McCurry v. Eppolito

506 So. 2d 1110, 12 Fla. L. Weekly 1166, 1987 Fla. App. LEXIS 8169
CourtDistrict Court of Appeal of Florida
DecidedMay 6, 1987
DocketNo. BJ-231
StatusPublished
Cited by2 cases

This text of 506 So. 2d 1110 (McCurry v. Eppolito) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCurry v. Eppolito, 506 So. 2d 1110, 12 Fla. L. Weekly 1166, 1987 Fla. App. LEXIS 8169 (Fla. Ct. App. 1987).

Opinion

NIMMONS, Judge.

McCurry appeals from a final judgment in a nonjury case awarding Mr. and Mrs. Eppolito damages in their legal malpractice action against appellant. We affirm.

In December 1980, the Eppolitos engaged Broward Builders, Inc., as the general contractor to construct their new home. The contract price for the construction project was $356,275. Thereafter, difficulties began to develop with the general contractor and it became necessary for the general contractor to be terminated. Mr. Eppolito first consulted with McCurry regarding the termination of the general contractor on July 7, 1981. With the assistance of McCurry, the contractor was terminated on July 9, 1981.

Construction of the project recommenced at approximately the end of July. The cost of completion, when added to the amounts previously paid to Broward Builders — a total of $495,238 — was approximately $140,-000 more than the original contract price.

Both prior and subsequent to completion, various subcontractors of Broward Builders filed mechanics’ liens against the Eppo-litos’ residence because they had not been paid for work done in connection with the construction. All of such liens related to work done prior to the termination of the original contractor, Broward Builders.

As a result of failing to comply with the procedures of the Mechanics’ Lien Law surrounding recommencement, the appellees were subjected to mechanics’ lien claims in excess of $50,000. Appellees also necessarily expended in excess of $5,000 in legal fees to defend such actions.

It is the appellees’ position that their liability for the payment of the mechanics’ liens was the direct and proximate result of McCurry’s negligence in failing to comply with the procedures of the Mechanics’ Lien Law surrounding recommencement. Mr. Eppolito testified that he and his wife consulted McCurry for his representation on all items surrounding the termination of his general contractor and any future legal problems that the Eppolitos might encounter in dealing with their construction project. Thus, according to appellees, McCurry owed them a duty to comply with the Mechanics’ Lien Law requirements concerning recommencement and such a duty was breached.

McCurry, on the other hand, maintains that his employment was limited to the termination of the general contractor. He claims that because of the limited scope of [1112]*1112his employment, he did not owe a duty to appellees to comply with the Mechanics’ Lien Law requirements.

We are satisfied that the evidence established a duty on the part of McCurry to see that the requirements of the Mechanics’ Lien Law regarding recommencement of construction were complied with and that McCurry did, in fact, breach such duty.

In order to understand the legal duty that was owed by McCurry in this case, it is necessary to review the provisions of Florida’s Mechanics’ Lien Law regarding recommencement of construction.

When a contractor has been terminated and the owner desires to complete the construction project, a specific procedure must be followed in accordance with the Mechanics’ Lien Law. Section 713.07(4), Florida Statutes (1981)1 provides:

(4) If construction ceases before completion and the owner desires to recommence construction, he may pay all lien-ors in full or pro rata in accordance with s. 713.06(4) prior to recommencement in which event all liens for the recommenced construction shall take priority from such recommencement; or the owner may record an affidavit in the clerk’s office stating his intention to recommence construction and that all lienors giving notice have been paid in full except those listed therein as not having been so paid in which event 30 days after such recording, the rights of any person acquiring any interest, lien or encumbrance on said property or of any lienor on the recommenced construction shall be paramount to any lien on the prior construction unless such prior lienor records a claim of lien within said 30-day period. A copy of said affidavit shall be served on each lienor named therein. Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.

This section sets out the specific procedure an owner must follow when the original construction ceases before completion, regardless of the cause, and the owner desires to complete the project. The procedure essentially involves two steps.

The first step gives the owner, in recommencing construction, the option of either

(a) paying all lienors in full or pro rata in accordance with the provisions of the statute, or
(b) recording an affidavit of intention to recommence construction stating that all lienors giving notice to him have been paid in full, except for those lienors listed in the affidavit.

The second step is for the owner, prior to recommencement, to record a new notice of commencement for the recommenced construction, pursuant to Section 713.13, Florida Statutes (1981). See Leiby, Florida Construction Law Manual § 7.05 (1981).

Furthermore, these documents must be filed before construction is actually recommenced, and not, as argued by the appel-lees, before payments are made under the resumed construction. This is evident from the language of Sections 713.07(4) and 713.13(l)(a), Florida Statutes. Section 713.07(4), as previously set forth, provides that “[i]f construction ceases before completion and the owner desires to recommence construction, he may pay all lienors ... prior to recommencement ..or the owner may record an affidavit in the clerk’s office stating his intention to recommence construction_ Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.” (e.s.) Section 713.13(l)(a) provides:

(l)(a) An owner or his authorized agent before actually commencing to improve any real property, or recommencing completion of any improvement after default or abandonment, whether or not a project has a payment bond complying with s. 713.23, shall record a notice of commencement in the clerk’s office.... (e.s.)

The effect of an owner’s failure to file an affidavit of intention to recom-[1113]*1113menee construction and a new notice of commencement is twofold. First, and relevant to our case, the owner loses his right to set-off the cost of completing the improvement from the amount of the initial contract price to defeat the claims of lien-ors arising from the original construction. See 2 Rakusin, Florida Mechanics’ Lien Manual, Ch. 14, p. 9 (1974); Tamarac Village, Inc. v. Bates & Daly Co., 348 So.2d 23 (Fla. 4th DCA 1977); MacIntyre v. Torres, 358 So.2d 101 (Fla. 3rd DCA 1978); and Melnick v. Reynolds Metals Co., 230 So.2d 490 (Fla. 4th DCA 1970).2

When the original construction ceases before completion, whether by abandonment by the contractor or the owner’s termination of the contractor, the owner can insure that payment of lien claims on the original work will not exceed the amount of the original contract price by filing the affidavit of intention to recommence construction and recording a new notice of commencement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merkle v. Robinson
737 So. 2d 540 (Supreme Court of Florida, 1999)
Zaleznik v. Gulf Coast Roofing Co., Inc.
576 So. 2d 776 (District Court of Appeal of Florida, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
506 So. 2d 1110, 12 Fla. L. Weekly 1166, 1987 Fla. App. LEXIS 8169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccurry-v-eppolito-fladistctapp-1987.