McClellan v. Haley

250 S.W. 413
CourtTexas Commission of Appeals
DecidedApril 18, 1923
DocketNo. 411-3768
StatusPublished
Cited by7 cases

This text of 250 S.W. 413 (McClellan v. Haley) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McClellan v. Haley, 250 S.W. 413 (Tex. Super. Ct. 1923).

Opinion

RANDOLPH, J.

This suit was filed in the district court of Menard county by J. C. McClellan and others, who will hereinafter be styled plaintiffs, against Thomas, Ludlow, and Devenish, hereinafter styled defendants, to recover for labor performed, for “shutdown time,” and for underreaming, in the matter of a contract for the drilling of an oil well. The contract is alleged to have been verbal, and plaintiffs allege they were employed to drill said well by the defendants, who were the original contractors, and were to receive compensation for such drilling, shut-down time, and underreaming, as alleged in their account and affidavit which they filed and had recorded for the purpose of fixing a laborer’s lien upon certain property alleged therein to belong to the defendants. The defendants do not appear to have contested the suit, but E. P. Haley, as alleged owner of the property, filed in turn his petition of intervention, claiming to own the property upon which plaintiffs were asserting their lien. The trial court rendered a personal judgment in favor of plaintiffs as against the defendant, but, after the evidence was submitted, sustained the intervener’s exceptions to plaintiffs’ petition, and held that there was no lien established in plaintiffs’ favor on the property and refused to foreclose same. Prom the judgment sustaining said exceptions only, the plaintiffs appealed, and the Court of Civil Appeals affirmed the trial court’s judgment.

Plaintiffs’ claim for compensation for shut-down time is contested by intervener for the reason that the statute only provides for a lien for labor performed, and not for lost time. We think it only necessary to say in reply to this contention that the plaintiffs had the right to contract against lost time as well as for labor actually performed. Having so contracted, we can see no reason for not allowing compensation for lost time caused by the failure of the defendants to provide material and supplies for continuous labor, and that such lost time is labor and comes within the terms of the statute.

Intervener also contended in the trial court, and here contends, that the underreaming was performed by the plaintiffs under an agreement that the compensation for such work should be payable on demand, and that the alleged indebtedness accrued more than 30 days prior to the filing of said lien.

The plaintiffs’ petition, as well as their affidavit attached to their lien account, alleges that said item was payable on demand, and it is not anywhere shown in such pleadings or affidavit that any demand was made until the filing of this suit. The intervener did not by special exception raise the question as to the failure of the plaintiff’s petition to allege that demand was made, or when it was made.

Plaintiffs’ suit being based upon a claim of lien to secure the payment of their account for labor, and this appeal being an attack on a judgment rendered against them, they must show a strict compliance with the statutes, and it is our duty to sustain the judgment rendered, notwithstanding the error of the trial court in sustaining intervener’s exceptions, if plaintiffs have fundamentally failed to show their right to recover in their pleading filed in this cause, because it is the duty of this court to sustain such judgment if it clearly appears from the pleading of the plaintiffs that no other judgment could have been legally rendered than was rendered. Henderson v. Lindley, 75 Tex. 185, 12 S. W. 979; Albright v. Corley, 40 Tex. 110; Newton v. Emerson Talcott Co., 66 Tex. 147, 18 S. W. 348; Roller v. Reid (Tex. Sup.) 25 S.W. 624.

Were the plaintiffs entitled to assert their lien against the intervener? And did they show themselves to be so entitled by their pleadings? We will answer these questions in the discussion of the case stated in plaintiffs’ petition.

[415]*415Plaintiffs state their account and affidavit in their petition as follows:

Menard, Texas, Aug. 12, 1920.
M. Thomas and Ludlow and Devenish, Well No. 1, Ball In Account with McClellan & Shaffer, oil
Well Drilling Contractors.
Balance on Oct. account.$ 896 00
November, 1919, shut down 12 days. 960 00
December, 1919, shut down 27 days. 2,160 00
January, 1920, shut down 17 days. 1,360 00
February, 1920, shut down 24 days. 1,920 00
March, 1920, shut down 27 days. 2,160 00
April, 1920, underreaming 11 days. 1,100 00
May, 1920, underreaming 17 days, shut down 7 days. 2,260 00
June, 1920, underreaming 15 days. 1,500 00
July, 1920, shut down 9 days. 720 00
August, 1920, shut down 2 days.
Cleaning coil 7 days. 860 00
$15,896 00
Received on this acct. July 3. 1,000 00
Balance now due. $14,896 00

It is clear that statement of this account does not comply with the statutory requirement that such account shall be itemized. Article 5622, Vernon’s Sayles’ Civil Statutes. The first item, “Balance on October account,” is a lump sum that gives no data to determine the days upon which the work was alleged to have been done. The items for “shut-down” time and for underreaming do not identify the particular days upon which the labor was performed, and the item “Cleaning coil” gives no date upon which it was done.

In the case of Ferguson v. Ashbell and Simpson, 53 Tex. 249, the court, passing upon the sufficiency of a bill of particulars or statement of account filed under a verbal contract for the purpose of securing a materialman’s lien, says:

“In verbal contracts, however, the terms and specifications of' the contract and the amount and value of the work and materials furnished, are made ex parte, and should be so specific and certain as to advise the owner of the property, other lien creditors, if any, and all persons interested, of the particulars of the demand sought to be enforced, so that, if they desire, they may be prepared to contest the same. Phillips on Mech. Liens, § 350; Noll v. Swineford, 6 Pa. St. 191; Lanman’s Appeal, 8 Pa. St. 476; Carson v. White, 6 Gill (Md.) 27.
“In commenting upon the certainty required in such statement under the statute of Pennsylvania, the Supreme Court of that state say: ‘It has been felt that the extraordinary remedy afforded by our laws to mechanics and materialmen requires to be properly guarded, to prevent it from becoming a source of unjust annoyance and injury to those whose property is liable to be made the subject of its action. * * * As the law calls for nothing unreasonable at the hand of him who would fasten an incumbrance upon the property of his neighbor, no just ground of complaint is afforded by insisting upon a rigid adherence to its provisions. The information it exacts is, or ought to be, entirely within the power of the creditor to give, and an omission to put it on the record is therefore without excuse. Rehrer v. Zeigler, 3 Watts & Serg. 258; Thomas v. James, 7 Watts & Serg. 381; Witman v. Walker, 9 Watts & Serg. 186.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missouri Land Development Specialties, LLC v. Concord Excavating Co.
269 S.W.3d 489 (Missouri Court of Appeals, 2008)
Upham v. Boaz Well Service, Inc.
357 S.W.2d 411 (Court of Appeals of Texas, 1962)
Pacific Indemnity Co. v. Bowles & Edens Supply Co.
290 S.W.2d 353 (Court of Appeals of Texas, 1956)
Ruwaldt v. Mohawk Drilling Co.
195 S.W.2d 855 (Court of Appeals of Texas, 1946)
Trinity Universal Ins. Co. v. Woitaske
148 S.W.2d 235 (Court of Appeals of Texas, 1941)
Ball v. Davis
18 S.W.2d 1063 (Texas Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
250 S.W. 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclellan-v-haley-texcommnapp-1923.