McDonough Construction Co. of Florida v. Hanner

232 F. Supp. 887, 1964 U.S. Dist. LEXIS 6576
CourtDistrict Court, M.D. North Carolina
DecidedAugust 21, 1964
DocketC-2-WS-63
StatusPublished
Cited by3 cases

This text of 232 F. Supp. 887 (McDonough Construction Co. of Florida v. Hanner) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonough Construction Co. of Florida v. Hanner, 232 F. Supp. 887, 1964 U.S. Dist. LEXIS 6576 (M.D.N.C. 1964).

Opinion

EDWIN M. STANLEY, Chief Judge.

This is an action by the plaintiff, a Florida corporation, against the defendant, a citizen and resident of North Carolina, to recover damages for breach of contract to submit a dispute to arbitration.

At the final pre-trial conference, the parties stipulated that the issue of liability should be heard and determined by the court without a jury, and that in the event the issue of liability was determined favorably to the plaintiff, the issue of damage would then be determined by a jury unless the parties stipulated that the issue might be determined by the court or a master.

In accordance with said stipulation, the issue of liability was tried by the court without a jury. At the conclusion of the trial, the parties were afforded an opportunity to file briefs in support of their respective positions. The briefs having been received, the court, after considering the pleadings and evidence, including exhibits, and stipulations filed, and the briefs and arguments of the parties, now makes and files herein its Findings of Fact and Conclusions of Law, separately stated:

FINDINGS OF FACT

1. The plaintiff is a Florida corporation, and maintains its principal office and place of business in a state other than North Carolina.

2. The defendant is a citizen and resident of the State of North Carolina.

3. Sometime in advance of June 22, 1962, the plaintiff, a corporation engaged in the construction business, was awarded a contract to construct an office and warehouse building in Forsyth County, North Carolina, for the Crescent City Leasing Corporation.

4. On June 22, 1962, the plaintiff and defendant entered into a sub-contract, designated as Sub-contract 64-13, wherein the defendant was to perform certain cement work in the building being erect *889 ed by the plaintiff. The sub-contract contained the following arbitration clause:

“Article XI — Any controversy or claim arising out of or relating to this Sub-contract or any breach thereof shall be settled by arbitration in accordance with the rules, then obtaining, of the American Arbitration Association, and judgment upon the award rendered may be entered into any court having jurisdiction thereof. It is mutually agreed that the decision of the arbitrators appointed in accordance with said rules shall be a condition precedent to any right of legal action that either party may have against the other.”

5. The defendant proceeded with the work under the sub-contract. Before the completion of the work, however, the plaintiff notified the defendant, both orally and by mail, that said sub-contract had been terminated because of the unacceptability of the work being performed by the defendant.

6. On September 28, 1962, counsel for the defendant wrote the plaintiff acknowledging receipt of the notice of termination of the sub-contract, protesting that the termination was unwarranted, and demanding payment of $5,632.25, representing the amount alleged to be due the defendant for work performed and materials furnished. On October 19, 1962, counsel for the defendant again wrote the plaintiff advising that unless satisfactory arrangements for the settlement of the defendant’s claim had been made by October 26, 1962, “legal action” would be instituted.

7. ■ Payment of the amount alleged to be due under the sub-contract not having been received, S. E. Hanner, the defendant herein, on October 30, 1962, instituted a civil action in the Superior Court •of Forsyth County, North Carolina, against McDonough Construction Company of Florida, the defendant herein, seeking recovery of the sum of $5,634.25, with interest, representing the amount alleged to be due for work performed and materials furnished under the aforementioned sub-contract. On December 21, 1962, McDonough Construction Company of Florida filed its answer to the complaint in the State Court action, denying the amount claimed by S. E. Hanner and counterclaiming in the amount of $20,086.75, by reason of alleged defective work performed by S. E. Hanner. Before filing the State Court action, S. E. Hanner filed a sub-contractor’s lien with Crescent City Leasing Corporation, the owner of the property upon which the office and warehouse building was being constructed. No reference was made in any of the pleadings filed in the State Court action to the arbitration clause in the sub-contract.

8. On January 3, 1963, this action was instituted. The plaintiff herein seeks recovery against the defendant herein of $25,000.00 for damages for its trouble and expense in defending the State Court action, damage to “its good name and business reputation” by reason of the sub-contractor’s lien being filed with Crescent City Leasing Corporation, and damage to its “good name and business reputation” by reason of being subjected to a civil damage suit in a State Court, all on account of the defendant herein not having first submitted the dispute to arbitration as required by Subcontract 64-13.

9. There was no demand by either party that the dispute concerning the unsatisfactory completion of Sub-contract 64-13 be submitted to arbitration before the filing of the State Court action or before the filing of this action. Each party simply made demands upon the other with respect to the dispute, but neither made any mention of the provisions of the sub-contract relating to arbitration.

10. On April 2, 1963, while both suits were pending, counsel for McDonough Construction Company of Florida wrote counsel for S. E. Hanner and requested that the dispute between the parties be referred to arbitration, and expressed a willingness to submit to a voluntary dis *890 missal of both actions and let the arbitrators decide the entire controversy. Counsel for S. E. Hanner replied that since McDonough Construction Company of Florida had refused to discuss the dispute with S. E. Hanner in the past, and had refused to pay S. E. Hanner the amount claimed for work performed and materials furnished, and had terminated the sub-contract without any opportunity for discussion or arbitration, S. E. Hanner declined to agree to arbitration at that late date.

11. Prior to the trial of this action, the State Court action was tried in the Superior Court of Forsyth County and resulted in S. E. Hanner obtaining a judgment against McDonough Construction Company of Florida for $5,634.25, with interest, the full amount sought in that action, and McDonough Construction Company of Florida being denied any recovery on its counterclaim. No appeal was taken within the time provided by law, and the State Court judgment thereby becoming final.

DISCUSSION

The question for decision is whether there can be any recovery of damages for breach of a contract to submit future disputes to arbitration. If this question is answered in the affirmative, there is then presented the question of whether the plaintiff in this case waived the breach.

The contract under consideration, while between citizens of different states, was entered into in the State of North Carolina for work to be performed in North Carolina, and does not involve interstate or foreign commerce. The United States Arbitration Act 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collie v. Wehr Dissolution Corp.
345 F. Supp. 2d 555 (M.D. North Carolina, 2004)
Warren Bros. v. Community Building Corp. of Atlanta, Inc.
386 F. Supp. 656 (M.D. North Carolina, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
232 F. Supp. 887, 1964 U.S. Dist. LEXIS 6576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonough-construction-co-of-florida-v-hanner-ncmd-1964.