McDermott v. Fletcher

155 A.D. 615, 140 N.Y.S. 871, 1913 N.Y. App. Div. LEXIS 5171

This text of 155 A.D. 615 (McDermott v. Fletcher) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDermott v. Fletcher, 155 A.D. 615, 140 N.Y.S. 871, 1913 N.Y. App. Div. LEXIS 5171 (N.Y. Ct. App. 1913).

Opinion

Laughlin, J.:

This is an action to recover a balance agreed to be paid by the defendant to the plaintiffs for work, labor and services, less the cost of performing certain work which plaintiffs claim they were prevented from doing.

The plaintiffs were copartners engaged in the business of building construction work, and the defendant was the executor of H. J. Braker, deceased, who evidently died seized of the premises known as 42 West Thirty-fifth street, upon which the Hotel Gregorian had been erected. As the hotel was originally constructed there were six suites of rooms on each floor, each suite consisting of a parlor, bedroom and bath. The defendant, who, as executor, was conducting the hotel through one Bitchey as “director” or “Manager,” determined to change each suite into single room suites, which required the construction of a bathroom for the parlor of each of the former suites. Plans and specifications for the work and material required to make these changes had been prepared for defendant by an architect. On the 12th day of July, 1910, the plaintiffs entered into a contract in writing with the defendant for the performance of all or substantially all of the work and the furnishing of all of the material incident to these changes, excepting that relating to the plumbing, and it was provided that the work was to be done according to the drawings and specifications made by the architect, and that the contractors were to receive therefor the sum of $7,600, which the defendant agreed to pay in two installments, the first of $1,000 when the plastering was completed, “except patching,” and the balance when the work was completed. It was expressly provided that the work should be of “ the same quality, quantity and style as the work of the present building,” and that it [617]*617should he performed “ in a first class manner ” and completed on or before the 1st day of September, 1910, and if not so completed the defendant was given the right “within 5 days at his election ” to remove the contractor and to finish the work and to deduct the cost of completion from the contract price. It ivas further provided in the contract that if the contractors should fail to perform any work for a period of three days the owner might elect to deem the contract abandoned and complete the work at the expense of the contractor, and that all payments under the contract were “to be made only on the written certificate ” of the architect.

The contract contains no express provision with respect to the order in which the work was to be done. Specifications printed in the record with the contract contain provisions tending to show that it was understood that the possession of the hotel was not to be delivered over to the contractors during the progress of the work and that it was not to be closed; but a stipulation in the record shows that the specifications printed in the record were neither received in evidence nor marked for identification, and, therefore, the objection to their consideration is well taken.

On the fifth day after the date of the contract the plaintiffs wrote the architect complaining that Ritchey, the manager of the hotel, stated that he could not give them the entire space to work on at once and that it would be necessary for them to do the work in the rear of the hotel first and that they could not disturb the front until the rear was completed, which, they charged, was not in accordance with the understanding and would require more time and would interfere with their payments under the contract and added in effect that they would expect the payments “ to be changed according to how we proceed,” and expressed the hope that this might be satisfactorily arranged. Testimony given by one of the plaintiffs tends to show, as claimed in their letter, that it was understood that the work might be continued in the front and rear of the hotel at the same time. The preliminary negotiations for the contract on the part of the defendant were conducted by Ritchey who obtained the proposition from the plaintiffs and recommended its acceptance. The defendant attempted to [618]*618show by Ritchey’s testimony' that during the negotiations it was understood between him and the plaintiffs that the work was to be done without interfering with the business of the hotel, but on objections interposed by counsel for the plaintiffs the conversations on this subject were excluded. This, we think, was error, for the reason that the contract was silent on on the subject of the order in which the work was to be done, and one of the plaintiffs had been permitted to give testimony from which an inference to the contrary might be drawn. The plaintiffs, after writing the architect as stated commenced work on or about the 19th of July, 1910, in the apartments in the rear of the hotel and the other apartments continued to be used for hotel purposes; but plaintiffs continued to demand that they be given possession of the front apartments. There was subsequent delay in the progress of the work for which the owner was responsible, and it appears that the plaintiffs were not given possession of as many apartments at a time as they desired. According to the testimony of the architect he justly complained of delay on the part of the plaintiffs and charged that they did not have a sufficient force of men at work and from time to time complained both with respect to material furnished and workmanship, and that in some respects neither the material nor workmanship was in accordance with the contract.

On September 10, 1910, $2,000 was paid to apply on the contract, and on October third the plaintiffs requested a further payment of $2,000. Replying to this request under date of October fourth the architect stated that there was still work to be done before the bathrooms in the rear of the hotel could be used, but that in his opinion “with a little effort ” on the part of the contractors the remaining work could be finished that week, and that he' would consult the defendant with respect to the payment requested. On the third of October the architect had written to the plaintiffs that certain work in the bathrooms in the rear of the hotel had not been finished and that there was only one man at work there, and demanded that a sufficient force be employed to complete the work at once. On the fourth the plaintiffs replied to this letter expressing surprise at the claim with respect to the unfinished work, and stated that [619]*619they considered that they had completed the work “with the exception of a little painting.” The plaintiffs had been insisting that they be permitted to proceed with the work in the front part of the building and by letter under date of October thirteenth they reqiiested that the architect let them know when they would be permitted so to do. On the same day the architect wrote them that he saw no effort being made on their part to complete the work and making an appointment to meet them, and on that day Ritchey wrote them by specifying certain unfinished work in the rear of the hotel which rendered it impossible for the hotel to use the rooms and asked when they intended to proceed with the work in the front of the hotel. The plaintiffs replied to this letter on the fourteenth, asserting that they had been endeavoring to arrange with the architect with respect to completing the work but had been unable to obtain any information, and insisted on their right to complete the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Exchange National Bank v. Woodlawn Cemetery
120 A.D. 119 (Appellate Division of the Supreme Court of New York, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
155 A.D. 615, 140 N.Y.S. 871, 1913 N.Y. App. Div. LEXIS 5171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdermott-v-fletcher-nyappdiv-1913.