Mcclure And Sons, Inc., V. Stetner Electric, Inc.

Court of Appeals of Washington·Decided January 26, 2026·No. 87564-7·Unpublished

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

MCCLURE AND SONS, INC., a Washington Corporation, No. 87564-7-I

Respondent, DIVISION ONE v. UNPUBLISHED OPINION

STETNER ELECTRIC, INC. d/b/a STETNER CONSTRUCTION GROUP, a Washington Corporation,

Appellant.

BIRK, J. — We are asked whether, when a general contractor incorporates a bid from a subcontractor into its prime bid, the subcontractor is bound by its bid despite conditioning the bid on written acceptance within seven days—written acceptance which it did not receive. Based on the doctrine of promissory estoppel, we answer yes, and affirm.

I

In December 2021, the City of Everett (City) issued solicitation for bids for the Evergreen Pump Station Modification Project. To prepare its bid for the project, McClure and Sons, Inc. (MSI), an industrial contractor, solicited bids from various electrical subcontractors. The bid submission deadline was February 15, 2022, at 2:00 p.m. At 1:30 p.m. on February 15, thirty minutes before the 2:00 p.m. deadline, Stetner Electric, Inc. (Stetner) e-mailed its electrical subcontractor bid to MSI, quoting a price of $2,059,209. At 1:48, Stetner sent MSI another e-mail,

stating, “We’ve received our final quote. Our pricing is updated now.” That e-mail included a bid price of $2,709,000.

Typically, MSI closes all bids to subcontractors and suppliers 15 minutes before the bid submission deadline. This allows them to “write in final numbers” and “physically turn in a bid no later than” five minutes before the deadline. Ten minutes before the bid submission deadline is the “absolute drop dead time” for incorporating bids from subcontractors and suppliers. MSI, relying on Stetner’s $2,709,000 bid, “marked up its own prime contract bid with a pen and submitted it to the City just before the deadline.” At 1:50:32 p.m., Stetner sent MSI a third e- mail stating, “Incorrect Proposal. Correct is included.” This last e-mail included a bid price of $2,850,000. Because MSI was already in the process of submitting its prime bid ahead of the 2:00 p.m. deadline it did not receive the $2,850,000 bid in time to incorporate it into its submission.

Based on MSI’s prime bid, which incorporated Stetner’s $2,709,00 bid, the City determined that MSI was the apparent lowest bidder for the project. One day later, on February 16, Stetner e-mailed MSI informing it that “[y]esterday definitely did not go as anticipated,” and that they were “unable to perform the project for [$2,709,000].” Stetner apologized “for any hassles that [its] typo may have caused,” and it indicated that $2,850,000 was the “willingly performable amount” for the project. MSI then submitted a claim of error to the City, seeking not to be awarded the project at the price it had bid, based on Stetner’s sub-bid. In March 2022, City staff rejected MSI’s claim of error and recommended to the city council that it award the project to MSI at its bid price. MSI secured a preliminary injunction

against the city council before it awarded MSI the project. On March 28, 2022, the court dissolved the preliminary injunction, and on March 30, the City awarded the project to MSI for its bid price. Staff recommended to the city council that the City “take all necessary steps to enforce MSI’s [$240,000] bid bond” if MSI failed to execute the contract.

On April 4, an MSI division manager, John Ogorsolka, called a Stetner project manager, Rance Ramey, and informed him that MSI had been awarded the project contract. According to Ogorsolka, the two agreed that Stetner would perform its subcontract for $2,850,000. Ogorsolka issued a letter of intent (LOI) to Ramey that same day. Between April 4 and April 7, Ogorsolka exchanged phone calls and e-mails with Ramey and with Stetner’s chief executive officer in which Ogorsolka sought Stetner’s agreement to perform for $2,850,000. By April 7 Stetner had not signed the LOI, but Ramey assured Ogorsolka that he would call the next day after confirming prices. After MSI received no communication from Stetner on April 8-10, Ogorsolka sent a LOI to EC Electric, the next lowest electrical subcontract bidder, and, on April 12, EC Electric agreed to the electrical subcontract for the project for $3,034,932.

In January 2024, MSI filed a complaint against Stetner alleging claims for breach of contract and promissory estoppel. MSI moved for partial summary judgment as to entitlement. The superior court granted partial summary judgment to MSI, reasoning that “the doctrine of promissory estoppel does apply” and that MSI was entitled to recover. The parties stipulated to damages of $325,932, the difference between Stetner’s $2,709,000 bid and the $3,034,932, which MSI paid

EC Electric for the electrical subcontracting work. In December 2024, Stetner timely appealed.

II

Stetner argues that the superior court erred in granting summary judgment to MSI because MSI did not accept Stenter’s bid in writing within seven days, as required by express language in its bid, and that MSI’s reliance on Stenter’s bid was unreasonable. Stetner’s arguments are unavailing. The elements of promissory estoppel were met, and the superior court correctly granted summary judgment in favor of MSI.

We review a trial court’s decision to grant summary judgment de novo.

Lakey v. Puget Sound Energy, Inc., 176 Wn.2d 909, 922, 296 P.3d 860 (2013). We perform the same inquiry as the trial court and affirm an order for summary judgment when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Id. We view the evidence in the light most favorable to the nonmoving party and draw all reasonable inferences in the nonmoving party’s favor. Id.

To prevail on a claim for promissory estoppel, the plaintiff must prove five elements:

(1) [a] promise which (2) the promisor should reasonably expect to cause the promisee to change his position and (3) which does cause the promissee to change his position (4) justifiably relying upon the promise, in such a manner that (5) injustice can be avoided only by enforcement of the promise.

Corbit v. J.I. Case Co., 70 Wn.2d 522, 539, 424 P.2d 290 (1967). Promissory estoppel “applies readily to the unique situation of a subcontractor and a general

contractor.” Ferrer v. Taft Structurals, Inc., 21 Wn. App. 832, 835, 587 P.2d 177 (1978). “A subcontractor submits a bid to a general contractor, knowing the general cannot accept the bid as an offer immediately, but must first incorporate it into the general’s offer to the prospective employer.” Id. The general contractor then “incorporates the bid in reliance upon the subcontractor to perform as promised, should the prospective employer accept the general’s offer.” Id. A “subcontractor’s bid is considered an irrevocable offer until the award of the prime contract; then the general contractor’s acceptance of the bid results in a bilateral contract.” Arango Constr. Co. v. Success Roofing, Inc., 46 Wn. App. 314, 323, 730 P.2d 720 (1986). If the subcontractor breaches this bilateral contract, it is “required to pay as damages the difference between its bid and the higher price the general had to pay another subcontractor to perform the work.” Id. at 322.

Free access — add to your briefcase to read the full text and ask questions with AI

Mcclure And Sons, Inc., V. Stetner Electric, Inc., (Wash. Ct. App. 2026).

Mcclure And Sons, Inc., V. Stetner Electric, Inc. (Mcclure And Sons, Inc., V. Stetner Electric, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Arango Construction Co. v. Success Roofing, Inc.
730 P.2d 720 (Court of Appeals of Washington, 1986)
Corbit v. J. I. Case Co.
424 P.2d 290 (Washington Supreme Court, 1967)
Haselden-Langley Constructors, Inc. v. D.E. Farr & Associates, Inc.
676 P.2d 709 (Colorado Court of Appeals, 1983)
Ferrer v. Taft Structurals, Inc.
587 P.2d 177 (Court of Appeals of Washington, 1978)
Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
1 Cal. App. 5th 727 (California Court of Appeal, 2016)
Lakey v. Puget Sound Energy, Inc.
296 P.3d 860 (Washington Supreme Court, 2013)