McCausland v. Cresap

3 Greene 161
CourtSupreme Court of Iowa
DecidedJune 15, 1851
StatusPublished

This text of 3 Greene 161 (McCausland v. Cresap) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCausland v. Cresap, 3 Greene 161 (iowa 1851).

Opinion

Opinion by

Williams, C. J.

Tbe plaintiffs brought their action of assumpsit against the defendants to the September term, 1850, and filed therewith a petition for a mechanic’s lien, under the statute, and claimed the sum of three hundred dollars as due to them on a contract to build a steam saw mill, in the construction > of which they had been employed, and had labored for the defendants. The petition filed by the plaintiffs set forth the contract, and the place where the mill was to be erected. Defendants were to furnish all the materials. The timber was to-be furnished, and delivered hewn or -sawed ready to be foamed or worked into the building and machinery: for which work and labor in erecting the mill, the defendants promised to pay the plaintiffs the sum of three hundred dollars, when the work was completed.” Plaintiffs aver that they completed the work according to the terms of the contract, and that defenants promised to pay them the sum of three hundred dollars therefor. That though requested to pay, the defendants refused to do so, &c. The plaintiffs also aver that other .and additional work was done by them, besides that required by the contract, at the instance and request of the defendants, which has not been paid for, and a refusal to pay the same. That the land, upon which, by the contract the mill was by them erected, is owned by the defendants. The damages are laid at the sum of four hundred and ten dollars. An averment is also made, that the money due to them-for the work became payable within one year last past, and [163]*163before ¡filing the petition. They concluded with a prayer .that the court would render judgment against the defendants in their favor for the damages, and that the same may "be adjudged a lien on the mill and land, as provided by ¡statute.

The defendants appeared and filed their plea of non. .assumpsit, and with it, under the statute, gave notice, that as a part of the contract between them, it was agreed that plaintiffs were “ to erect ¡and ¡build a steam saw mill for the ■defendants, like the steam sawmill of one William Funk, situated upon the Desmoines river ¡near ICeosauqu'a, and make such mill do ¡and perform as ¡good business as the said mill of said Funk.” That they had failed to do so, and also failed in other particulars. 'That -they had done the work in such a manner, that it was not in accordance with the .contract, and so .badly that thb mill was worthless and of no value to .defendants. Notice is also filed of set-off in damages, money paid, money ¡due, &c. The notice concludes by a judgment for so much of the -set-off' as will balance the plaintiff’s demand, and for the overplus if any. This notice is accompanied by a bill -of items of the matters of set-off. The cause was tried, and verdict rendered by the jury for the plaintiffs for fifty dollars damages and judgment thereon. The court also decreed a mechanic’s lien in favor of the plaintiffs, for the amount of the judgment on the mill and land of the defendants, as prayed for in the petition.

The plaintiffs in error insist on the following as error in the instructions of the court below :

1. The court erred in instructing the jury that the plaintiff’s claimed that if the work was wrong and needed to be. altered, the fault belonged to the defendants, or at least to the plaintiffs and defendants jointly ; so that the loss if any, must be where it falls; and so is the law if such is the fact.-

2. The court erred in the instruction that if the defendants do not claim damages for the abandonment of the jol>, [164]*164but only for its being improperly done, then, they must pay such proportion of the whole price, as the part done, bears to the whole job, deducting the necessary expense of alteration, and reduction in value, &c., without giving any damages for the delay.

3. The court erred in only instructing the jury, that if defendants claimed for damages for abandoning the job, defendants would only be entitled to deduct for the expenses of alteration, and what it would cost to finish the job, and in said instruction the court gave defendants nothing for damages for delay.

4. The court erred in instructing the jury that if defenants knew that plaintiffs were deviating from the model and permitted them to go on, the defendants must take the consequences. '

5. The court erred in instructing the jury as they did, as to the foundation for the mill, and gratuitous advice as to foundation, 'given while plaintiffs were doing the job.

The first assignment of error relates to an alleged alteration of the work, as done, by the plaintiffs, upon a discovery that it had not been ¿lone in a right manner. The case aa of record shows that the defendants, as set-off to the plaintiff’s demand, claimed, that the work had been improperly done, so that he was under the necessity of having it altered at his own expense. This allegation was answered by the plaintiffs, by alleging that this additional trouble and expense was not occasioned by their default, but by that of the defendants themselves. Upon this point, the court charged the jury, as follows : “ The defendants claim that the plaintiffs undertook to construct the mill on the same plan, with the same arrangement of machinery, and to operate in the same way as a certain other mill which was agreed upon as a model, and that having partly performed the job, it was found they had departed from the model mill, and so arranged the work that it could not be put into operation without expensive alterations, and that they thereupon [165]*165advanced it voluntarily, and the.defendants made the necessary alterations and completed the job on the original plan as nearly as it would admit of, at their own expense. And they claim to deduct from the proportionate part of the price, the necessary expense of making the alterations, and the reduction in the value of the mill, occasioned by faults that could not he so remedied; and they claim that the payments they have already made, and the deductions to which they are entitled, are together, more than the proportionate share of the price to which the plaintiffs would otherwise have heen entitled. If you shall find the facts to be so, and that there is nothing else in the case to change the rights of the parties, your verdict should be for the defendants. But the plaintiffs claim that the arrangements of the model mill were departed from, by the direction or at least with the assent of the defendants, and if the work was wrong and needed to he altered, the fault belonged to the defendants, or at least to the plaintiffs and defendants, jointly, and so the loss, if any, must he where it falls ; and so is the law, if such are the facts.”

It appears that the plaintiffs before the work was finished abandoned it, and left it; and that in order to render the mill available for any useful purpose, the defendants proceeded at their own expense to finish it. it also appears that there had been a departure, as to the plan of construction, from that of the mill which had been taken and agreed on as the model for the work. The liability for the loss and expense occasioned by this departure, was charged by the parties, each on the other; and the proposition also was presented that the responsibility of it was chargeable to the parties mutually. It also appears that it was alleged, and urged that the work was abandoned before it was completed, at the instance of the defendants, who prevented the plaintiffs from proceeding with the work to completion.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
3 Greene 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccausland-v-cresap-iowa-1851.