Mcclure And Sons, Inc., V. Stetner Electric, Inc.

CourtCourt of Appeals of Washington
DecidedJanuary 26, 2026
Docket87564-7
StatusUnpublished

This text of Mcclure And Sons, Inc., V. Stetner Electric, Inc. (Mcclure And Sons, Inc., V. Stetner Electric, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mcclure And Sons, Inc., V. Stetner Electric, Inc., (Wash. Ct. App. 2026).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

MCCLURE AND SONS, INC., a Washington Corporation, No. 87564-7-I

Respondent, DIVISION ONE

v. UNPUBLISHED OPINION

STETNER ELECTRIC, INC. d/b/a STETNER CONSTRUCTION GROUP, a Washington Corporation,

Appellant.

BIRK, J. — We are asked whether, when a general contractor incorporates

a bid from a subcontractor into its prime bid, the subcontractor is bound by its bid

despite conditioning the bid on written acceptance within seven days—written

acceptance which it did not receive. Based on the doctrine of promissory estoppel,

we answer yes, and affirm.

I

In December 2021, the City of Everett (City) issued solicitation for bids for

the Evergreen Pump Station Modification Project. To prepare its bid for the project,

McClure and Sons, Inc. (MSI), an industrial contractor, solicited bids from various

electrical subcontractors. The bid submission deadline was February 15, 2022, at

2:00 p.m. At 1:30 p.m. on February 15, thirty minutes before the 2:00 p.m.

deadline, Stetner Electric, Inc. (Stetner) e-mailed its electrical subcontractor bid to

MSI, quoting a price of $2,059,209. At 1:48, Stetner sent MSI another e-mail, No. 87564-7-I/2

stating, “We’ve received our final quote. Our pricing is updated now.” That e-mail

included a bid price of $2,709,000.

Typically, MSI closes all bids to subcontractors and suppliers 15 minutes

before the bid submission deadline. This allows them to “write in final numbers”

and “physically turn in a bid no later than” five minutes before the deadline. Ten

minutes before the bid submission deadline is the “absolute drop dead time” for

incorporating bids from subcontractors and suppliers. MSI, relying on Stetner’s

$2,709,000 bid, “marked up its own prime contract bid with a pen and submitted it

to the City just before the deadline.” At 1:50:32 p.m., Stetner sent MSI a third e-

mail stating, “Incorrect Proposal. Correct is included.” This last e-mail included a

bid price of $2,850,000. Because MSI was already in the process of submitting its

prime bid ahead of the 2:00 p.m. deadline it did not receive the $2,850,000 bid in

time to incorporate it into its submission.

Based on MSI’s prime bid, which incorporated Stetner’s $2,709,00 bid, the

City determined that MSI was the apparent lowest bidder for the project. One day

later, on February 16, Stetner e-mailed MSI informing it that “[y]esterday definitely

did not go as anticipated,” and that they were “unable to perform the project for

[$2,709,000].” Stetner apologized “for any hassles that [its] typo may have

caused,” and it indicated that $2,850,000 was the “willingly performable amount”

for the project. MSI then submitted a claim of error to the City, seeking not to be

awarded the project at the price it had bid, based on Stetner’s sub-bid. In March

2022, City staff rejected MSI’s claim of error and recommended to the city council

that it award the project to MSI at its bid price. MSI secured a preliminary injunction

2 No. 87564-7-I/3

against the city council before it awarded MSI the project. On March 28, 2022, the

court dissolved the preliminary injunction, and on March 30, the City awarded the

project to MSI for its bid price. Staff recommended to the city council that the City

“take all necessary steps to enforce MSI’s [$240,000] bid bond” if MSI failed to

execute the contract.

On April 4, an MSI division manager, John Ogorsolka, called a Stetner

project manager, Rance Ramey, and informed him that MSI had been awarded

the project contract. According to Ogorsolka, the two agreed that Stetner would

perform its subcontract for $2,850,000. Ogorsolka issued a letter of intent (LOI) to

Ramey that same day. Between April 4 and April 7, Ogorsolka exchanged phone

calls and e-mails with Ramey and with Stetner’s chief executive officer in which

Ogorsolka sought Stetner’s agreement to perform for $2,850,000. By April 7

Stetner had not signed the LOI, but Ramey assured Ogorsolka that he would call

the next day after confirming prices. After MSI received no communication from

Stetner on April 8-10, Ogorsolka sent a LOI to EC Electric, the next lowest electrical

subcontract bidder, and, on April 12, EC Electric agreed to the electrical

subcontract for the project for $3,034,932.

In January 2024, MSI filed a complaint against Stetner alleging claims for

breach of contract and promissory estoppel. MSI moved for partial summary

judgment as to entitlement. The superior court granted partial summary judgment

to MSI, reasoning that “the doctrine of promissory estoppel does apply” and that

MSI was entitled to recover. The parties stipulated to damages of $325,932, the

difference between Stetner’s $2,709,000 bid and the $3,034,932, which MSI paid

3 No. 87564-7-I/4

EC Electric for the electrical subcontracting work. In December 2024, Stetner

timely appealed.

II

Stetner argues that the superior court erred in granting summary judgment

to MSI because MSI did not accept Stenter’s bid in writing within seven days, as

required by express language in its bid, and that MSI’s reliance on Stenter’s bid

was unreasonable. Stetner’s arguments are unavailing. The elements of

promissory estoppel were met, and the superior court correctly granted summary

judgment in favor of MSI.

We review a trial court’s decision to grant summary judgment de novo.

Lakey v. Puget Sound Energy, Inc., 176 Wn.2d 909, 922, 296 P.3d 860 (2013).

We perform the same inquiry as the trial court and affirm an order for summary

judgment when there is no genuine issue of material fact and the moving party is

entitled to judgment as a matter of law. Id. We view the evidence in the light most

favorable to the nonmoving party and draw all reasonable inferences in the

nonmoving party’s favor. Id.

To prevail on a claim for promissory estoppel, the plaintiff must prove five

elements:

(1) [a] promise which (2) the promisor should reasonably expect to cause the promisee to change his position and (3) which does cause the promissee to change his position (4) justifiably relying upon the promise, in such a manner that (5) injustice can be avoided only by enforcement of the promise.

Corbit v. J.I. Case Co., 70 Wn.2d 522, 539, 424 P.2d 290 (1967). Promissory

estoppel “applies readily to the unique situation of a subcontractor and a general

4 No. 87564-7-I/5

contractor.” Ferrer v. Taft Structurals, Inc., 21 Wn. App. 832, 835, 587 P.2d 177

(1978). “A subcontractor submits a bid to a general contractor, knowing the

general cannot accept the bid as an offer immediately, but must first incorporate it

into the general’s offer to the prospective employer.” Id. The general contractor

then “incorporates the bid in reliance upon the subcontractor to perform as

promised, should the prospective employer accept the general’s offer.” Id. A

“subcontractor’s bid is considered an irrevocable offer until the award of the prime

contract; then the general contractor’s acceptance of the bid results in a bilateral

contract.” Arango Constr. Co. v. Success Roofing, Inc., 46 Wn. App. 314, 323,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arango Construction Co. v. Success Roofing, Inc.
730 P.2d 720 (Court of Appeals of Washington, 1986)
Corbit v. J. I. Case Co.
424 P.2d 290 (Washington Supreme Court, 1967)
Haselden-Langley Constructors, Inc. v. D.E. Farr & Associates, Inc.
676 P.2d 709 (Colorado Court of Appeals, 1983)
Ferrer v. Taft Structurals, Inc.
587 P.2d 177 (Court of Appeals of Washington, 1978)
Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
1 Cal. App. 5th 727 (California Court of Appeal, 2016)
Lakey v. Puget Sound Energy, Inc.
296 P.3d 860 (Washington Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Mcclure And Sons, Inc., V. Stetner Electric, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclure-and-sons-inc-v-stetner-electric-inc-washctapp-2026.