McDonald Construction Co. v. Bituminous Casualty Corp.

632 S.E.2d 420, 279 Ga. App. 757
CourtCourt of Appeals of Georgia
DecidedMay 24, 2006
DocketA06A0633, A06A0634
StatusPublished
Cited by10 cases

This text of 632 S.E.2d 420 (McDonald Construction Co. v. Bituminous Casualty Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald Construction Co. v. Bituminous Casualty Corp., 632 S.E.2d 420, 279 Ga. App. 757 (Ga. Ct. App. 2006).

Opinion

Ellington, Judge.

In Case No. A06A0633, McDonald Construction Company, Inc. (‘McDonald”) appeals from the grant of partial summary judgment to its insurer, Bituminous Insurance Companies (“Bituminous”) in this contract dispute involving a Commercial General Liability (“CGL”) policy. McDonald contends the trial court erred in finding, as a matter of law, that portions of its claim were not covered under the CGL policy. In a cross-appeal, Case No. A06A0634, Bituminous contends the trial court erroneously denied summary judgment on McDonald’s remaining claims, arguing that those claims also were not covered under the CGL policy. For the following reasons, we find that Bituminous was entitled to summary judgment on McDonald’s entire claim. Therefore, we affirm the trial court’s judgment in part and reverse in part.

“Summary judgment is appropriate when no genuine issues of material fact remain and the moving party is entitled to judgment as a matter of law. We review the trial court’s grant of summary judgment de novo, construing the evidence and all reasonable conclusions and inferences in favor of the nonmovant.” (Footnotes omitted.) SawHorse, Inc. v. Southern Guaranty Ins. Co. &c., 269 Ga. App. 493 (604 SE2d 541) (2004).

In its order granting partial summary judgment to Bituminous, the trial court included a recitation of the relevant evidence based upon the undisputed evidence in the record. We adopt it here, as follows:

In 1998[,] McDonald Construction Company entered into a contract to renovate and remodel Jennings Homes, a housing project owned by the Augusta Housing Authority. The project involved the remodeling and renovating of 26 buildings consisting of 150 separate apartment units. McDonald began its work on the project in 1998, and subcontracted the application of vinyl composition tile flooring (“VCT”) to Co-Defendant Augusta Tile Crafters, Inc. As part of the remodel job, McDonald purchased, and its employees installed, plywood underlayment on the second floor of the various apartment buildings. Augusta Tile performed its work on the site from 1999 through 2001. The Bituminous Defendants issued various [CGL] policies to McDonald, each covering one-year periods effective January 10,1999, January 10, 2000, and January 10, 2001, respectively.
*758 Some time shortly after Augusta Tile began its subcontracted work on the project in 1999, a few individual VCT tiles delaminated, or came unstuck, from their plywood underlayment on the second floor of certain of the apartments. It is undisputed there were no problems with any of the tile applied on the first floor. Individual tiles sporadically delaminated throughout the rest of the project. When the tiles came unstuck[,] they were repaired.
By February 2001, McDonald had completed the final punchlist requirements and the Housing Authority had occupied all the buildings. After McDonald completed its work, the architect discovered that most of the second floor tiles had delaminated, prompting the architect to issue an order of condemnation with respect to the tile.

The record also shows that, in his February 5, 2001 condemnation letter, the architect stated that the delaminated tiles failed to comply with contract specifications and instructed McDonald to correct the problem. McDonald hired experts to determine the cause of the delamination, but the experts disagreed as to the cause of the problem. Several months later, on September 21, 2001, the Housing Authority sent a letter to McDonald demanding that it immediately repair the delaminated tiles. According to McDonald, the Housing Authority refused to accept the project “as it was” because the tile flooring was not satisfactory or in accordance with the contract. Although the Housing Authority expressed concern that the loose tiles created a hazard that could cause an injury if they were not repaired promptly, there is no evidence of any injury which resulted from the delaminated tiles. Further, there is no evidence in the record of any damage to the building or other property caused by the delaminated tiles or that the Housing Authority ever asked McDonald to pay for any property damage. The Housing Authority withheld $150,000 under the construction contract, to be paid when McDonald completed the necessary repairs to the floors. McDonald then hired a different subcontractor to install replacement tiles. Before the subcontractor installed the tiles, McDonald’s employees moved furniture from the second-story apartments and removed the old tiles. After the replacement tiles were installed, McDonald’s employees moved the furniture back into the apartments. McDonald paid the subcontractor $91,745 for replacing the tiles. McDonald also estimated that it had incurred approximately $14,000 in labor costs for moving the furniture and preparing the floors for the new tiles. Once the repairs were complete, the Housing Authority paid McDonald the funds that had been withheld.

*759 On December 7, 2001, McDonald sent a claim letter to Bituminous asking for $154,655.80 under its CGL policy. This amount included the following expenses: the costs of labor to move the furniture and remove the delaminated tiles, the subcontractor fees to install the replacement tiles, equipment rental, and material and supplies. McDonald also demanded reimbursement for the costs of testing to determine the cause of the delamination, lost overhead and profit, attorney fees, gas and travel costs, and the costs of lodging for trips to Augusta. 1 McDonald did not assert a claim for any liability it had incurred for injuries to a third party or to damage to property belonging to the Housing Authority or a third party. Instead, McDonald repeatedly acknowledged that its claim under the CGL policy for the costs it incurred to replace the tiles arose from its legal obligation under the construction contract to properly install the tiles, not from any tort liability.

After Bituminous denied the claim, McDonald sued Bituminous for breach of contract. Bituminous answered and asserted a counterclaim for declaratory judgment on its obligations to McDonald under the CGL policy. Following a hearing on both parties’ motions for summary judgment, the trial court found that McDonald incurred the costs of replacing the delaminated tiles due to its contractual obligations to the Housing Authority, and not due to any tort claim arising from the loose tiles. The court found that the costs to replace the tile were part of the “risk borne by the contractor to make the building project conform to the agreed contractual requirements.” Based upon these findings, 2 the court granted Bituminous partial summary judgment on McDonald’s claim for the cost of the subcontractor who replaced the tile. The court also found, however, that the other costs incurred by McDonald, such as the cost of moving the furniture, might be considered “damage to other property” under the contract. Therefore, the court denied summary judgment to Bituminous on the remaining portions of McDonald’s claim. Both McDonald and Bituminous appeal from the court’s order.

Determination of the issues herein requires us to construe the provisions of the subject insurance policy under the facts of record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor Morrison Services, Inc. v. HDI-Gerling America Insurance
746 S.E.2d 587 (Supreme Court of Georgia, 2013)
Maxum Indemnity Company v. Jose Jimenez
Court of Appeals of Georgia, 2012
Maxum Indemnity Co. v. Jimenez
734 S.E.2d 499 (Court of Appeals of Georgia, 2012)
Hathaway Development Co. v. American Empire Surplus Lines Insurance Co.
686 S.E.2d 855 (Court of Appeals of Georgia, 2009)
Bollers v. Noir Enterprises, Inc.
677 S.E.2d 338 (Court of Appeals of Georgia, 2009)
Stoker v. Severin
665 S.E.2d 913 (Court of Appeals of Georgia, 2008)
Gentry MacHine Works, Inc. v. Harleysville Mutual Insurance
621 F. Supp. 2d 1288 (M.D. Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
632 S.E.2d 420, 279 Ga. App. 757, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-construction-co-v-bituminous-casualty-corp-gactapp-2006.