Mcclure And Sons v. Department Of Labor & Industries

CourtCourt of Appeals of Washington
DecidedMarch 15, 2021
Docket80588-6
StatusUnpublished

This text of Mcclure And Sons v. Department Of Labor & Industries (Mcclure And Sons v. Department Of Labor & Industries) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mcclure And Sons v. Department Of Labor & Industries, (Wash. Ct. App. 2021).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

MCCLURE & SONS, INC., ) No. 80588-6-I ) Appellant, ) ) DIVISION ONE v. ) ) STATE OF WASHINGTON, ) DEPARTMENT OF LABOR AND ) INDUSTRIES, ) ) UNPUBLISHED OPINION Respondent. ) )

MANN, C.J. — McClure and Sons (MSI) appeal a Board of Industrial Insurance

Appeals (Board) final order, contending that there was insufficient evidence to support

the five construction worksite violations that they were cited with by the Department of

Labor and Industries (Department). MSI also argues that it was unfairly prejudiced by

the Board’s exclusion of evidence concerning the inspector’s conduct. We affirm.

FACTS

MSI is an industrial contractor with offices in Washington and Oregon. MSI was

the general contractor for a new riverfront sewer pump and lift station for the City of

Everett, adjacent to the Snohomish River. The project consisted of two sites separated

Citations and pin cites are based on the Westlaw online version of the cited material. No. 80588-6-I/2

by approximately one-half mile: Lift/Pump Station No. 43 (Station 43) and Lift/Pump

Station No. 33 (Station 33). Station 43 was in close proximity to two sets of energized

power lines—a set of high voltage power lines and a separate, lower-voltage set.

On February 8, 2016, Mark Valgardson, a compliance and safety officer for the

Department drove by the site and observed two cranes with the booms extended near

power lines. Valgardson spoke with John Orgorolka, MSI’s project manager, and Loren

West, the project superintendent, who gave Valgardson permission to inspect the site.

MSI built Station 43 by constructing a concrete structure that went 20 to 30 feet

into the earth. Axis Cranes, a subcontractor to MSI, used a Liebherr 1225 hydraulic

boom crane to drive interlocking tongue-and-groove sheets of steel (piles) into the

ground, then poured concreted into the mold created by the piles. When Valgardson

arrived, the concrete had set and MSI was removing the piles with a vibra hammer

connected to the crane.

During the inspection, Valgardson discovered that the Liebherr crane operating

at Station 43 did not have a range limiting device or an alarm to prevent the crane from

getting too close to the power lines, a hazard known as encroachment. Valgardson

measured the distance from the base of the crane’s boom to the area immediately

beneath the power line (center pin to drip line) which measured 103 feet, 8 inches. The

crane operated the hydraulic boom at two different lengths: 117 feet and 134 feet.

Valgardson believed that the crane could have made contact with the power lines.

Because the crane’s boom tip, load block, and vibra hammer were made of conductive

steel, if the crane came too close to the power lines, it would expose the workers to

electrocution hazards.

-2- No. 80588-6-I/3

Valgardson observed that there was no work zone demarcation at the site. MSI

disagreed, and their expert witness, Mark Lawless, testified that the iron beams laid out

on the ground demarcated the work zone, serving as a template while the workers

drove the piles into the ground, and then the piles themselves demarcated the zone as

MSI extracted them vertically. Valgardson testified that there were no flags on the sheet

pile wall, or any other flags or other high visibility materials to demarcate the work zone

anywhere on the jobsite.

Valgardson did not find an elevated warning line at the site as required by code.

Valgardson testified that a warning line is “preferably red tape off the ground supported

by a cone, a stick, a sandwich board, all indicating vertically the maximum approach to

the power lines.” West told Valgardson that MSI used orange “snow fence” as a

warning line. Valgardson believed that the snow fence was “nowhere near compliant,”

as it “meandered through the site,” and was “wadded up on the ground” at some points.

Valgardson assisted the crew with constructing an elevated warning line.

Valgardson observed that there was not a dedicated spotter on site for the crane.

A spotter functions to “accurately gauge the crane’s proximity, the crane’s boom, the

crane’s load line or the crane’s load to the power lines and [to] be able to communicate

that immediately to the crane operator and be in a position where he can make that

observation.”

Larry Lindborg, a certified crane operator, worked as the crane’s oiler. Lindborg

testified that he would act as the crane’s spotter when the crane would sling over the

power lines with its boom, creating danger. Lindborg testified that he was the

designated spotter on certain days, but not for the whole project. As the oiler, Lindborg

-3- No. 80588-6-I/4

was responsible for making sure that the crane stayed level and did not tip over. The

pile buck, Paul Walters, identified himself as the spotter, but Valgardson opined that he

was not in the position to accurately gauge the location of the crane boom or load lines

in relationship to the power lines.

At Station 33, Valgardson observed a Favco Hydraulic Boom Crawler crane with

an elevated boom. The crane held a load in an excavation and it had a nylon sling

wrapped around a pipe in the ground. Valgardson observed that the crane was holding

the pipe while the concrete dried and was actively involved in the worksite. Although

the crane operator, Jason Kelkenberg, initially said that the Favco crane was certified,

when Valgardson returned the next day (February 9, 2016), Kelkenberg explained that

he misspoke, and said the crane was not certified in Washington. Kelkenberg had

removed the crane from service at this point. Additionally, Kelkenberg explained that

the load moment indicator—which gives the crane operator a read of the weight of the

load, the boom length and angle, and produces an “overhoist or overload” warning—

was nonfunctional.

As part of the inspection, Valgardson reviewed MSI’s accident prevention

program (APP). While there were 14 crane-specific rules in the plan, none covered

crane operations around power lines. Valgardson believed that the plan was deficient

because it lacked information on “power line safety, requirements and prohibitions,

rigging and signaling, as well as Washington State crane certification inspection and

load test language.”

The Department cited MSI with violating five regulations under Washington

Industrial Safety and Health Act of 1973 (WISHA), ch. 49.17.73 RCW. The Department

-4- No. 80588-6-I/5

grouped three serious power line safety violations together and issued one penalty.

The power line citations were: (1) MSI violated WAC 296-155-53401(5)(i) because it

failed to carry out the site supervisor’s duties by allowing crane operations near power

lines without first meeting the requirements of WAC 296-155-53408; (2) MSI violated

WAC 296-155-53408(2)(a)(i)(A) because it did not define a work zone by demarcating

boundaries and prohibiting the crane from operating past those boundaries, or define

the work zone as the area 360 degrees around the crane up to its maximum working

radius; and (3) MSI violated WAC 296-155-53408(2)(b) because it did not take

encroachment precautions to prevent electrocution. The Department also cited MSI

with one serious violation of WAC 296-155-52901 for operating the Favco crane without

certification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MOWAT CONST. CO. v. Department of Labor and Industries
201 P.3d 407 (Court of Appeals of Washington, 2009)
Potelco, Inc. v. Department Of Labor And Industries
433 P.3d 513 (Court of Appeals of Washington, 2018)
King County Public Hospital District No. 2 v. Department of Health
309 P.3d 416 (Washington Supreme Court, 2013)
Mowat Construction Co. v. Department of Labor & Industries
148 Wash. App. 920 (Court of Appeals of Washington, 2009)
Erection Co. v. Department of Labor & Industries
160 Wash. App. 194 (Court of Appeals of Washington, 2011)
Brown v. Spokane County Fire Protection District No. 1
668 P.2d 571 (Washington Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Mcclure And Sons v. Department Of Labor & Industries, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclure-and-sons-v-department-of-labor-industries-washctapp-2021.