintiffs case was one of only two cases on the August docket *16 that had not yet been resolved. Because the court was scheduled to be gone at the beginning of the following week and because the selection of a jury, for what was scheduled to be a lengthy trial, would likely be easier after Labor Day, the court set September 5 as the first day of trial.

In sum, as of August 24, the parties understood that plaintiffs case would proceed in the following manner: (1) Trial would begin on September 5 — that is, the Tuesday after the Labor Day holiday. (2) The motions in limine would be decided when each expert was scheduled to testify — that is, after jury selection and opening statements. (3) The “48/24” rule would apply to the disclosure of expert names and files.

A week later, on August 31, the sequence of events that precipitated this appeal began. On the afternoon of August 31, at the request of the trial court, an attorney for one of the defendants sent an e-mail to the other attorneys in the case, including Niebling. That e-mail indicated that the trial court had scheduled a pretrial hearing for the next day — -that is, September 1, the Friday before the Labor Day weekend — at 10:00 a.m. According to the e-mail, one purpose of the hearing was to “take up some motions in limine prior to trial.” (Emphasis added.)

Because plaintiffs other attorney, Shadduck, had planned to be out of town from the afternoon of August 31 through the morning of September 1, Niebling appeared at the hearing. While addressing the motions in limine, the trial court noted that plaintiffs case had “striking similarities” to another case on the August asbestos docket and that “on [its] own motion” it was “reconsidering” and would “make an order concerning defendant’s motions in limine.”

Specifically, the court stated:

“I believe that there are serious issues here concerning causation that trigger a careful analysis of the Oregon Evidence Code and are requiring * * * Rule 104 hearing[s] before we bring a jury in.”

(Emphasis added.) The court identified five motions in limine that it intended to address during the OEC 104 hearings *17 on the following Tuesday — that is, September 5 — and reiterated:

“On these motions, I’m going to start Tuesday off — your case is set at 9 o’clock. I’m going to conduct a Rule 104 hearing, which I expect to be extensive, and deal, among other things, with these scientific evidence issues on the matters that I’ve indicated.”

In sum, contrary to the parties’ understanding when they arrived at the hearing (and to the procedure the court had outlined as of August 24), the trial court had significantly changed course, ruling that the OEC 104 hearings concerning the pertinent motions in limine would occur before the jury was selected and not thereafter when each expert was scheduled to testify.

In the colloquy that followed, one defendant sought the names of plaintiffs experts so that defendants could prepare over the weekend for the Tuesday morning OEC 104 hearings. The trial court agreed. Niebling’s primary response was that plaintiff would be “ready to go on Tuesday” according to the procedure that the court had outlined as of August 24. Significantly, however, he did not object to the trial court’s rulings at the hearing concerning the exchange of expert names and files and the appearance of those experts on Tuesday morning. Instead, he provided the court with the names of some of plaintiffs experts and indicated that Shadduck would have additional information that afternoon. The court concluded by cautioning plaintiff:

“So that’s the sequence [in which the experts will be examined]. And plaintiff needs to have these people here and ready to go. Plaintiff is at risk, plaintiff — and I had to warn plaintiffs on [one of the other asbestos cases], if you don’t have witnesses here and ready to go, you’re at risk of the Court granting a motion to dismiss for failure of prosecution.
* * Hi ❖
“So I also expect everyone to exchange all of the other information and documents prior to trial that’s supposed to be exchanged. And things are just going to go — you know, one step after another.”

*18 The court’s ruling was embodied in an order that provided, in part:

“IT IS HEREBY ORDERED THAT an OEC Rule 104 hearing will be conducted at 9:00 a.m. on September 5, 2006. At this hearing, plaintiff will bear the burden to establish the admissibility and qualification of the experts listed below and each witness will state each of their opinions and the basis for those opinions. In conjunction with this Order and the Court’s previous Order regarding the disclosure of an expert’s entire file twenty-four hours prior to offering testimony, plaintiff must produce the entire files of the experts noted, below by 5:00p.m. today, September 1, 2006.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgan and Morgan
340 Or. App. 272 (Court of Appeals of Oregon, 2025)
State of Washington v. Steven K. Young
Court of Appeals of Washington, 2016

Cite This Page — Counsel Stack

Bluebook (online)
230 P.3d 552, 235 Or. App. 12, 2010 Ore. App. LEXIS 411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdowell-v-allied-building-products-corp-orctapp-2010.