McCarl's, Inc. v. Beaver Falls Municipal Authority

847 A.2d 180, 2004 Pa. Commw. LEXIS 300
CourtCommonwealth Court of Pennsylvania
DecidedApril 15, 2004
StatusPublished
Cited by10 cases

This text of 847 A.2d 180 (McCarl's, Inc. v. Beaver Falls Municipal Authority) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarl's, Inc. v. Beaver Falls Municipal Authority, 847 A.2d 180, 2004 Pa. Commw. LEXIS 300 (Pa. Ct. App. 2004).

Opinion

OPINION BY Senior Judge FLAHERTY.

Beaver Falls Municipal Authority (Authority) appeals from the decision of the Court of Common Pleas of Beaver County (trial court) which denied the Authority’s motion for summary judgment and granted the motion for summary judgment filed on behalf of McCarl’s Inc. (McCarl’s). The trial court found in favor of McCarl’s and against the Authority in the amount of $24,078.02 plus interest on the outstanding balance due at the rate of one percent per month, plus penalty of one percent per month, plus reasonable attorney fees as provided by the Contractor and Subcontractor Payment Act, Act of February 17, 1994, P.L. 73, as amended, 73 P.S. §§ 501-515, calculated from December 6, 2000, the time in which the Authority certified that McCarl’s had completed 100% of the work it was required to do. The trial court then granted leave to McCarl’s to submit evidence to the court per its claim for attor *182 ney fees. We reverse and this matter is remanded to the trial court for referral of the matter to arbitration in accordance with the contract.

On October 22, 1998, the Authority awarded McCarl’s one of three contracts (Contract) for a sludge handling facility at the Authority’s water treatment plant in Eastvale, Beaver County. McCarl’s was awarded the job for a total price of $284,000.00. The Contract contains an exclusive arbitration provision and requires the parties to subject all their claims regarding this Contract to arbitration.

By the summer of 2000, McCarl’s had performed, requested and been awarded payment on the mechanical contract for about ninety (90%) percent of the required work. At this time a dispute arose between McCarl’s and the Authority over the scope of the work in McCarl’s Contract and the responsibility of McCarl’s to integrate its work with those of the other contractors. The Authority withheld payment numbers 15-18, disputing McCarl’s entitlement to those payments because of its refusal to do the coordination and to supply the operations manual. The parties did not arbitrate the disputes. The Authority hired SAI Associates (SAI) as the construction engineer to oversee the sludge project. SAI attempted to resolve the matter and the parties negotiated an agreement (Agreement). The Agreement was memorialized in a letter from the Authority’s project manager and agent, Kevin Lettrich. The letter directed the parties to address any questions or concerns regarding the proposed Agreement to Mr. Riggio. Both Mr. Riggio and Mr. Lettrich testified that neither party expressed any questions or concerns following issuance of the letter Agreement.

The letter Agreement states in pertinent part as follows:

RE: Beaver Falls Municipal Authority Eastvale Water Treatment Plant Sludge Handling Facility Contract No. S-3 Mechanical Construction
Project Completion Agreement
...
The following is a recap of the agreement between Beaver Falls Municipal Authority and McCarl’s, Inc:
1. The Beaver Falls Municipal Authority will pay McCari’s $9,262.50 of their contract amount as soon as the agreement is signed by both parties.
The Authority will forgive any liquidated damages.
The Authority will still hold a 2.5% retainer ($2,439.86) and the balance of McCari’s contract of $5,479.85 will be paid under next month’s estimate. This should complete McCarl’s contracted amount of $297,594.23 (including Changes Order Nos. 1 and 2).
2. Upon completion of all outstanding issues including the operators for the primary basin valves, the Beaver Falls Municipal Authority will pay a net change order in the amount of $15,000.00 ($15,000 for the effluent pump panel, $5,000 for the S02 line installation, and a credit of $5,000 for the effluent pump hoist.) This change order will cover all known costs associated with making the project complete and operational.
3. The scheduling of start-up and testing of equipment will work in conjunction with an anticipated completion of two weeks. All equipment manufacturers will be informed immediately that the site should be ready in two weeks, so that there is no lag time between completion and start-up.
4. This agreement is to be confidential between Beaver Falls Municipal Authority and McCari’s.
*183 I hope this completely and adequately describes the proposed agreement. If you have any questions or concerns, please address them to Mr. Jim Riggio at....

Letter agreement, October 19, 2000 at 1.

After the letter was delivered, the Authority made three separate payments in accordance with the terms of the letter. Lettrich certified to the Authority that McCarl’s had completed 100% of all work required on the project. The Authority failed and refused to pay the remaining balance owed under the Agreement stating that McCarl’s had not fully integrated the systems as it was required to do. Nine days after the letter Agreement, the Authority entered into a contract with one of McCarl’s sub contractors for integration of the system. The Authority never requested that McCarl’s perform any further work on the project after the letter Agreement, nor did it dispute the work McCarl’s had done. The coordination problem was known before the October letter Agreement. On August 13, 2001, McCarl’s filed a complaint for the $24,000.00 owed under the Agreement with the trial court.

On September 4, 2001, the Authority filed preliminary objections seeking to dismiss McCarl’s complaint and require the parties to arbitrate the dispute pursuant to the arbitration clause in the original Contract. On January 2, 2002, the trial court dismissed the Authority’s preliminary objections as McCarl’s was not suing under the original Contract but on the settlement Agreement. The trial court further found that factual issues existed as to the extent to which the Agreement affected the parties’ obligations under the original Contract.

The Authority then filed an answer, new matter and counterclaim to MeCarl’s complaint, once again asserting that the matters raised in McCarl’s complaint were subject to the arbitration provisions of the original Contract.

McCarl’s filed preliminary objections to the Authority’s new matter and counterclaim, alleging that the issues raised should be stricken as they were settled by the Agreement and the issue had been resolved by the trial court’s order of January 2, 2002. The trial court dismissed McCarl’s preliminary objections.

After discovery, both parties filed motions for summary judgment. McCarl’s asserted that all issues were resolved in the letter Agreement and that therefore, there was no genuine issue of material fact. McCarl’s asked for the money still owed under the Agreement, plus interest. The Authority asserted that the letter Agreement was not an independent Agreement but merely implemented and completed the original Contract. The Authority asked that the complaint be dismissed and arbitration ordered pursuant to the Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KANTZ v. AT&T, INC.
E.D. Pennsylvania, 2021
Hughes v. Nationwide Bank
387 F. Supp. 3d 612 (W.D. Pennsylvania, 2019)
Maxatawny Township v. Kutztown Borough
113 A.3d 895 (Commonwealth Court of Pennsylvania, 2015)
United States ex rel. Thomas v. Siemens AG
991 F. Supp. 2d 540 (E.D. Pennsylvania, 2014)
Fastuca v. L.W. Molnar & Associates
10 A.3d 11961230 (Supreme Court of Pennsylvania, 2011)
City of Scranton v. Heffler, Radetich & Saitta, LLP
871 A.2d 875 (Commonwealth Court of Pennsylvania, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
847 A.2d 180, 2004 Pa. Commw. LEXIS 300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarls-inc-v-beaver-falls-municipal-authority-pacommwct-2004.