McCarthy Concrete, Inc. v. Banton Constr. Co.

166 N.Y.S.3d 306, 203 A.D.3d 1496, 2022 NY Slip Op 02168
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 31, 2022
Docket532089
StatusPublished
Cited by5 cases

This text of 166 N.Y.S.3d 306 (McCarthy Concrete, Inc. v. Banton Constr. Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarthy Concrete, Inc. v. Banton Constr. Co., 166 N.Y.S.3d 306, 203 A.D.3d 1496, 2022 NY Slip Op 02168 (N.Y. Ct. App. 2022).

Opinion

McCarthy Concrete, Inc. v Banton Constr. Co. (2022 NY Slip Op 02168)
McCarthy Concrete, Inc. v Banton Constr. Co.
2022 NY Slip Op 02168
Decided on March 31, 2022
Appellate Division, Third Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered:March 31, 2022

532089

[*1]McCarthy Concrete, Incorporated, Respondent,

v

Banton Construction Company et al., Appellants.


Calendar Date:February 16, 2022
Before:Egan Jr., J.P., Aarons, Pritzker, Reynolds Fitzgerald and Ceresia, JJ.

Hinckley, Allen & Snyder LLP, Albany (Antonino M. Leone of counsel), for appellants.

Robinson & Cole LLP, New York City (Thomas J. Donlon of counsel), for respondent.



Pritzker, J.

Appeals (1) from an order of the Supreme Court (McNally Jr., J.), entered January 15, 2020 in Rensselaer County, upon a decision of the court in favor of plaintiff, (2) from the judgment entered thereon, and (3) from an order of said court, entered June 16, 2020 in Rensselaer County, which denied defendants' motion to reargue.

In relation to a construction project at the train station in Rensselaer County (hereinafter the project), Amtrak, as owner of the project, hired defendant Middlesex Corporation as general contractor, which in turn subcontracted for the services of defendant Banton Construction Company. In accordance with its obligations as provided for in the general contract, Middlesex procured a payment bond with defendant Travelers Casualty and Surety Company of America. Thereafter, Banton entered into a subcontractor agreement with plaintiff to furnish labor, materials and services relating to the project's concrete work. The subcontract expressly provided for 11 enumerated exclusions from the scope of its concrete work, including, as relevant here, "[c]oncrete [p]umping" and "[t]actile." The subcontract laid out compensation for plaintiff based upon the unit pricing of the actual quantity of concrete poured into the project, including the reinforcement bar (hereinafter rebar) to the project.

Plaintiff performed work on the project until the summer of 2015, when an "overall work suspension" by Amtrak caused Banton to demobilize plaintiff, estimating that the project would resume in the spring of 2016. After being unable to resolve two payment issues with Banton, plaintiff filed suit in Connecticut in accordance with the subcontract's relevant provisions. In August 2016, the parties entered into a settlement agreement, lien waiver and release wherein Banton agreed to pay a certain amount for outstanding claims and, in return, plaintiff would withdraw its lawsuit and resume work on the project. Plaintiff returned to the project to finish the remaining minor items, however, subsequent communications between plaintiff and Banton indicated plaintiff's belief that the settlement agreement did not resolve its claim for rebar and that it would not complete the remaining concrete work until after it received payment for the furnished material.

Thereafter, Banton indicated that Amtrak desired to make changes to the concrete work including, as relevant here, using a concrete pumping method and installing tactile warning strips, and requested that plaintiff provide proposals for the costs of said modifications. Plaintiff sent proposals for some of the modifications, but they were not agreeable to Banton, and plaintiff was concerned about going forward without reaching an agreement as to compensation that accounted for plaintiff's increased labor and risk. On September 23, 2016, Banton directed plaintiff to return to the project site and proceed with the remaining work, despite having not yet reached an agreement as to compensation. [*2]Banton stated that it was "willing to fund the alleged added costs for concrete pumping and added reinforcing, under a reservation of rights." Banton also stated that if plaintiff did not commence and continue work within three days, Banton would terminate plaintiff for default as well as seek costs. After plaintiff did not commence work, on September 27, 2016, Banton notified plaintiff that, because plaintiff breached the contract and did not proceed with the work, Banton was "forced to contract with another subcontractor to complete [plaintiff's] work."

In January 2018, plaintiff commenced this action asserting causes of action against Banton for, among other things, breach of contract for failure to pay plaintiff's retainage and for rebar and quantum meruit, and against Middlesex and Travelers for breach of a payment bond. Defendants answered, generally denying the allegations and asserting affirmative defenses, and Banton asserted a counterclaim for breach of contract. A nonjury trial was held and, ultimately, Supreme Court,[FN1] by order entered January 15, 2020, found in favor of plaintiff for its breach of contract claim but denied plaintiff's claim for quantum meruit, as well as Banton's counterclaim; however, the decision did not expressly address plaintiff's claim for breach of the payment bond. Defendants moved to reargue, which motion the court denied by order entered June 16, 2020. Thereafter, the court held a hearing to determine plaintiff's award of counsel fees and, in August 2020, judgment was entered. Defendants appeal from the January 15, 2020 and June 16, 2020 orders, as well as the judgment issued thereon.[FN2]

The fundamental question to be answered in this case is whether plaintiff or Banton breached the subcontract. To that end, defendants contend that Supreme Court erred in finding that plaintiff's nonperformance did not constitute a breach of the subcontract due to defendants' alteration of the scope of plaintiff's work and in finding that Banton breached said subcontract upon its termination of plaintiff. "When conducting [a] review of [a] nonjury trial verdict, [this Court] independently review[s] the probative weight of the evidence, together with the reasonable inferences that may be drawn therefrom, and grant[s] the judgment warranted by the record while according due deference to the trial court's factual findings and credibility determinations" (Kingsley Arms Inc. v Kirchhoff-Consigli Constr. Mgt., LLC, 173 AD3d 1506, 1507 [2019] [internal quotation marks and citation omitted]). "[A] cause of action for breach of contract requires that [the] plaintiff show the existence of a contract, the performance of its obligations under the contract, the failure of [the] defendant to perform its obligations and damages resulting from [the] defendant's breach" (GRJH, Inc. v 3680 Props., Inc., 179 AD3d 1177, 1178 [2020]). "It is well settled that a contractual agreement that is complete, clear and unambiguous on its face [*3]must be enforced according to the plain meaning of its terms" (EDW Drywall Constr., LLC v U.W. Marx, Inc., 189 AD3d 1720, 1722 [2020] [internal quotation marks and citation omitted]).

The subcontract between Banton and plaintiff provides that plaintiff "shall perform and provide all labor, materials, tools, equipment . . . and any other item necessary to complete the [w]ork described below for the [p]roject" and provides a list of tasks that are "excluded from the subcontract," including concrete pumping, winter conditions and tactile.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Quinones
2025 NY Slip Op 06766 (Appellate Division of the Supreme Court of New York, 2025)
Cobleskill Stone Prods., Inc. v. Merchants Natl. Bonding, Inc.
202 N.Y.S.3d 824 (Appellate Division of the Supreme Court of New York, 2024)
AMPOWER-US, LLC v. WEG Transformers USA, LLC
185 N.Y.S.3d 811 (Appellate Division of the Supreme Court of New York, 2023)
Miller v. Carter
182 N.Y.S.3d 771 (Appellate Division of the Supreme Court of New York, 2023)
Patton v. Modern Asian, Inc.
208 A.D.3d 1491 (Appellate Division of the Supreme Court of New York, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
166 N.Y.S.3d 306, 203 A.D.3d 1496, 2022 NY Slip Op 02168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-concrete-inc-v-banton-constr-co-nyappdiv-2022.