McDonald v. Windermere Construction Co.

41 Va. Cir. 177, 1996 Va. Cir. LEXIS 471
CourtFairfax County Circuit Court
DecidedDecember 2, 1996
DocketCase No. (Law) 146632
StatusPublished

This text of 41 Va. Cir. 177 (McDonald v. Windermere Construction Co.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald v. Windermere Construction Co., 41 Va. Cir. 177, 1996 Va. Cir. LEXIS 471 (Va. Super. Ct. 1996).

Opinion

By Judge Dennis J. Smith

On October 31,1996, this matter came before this Court on Windermere Construction Company’s Plea in Bar to the Plaintiffs’ Second Amended Motion for Judgment. Windermere argues that § 8.01-250 of the 1950 Code of Virginia, a five-year statute of repose, bars the Plaintiffs claim for damages which arises out of an alleged unsafe installation of a stove. Counsel disagreed as to what date initiated the running of the statute of repose under the facts in this case. Following the submission of briefs and a hearing where testimony and evidence were provided, the question was taken under advisement.

This action arose from an injury to Plaintiffs’ daughter, which occurred on April 3,1995. Suit was filed on October 26, 1995. The action seeks to hold Windermere, one of many defendants, liable for the negligent failure to install a stove anti-tip device which is alleged to have caused the injury. Windermere was the general contractor hired in 1989 to renovate an apartment complex owned by Defendant Fairfield Crossing Associates. Windermere hired subcontractors to do the actual renovation work. According to testimony, the renovation done to each apartment in the complex was extensive and included replacement of major appliances such as the stove that is involved in this case. Testimony revealed that the renovation of the entire complex proceeded on an apartment-by-apartment basis as each became vacant. Plaintiffs’ apartment at 2901 Dover Lane, Apt. T2 (“T2”), was one of the apartments renovated under the contract, and it is not disputed that the stove at issue was replaced in the renovation of T2.

[178]*178At the October31,1996, hearing, this court found that the Plaintiffs’ claims as to the defendants who were subcontractors were time barred by § 8.01-250. The subcontractors were hired to provide construction services on an apartment-by-apartment basis. Their obligations ended upon completion of their work on each apartment, and they may or may not have been hired to do further work at the project site. However, in applying the statute to the subcontractors, it was not necessary to determine whether it was the date that they installed the stove in T2 or completed their renovation work in T2 which triggered the statute of repose as either date fell outside the statutory period for bringing a claim.

Virginia’s statute of repose, § 8.01-250, states in relevant part:

[n]o action to recover for any injury to property, real or personal, or for bodily injuiy or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained as a result of such injury, shall be brought against any person performing or furnishing the design, planning, surveying, supervision of construction, or construction of such improvement to real property more than five years after the performance of furnishing of such services and construction.

Section 8.01-250, Va. Code (Michie 1992). The question here is whether a suit filed against the general contractor on October 26,1995, is titne barred by the five-year period under this staute.

Windermere in its Plea argues that the appropriate date for the commencement of the five-year period is the date the stove was installed in T2, in August of 1990. In the alternative, Windermere argues that the appropriate date is when renovation work on apartment T2 was completed, before the end of September 1990. Using either date, any claim for faulty construction would thus be time barred. However, Plaintiffs insist that the running of the time limit in § 8.01-250 begins on the date that the renovation of the entire apartment complex was completed. The parties agreed that if the court ruled that the completion of the project was the proper commencement date, then the issue of establishing that date would be reserved for presentation of proof at trial.

Plaintiffs, in their briefs and oral argument, have relied primarily on the decision in Federal Reserve Bank of Richmond v. Wright, 392 F. Supp. 1126 (E.D. Va. 1975). Plaintiffs insist that this case requires a finding in the present [179]*179situation that the period of repose in § 8.01-250 begins to run on the date that Windermere completed the entire renovation project.1 Federal Reserve Bank of Richmond involved a suit brought under former Va. Code § 8-24.2, the predecessor to § 8.01-250.2 There, a claim was brought against architects who were hired to provide architectural, engineering, and supervisory services for the design and construction of the Communications and Records Center of the Federal Reserve Bank. The Court considered whether the statute contemplated more than one commencement date, with the selection of the appropriate date depending upon whether the cause of action arose from negligent design rather than negligent construction. The Court held that “a reasonable construction of the statute would suggest a single limitation period to run from the final completion date of the entire project, whether the claim arises from faulty design or from faulty construction.” Federal Reserve Bank of Richmond, 392 F. Supp. at 1130 (emphasis added). In Powell v. Gilbane Bldg. Co., 34 Va. Cir. 12 (1994), Judge Bach of this Court adopted this same interpretation of the statute.

In this case, application of the Federal Reserve Bank of Richmond holding would mean that the action against Windermere would not be time barred. However, Windermere urges that the question in the present case is not answered by Federal Reserve Bank of Richmond and presents several arguments in support. Windermere argues, inter alia, that as Plaintiffs have only alleged negligent installation of a stove and not negligence in construction of the entire complex, the contract between Windermere and Fairfield Crossing Apartments is not relevant to a determination of the commencement date for the statute of repose issue. An analysis of the purpose of the statute of repose, however, suggests otherwise.

In Hess v. Snyder Hunt Corp., 240 Va. 49 (1990), the Virginia Supreme Court decided the constitutionality of § 8.01-250. In that case, the defendant [180]*180was a construction contractor for an apartment complex and was sued by a tenant for negligent construction of a balcony. The defendant filed pleas in bar alleging that the plaintiffs claims were extinguished by § 8.01-250 because all work was completed on the building in question more than five years prior to the filing of the lawsuits. Relevant to the issue in the present case, the Court discussed the rationale behind Virginia’s statute of repose. “Statutes of repose evince a legislative policy decision that after the expiration of a specific time, a defendant should no longer be subjected to liability.” Hess, 240 Va. 49 at 52.

Construction projects can be expected to last for many years after their completion. The owner or occupier of the project will be exposed to long-term liability because he will remain responsible for the maintenance of the project. With the abolition of lack of privity as a defense ... building contractors may be subject to liability. However, absent a statute of repose ... [a] building contractor also would be exposed to long-term liability, even though their work had long since been completed ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hess v. Snyder Hunt Corp.
392 S.E.2d 817 (Supreme Court of Virginia, 1990)
Federal Reserve Bank of Richmond v. Wright
392 F. Supp. 1126 (E.D. Virginia, 1975)
Powell v. Gilbane Building Co.
34 Va. Cir. 12 (Fairfax County Circuit Court, 1994)
Wiggins v. Proctor & Schwartz, Inc.
330 F. Supp. 350 (E.D. Virginia, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
41 Va. Cir. 177, 1996 Va. Cir. LEXIS 471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-v-windermere-construction-co-vaccfairfax-1996.