McDANIEL BROS. CONSTRUCTION COMPANY v. Jordy

195 So. 2d 922
CourtMississippi Supreme Court
DecidedMarch 20, 1967
Docket44277
StatusPublished
Cited by26 cases

This text of 195 So. 2d 922 (McDANIEL BROS. CONSTRUCTION COMPANY v. Jordy) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDANIEL BROS. CONSTRUCTION COMPANY v. Jordy, 195 So. 2d 922 (Mich. 1967).

Opinion

195 So.2d 922 (1967)

McDaniel BROS. CONSTRUCTION COMPANY, Inc., Defendant-Appellant,
v.
Walter S. JORDY, d/b/a Jordy Associates, Plaintiff-Appellee.

No. 44277.

Supreme Court of Mississippi.

March 6, 1967.
Suggestion of Error Overruled March 20, 1967.

*923 Young, Young & Scanlon, Jackson, for appellant.

Watkins & Eager, William E. Suddath, Jr., Jackson, for appellee.

PATTERSON, Justice.

This is an appeal from the Circuit Court of Hinds County, sitting without a jury, wherein a judgment of $6,000 was entered for plaintiff as a result of a breach of contract.

The case has been before this Court previously on a jurisdictional question dealing with whether a circuit court has authority to enter a judgment in vacation.

Walter S. Jordy, a building contract broker, brought suit originally for breach of contract, claiming a loss of profit in the amount of $6,004. McDaniel Bros. Construction Company, Inc., hereinafter referred to as McDaniel, claimed there was no contract and consequently no breach. The circuit court, as trier of the facts, found that the contract had been breached and entered judgment for Jordy in the sum of $3,000. Jordy filed a motion to correct judgment or for judgment notwithstanding the verdict, and after the court term had ended, the trial judge set aside the original judgment and in vacation of the court entered another judgment for Jordy in the amount of $6,004. This action was reversed on appeal (254 Miss. 839, 183 So.2d 501 (1966)), this Court holding that Jordy's motion was still pending and that the circuit judge could rule on the motion during any regular or properly extended term. Thereafter Jordy filed a motion for entry of judgment, and on May 19, 1964, during a regular term, the circuit judge held, without opinion, that the prior judgment of August 6, 1964, should be changed; he then entered a judgment against McDaniel for $6,000, plus interest at 6% per annum, from August 6, 1964, the date of the original trial.

McDaniel assigns as error the following:

1. The verdict and the judgment of the lower court are contrary to the overwhelming weight of the evidence.

2. The trial court erred in finding that a contract existed between the parties, that a breach had been committed by the appellant, and that the appellee was entitled to damages.

3. The lower court erred in sustaining appellee's motion for entry of judgment and by entering a judgment against the appellant in the sum of $6,000 plus interest from the date of the original trial.

4. The lower court erred by setting aside its original judgment of August 6, 1964, and at a later term entering a judgment for twice the amount of the original judgment.

I.

The disputed contract involved the purchase and installation of windows in a hospital to be constructed at Corinth, Mississippi. McDaniel, as a general contractor, was bidding for the prime contract for the hospital job when Jordy submitted his offer on June 3, 1963, to furnish and install aluminum windows and window walls. Jordy talked by long distance telephone with McDaniel, president of appellant, on June 7, 1963, in regard to Jordy's proposal, and he suggested that Jordy submit a package bid which would include the glazing of windows. Jordy and McDaniel met on June 12, 1963, and when Jordy proposed the price of $36,000 to include his original offer plus the glazing, McDaniel accepted his bid, according to appellee's testimony. On June 17, 1963, McDaniel wrote Jordy in reference to the Corinth hospital project. The body of the letter is as follows:

This letter is to confirm our agreement for the purchase of certain materials required *924 for this project which are listed as follows:
All window, window wall requirements including panels completely erected in accordance with plans and specifications.
1. All glass, glazing and mirror requirements in accordance with plans and specifications.
The above items are to be furnished and installed in accordance with all contract documents as prepared by the office of Overstreet, Ware, Ware & Lewis, architects, for a total lump sum of $36,000.00.
This confirmation is based on a contract being awarded to this office. In the event this contract does not go through this letter is void.

McDaniel signed the prime contract to build the Corinth hospital on June 24, 1963. McDaniel denied that the letter of June 17, 1963, to Jordy represented a contract. He stated it was a letter written at the request of Jordy to be used as part of a financial statement to obtain a line of credit. He testified it was written merely as a favor and that both he and Jordy knew the letter did not constitute a binding contract.

As trier of the facts, the trial court found that there was a contract between McDaniel and Jordy. The trial judge observed and heard the witnesses and the testimony. All negotiations and actions were directed toward a contract, and although there were some details not definitely agreed upon, a firm contract was established in the letter of June 17, 1963, conditioned only upon the obtaining of the prime contract by McDaniel.

We have reviewed the testimony and the exhibits and have concluded that there was sufficient evidence introduced for the trial judge to find that the parties entered into a contract. The findings of the trial court should and must be accepted unress they are manifestly wrong. United States Fidelity & Guaranty Co. v. State, 211 Miss. 864, 53 So.2d 11 (1951). We are of the opinion this assignment of error is not well taken.

II.

Jordy testified that he had an arrangement with Burton Brothers, Inc. whereby this company would furnish certain materials and fulfill the construction requirements imposed upon Jordy by the subcontract for its part in the construction of the hospital. Burton Brothers' payment for its participation in the subcontract, by the testimony of Jordy, was to be an equal division of the profits anticipated by Jordy to be received under his contract with McDaniel in the estimated sum of $6,004 for the $36,000 bid. The lower court judgment in favor of Jordy was for $6,000.

Appellee contends that this judgment is correct since he is entitled to recover profits which would have been realized if the contract had been performed, and that even though he may later have to account to Burton Brothers, he is still entitled to collect the total damages in his own name. In support of this argument he cites the cases of United States Finance Co. v. Barber, 247 Miss. 800, 157 So.2d 394 (1963) and Cottrell v. Smith, 146 Miss. 837, 112 So. 465 (1927).

McDaniel argues that the measure of Jordy's damages is the difference between what he was to receive and what it would cost him to do the job. B. Bluethenhal Co. v. McDougal, 163 Miss. 406, 141 So. 291 (1932) and Jones v. Griffin, 157 Miss. 256, 126 So. 35 (1930). Out of the $6,004 sum due to Jordy from McDaniel as a "profit" was to come the half due Burton Brothers from Jordy as an "expense" for doing the job. Jordy was a contract broker. He was not going to do the actual work since that was Burton Brothers' responsibility according to their agreement. Jordy was to supply the job and Burton Brothers was to supply the work, and had agreed additionally to waive any commissions on materials furnished. The record reflects, however, *925 that Burton Brothers had furnished no materials or labor in regard to the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson HMA, LLC v. Morales
130 So. 3d 493 (Mississippi Supreme Court, 2013)
Morris Newspaper Corp. v. Allen
932 So. 2d 810 (Court of Appeals of Mississippi, 2005)
Wilson v. General Motors Acceptance Corp.
883 So. 2d 56 (Mississippi Supreme Court, 2004)
Purdon v. Locke
807 So. 2d 373 (Mississippi Supreme Court, 2001)
Temple-Inland Mortg. Corp. v. Jones
749 So. 2d 1161 (Court of Appeals of Mississippi, 1999)
J. S. Purdon v. Larry Locke
Mississippi Supreme Court, 1999
Independent Healthcare Management, Inc. v. City of Bruce
746 So. 2d 881 (Court of Appeals of Mississippi, 1998)
Shields v. State
702 So. 2d 380 (Mississippi Supreme Court, 1997)
Peoples Bank and Trust Company v. Cermack
658 So. 2d 1352 (Mississippi Supreme Court, 1995)
Wasserman's Inc. v. Township of Middletown
645 A.2d 100 (Supreme Court of New Jersey, 1994)
Polk v. Sexton
613 So. 2d 841 (Mississippi Supreme Court, 1993)
Joseph E. Shields v. State of Mississippi
Mississippi Supreme Court, 1992
Eastland v. Gregory
530 So. 2d 172 (Mississippi Supreme Court, 1988)
Varvaris v. Kountouris
528 So. 2d 800 (Mississippi Supreme Court, 1988)
Matter of Estate of Varvaris
528 So. 2d 800 (Mississippi Supreme Court, 1988)
UHS-Qualicare, Inc. v. GULF COAST COM. HOSP., INC.
525 So. 2d 746 (Mississippi Supreme Court, 1987)
Aetna Cas. & Sur. Co. v. Doleac Elec. Co.
471 So. 2d 325 (Mississippi Supreme Court, 1985)
McCain v. Cox
531 F. Supp. 771 (N.D. Mississippi, 1982)
NAACP v. Claiborne Hardware Co.
393 So. 2d 1290 (Mississippi Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
195 So. 2d 922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdaniel-bros-construction-company-v-jordy-miss-1967.