McCluer v. Heim-Overly Realty Co.

71 F.2d 100, 1934 U.S. App. LEXIS 3029
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 18, 1934
Docket9883
StatusPublished
Cited by6 cases

This text of 71 F.2d 100 (McCluer v. Heim-Overly Realty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCluer v. Heim-Overly Realty Co., 71 F.2d 100, 1934 U.S. App. LEXIS 3029 (8th Cir. 1934).

Opinion

STONE, Circuit Judge.

The' W. C. Mullins 'Construction Company was adjudicated a bankrupt, Januaiy 20, 1928, on an involuntary petition, filed tlm day before. The trustee brought this suit against appellee to recover $54,177.50, with interest from November 9, 1927, claiming that the collection of that amount on the above date by appellee constituted an unlawful preference. Jury was waived, the court made findings of fact and stated conclusions of law upon which a judgment was entered for appellee. Erom that judgment this appeal.

*101 This litigation has been strenuously contested on both sides. One result of this is the presentation here, by appellant, of a number of separately stated and argued issues. All of these may well be covered by two general points.

I. The first of these is that the grounds upon which the court found for appellee depended upon issues not presented as such in the pleadings. Since this ease (¡ornes up oh the entire record, including a bill of exceptions containing all of the evidence, it is a matter of no controlling concern whether the reasoning of the court, although embodied in findings and conclusions, is correct or not, if the right result is reached. So far as the pleading's are concerned, we need notice only whether the issues raised thereby are such as to justify the resulting judgment, when viewed in connection with the evidence to support such issues. While it is necessary to an understanding of the issues presented by the pleadings to state some matters rather fully, it is enough in connection with this point to say that the main issue presented by the pleadings was whether a certain assignment operated as a valid lien giving appellee a right to the above money superior to that of the trustee.

II. While presented from many viewpoints and as many issues, the real controversy here is whether the evidence is sufficient to sustain the existence of the lien, contended for. There is little dispute as to much of the evidence and as to- the disputed points there is ample evidence to sustain the view of the trial court thereon, as represented in the finding's of fact. The lien here relied upon is based upon an assignment of February 30, 1927, which will bo set out, hereinafter, in chronological order. The proof and the pleading as to- this lien so closely correspond that it is unnecessary to make separate statement as to the pleading and as to the proof. The situation pleaded and shown is as follows: W. C. Mullins was president and active officer of the bankrupt in the matters hereinafter related, just as Joseph Overly was secretary and treasurer and actively representing appellee in the same transactions. In July, 1925., the bankrupt was preparing to make two bids to. the city of Kansas City, Mo., for the construction of two separate portions of a city sewer. It was required that every bidder should file with his bid a certified check for $35,009, which was subject to forfeiture if the bidder should receive and fail to make the contract covered by the bid. Mullins secured from Overly that loan of this $30,000. The Mullins’ bids were accepted for respective contract priees of $203,5-25.90 and $240,804.8 L. The bidder was required to furnish a surety bond, securing performance of each contract, in the amount of 50 per cent, of the contract price. In this situation Mullins represented to Overly that he was unable to make the bonds and would also need $40,000 to provide sufficient funds for the work during the progress of the contracts, and that if appellee would arrange for a sufficient indemnity to induce a qualified surety company to execute the required bonds and arrange to advance the bankrupt the above $40,000, that it would give appellee a sum equal to 50 per cent, of the profit on the contracts. Faced with the possible loss of the $30,000 already advanced, appellee complied with this request by indemnifying the surety company which made the bonds and by agreeing to advance the $40,000. Shortly after, Mullins advised Overly that the bankrupt desired to change the above arrangement so that in lieu of the 50 per cent, of the profits from the contracts it would pay appellee $25,000— one-half in six months and one-half upon completion of the contracts. This chango in this part of the prior verbal contract was put into a written contract, of August 23, 1925, between the bankrupt and appellee. This contract is as follows:

“This Agreement, entered into at Kansas City, Missouri, this 22d day of August, 3.925, by and between W. C. Mullins Construction, Company, a Missouri corporation (hereinafter called first party) and Heim & Overly Realty Company, a Missouri corporation (hereinafter called second party) witnesseth:
“Recitals: First party has entered into a contract with Kansas City, Missouri, to construct certain public sewers for said municipality known as Sections ‘D’ and ‘E’ of the Blue River Sewer, in which said contract second party now lias a one-half interest in the contract price thereof to be paid by said City for the doing of said work, which said interest arises and accrues to second party because of an existing agreement between, first and second parties, under which said second party agreed to furnish all of the necessary funds for the building of said sewer and to furnish indemnity to the surety company in order to procure the necessary bond guaranteeing the performance of said contract.
“Agreements: Now, in consideration of the sum of Twenty-live Thousand Dollars ($25,000.00) to be paid by first party to see *102 ond party without interest, and which by these presents said first party agrees to pay to second party, one-half thereof to be paid six (&) months from the date of this contract, and the remaining half to be paid when said sewer shall have been completed and the above described contract fully performed, and in further consideration of second party’s agreement hereby to furnish to said first party from time to time and during the progress of the work as and when needed therefor, funds not to exceed the sum of Forty Thousand Dollars ($40,000.00), which said funds, advancements and loans first party agrees and promises hereby to refund and to repay to second party at the completion of said work and contract, with eight percent interest on such advancements and loans from the respective dates on which the same were made, second party does hereby relinquish and release'to first party all of the present rights and interests of second party in and to the aforesaid existing contract between first party and said Kansas City, Missouri.”

To protect appellee on account of the obligations of the above contracts, the bankrupt, at this time, executed an assignment to appellee of any and all sums of money to be derived by reason of the performance of the work under the contracts with the city.

Prior to executing the indemnity agreement upon which the construction contract bonds were secured, there was a verbal agreement between the parties that all money received by the bankrupt on the construction, contracts should be deposited in a special account in a bank in which Overly was a director and official; that such funds should be kept separate and distinct from all other moneys of the bankrupt and used to pay bills on account of labor or materials going into the construction contracts, and to repay appellee for its advances, and for the $25,000 under the August contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Otte v. Franklin National Bank of Franklin Square
179 F. Supp. 381 (E.D. New York, 1959)
Atma v. Munoz
146 P.2d 631 (New Mexico Supreme Court, 1944)
Sterling Aluminum Products, Inc. v. Shell Oil Co.
140 F.2d 801 (Eighth Circuit, 1944)
In Re Pusey-Maynes-Breish Co.
37 F. Supp. 316 (E.D. Pennsylvania, 1941)
In re De Luxe Oil Co.
36 F. Supp. 287 (D. Minnesota, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
71 F.2d 100, 1934 U.S. App. LEXIS 3029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccluer-v-heim-overly-realty-co-ca8-1934.