McCandless Township Appeal

199 A.2d 438, 414 Pa. 168, 1964 Pa. LEXIS 538
CourtSupreme Court of Pennsylvania
DecidedApril 21, 1964
DocketAppeal, 218
StatusPublished
Cited by3 cases

This text of 199 A.2d 438 (McCandless Township Appeal) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCandless Township Appeal, 199 A.2d 438, 414 Pa. 168, 1964 Pa. LEXIS 538 (Pa. 1964).

Opinion

Opinion by

Mr. Justice Jones,

This appeal is from an order of the Court of Common Pleas of Allegheny County which affirmed a supplemental report of a board of viewers (Board) wherein the Board levied assessment benefits, arising from the installation of certain water lines in MeCandless Township, Allegheny County, against properties which were improved by such project.

MeCandless Township (Township) duly authorized the installation of certain water lines in the Township. Pursuant thereto, the water lines were installed. Installation of the water lines was by the West View' Water Authority, under a contract with the Township, and the ultimate cost of such installation to the Township was $41,841.27. 1

*170 At the Township’s instance, the court of common pleas appointed a board “to ascertain the costs, damages, 2 if any, and expenses of [the project] and to assess the benefits of said improvement”. The Board prepared a report — herein called the schedule — in which the Board found there were no damages involved and that the total cost of the project was $41,-841.27 and it imposed the entire cost of the project upon the property owners charging nothing against the Township. Certain property owners excepted to this schedule and, after a hearing, 3 the Board levied assessments for benefits against the property owners total-ling $30,595.50 and charged to the Township the difference between the entire cost and the total amount of benefits assessed, to wit, $11,245.77. An examination of that report indicates that the Board made a general “across the board” reduction of the assessments. As we noted in McCandless Appeal, supra, this “report contain [ed] no findings of fact nor any reason or explanation for the reduction of the assessments made in the original report or for the placement of a portion of the costs of this project on the Township.” (p. 287).

On appeal to this Court from an order of the court below which had confirmed this report, in view of the completely unsatisfactory nature of the Board’s report, we remanded the matter to the court below with “instructions that [the Board] file a new report wherein are included appropriate findings of fact and reasons ... in justification of its determination”. Pursuant to our mandate, the court below properly returned the matter to the Board with instructions that the Board comply with our order.

*171 The Board then filed a supplemental report to which the Township filed exceptions, which exceptions were dismissed by the court below. From that order,, the instant appeal was taken.

Two questions are presented: (1) whether this supplemental report of the Board complied with the mandate of this Court? (2) in view of the Board’s failure to find that the design and plan of the water lines’ project were improper or faulty or that the- project costs were excessive or that the Township acted in bad faith or in a fraudulent manner, did the Board have the power and authority to assess against the property owners only a portion of the project costs and charge the balance of such costs against, the Township?

An analysis of the Board’s supplemental report readily reveals the failure of the Board to carry out our order. This supplemental report indicates: (1) the Board inferentially questions the validity of our order because (a) there was no record before the Board upon which findings of fact could be based and (b) it was never the Board’s practice to make findings of fact unless requested; (2) the procedure adopted by the Board in making its original report; (8) a statement by the Board that its original report was erroneous “in that certain properties were demonstrated to have different frontages and lesser benefits than had first appeared”, although the Board now acknowledges that such error had no bearing on the Board’s final determination “since the amount charged to the Township [was] in excess of the total value of these frontages”; (4) a statement of the Board’s belief that “all of the properties together were not benefited to the extent of the whole cost of the improvement as [the Board] first had thought” and, therefore all, of the assessments were reduced “in the interest of uniformity and justice”. The modus operandi by which *172 the Board determined and allocated the portion of the project costs to be paid by the Township and the portion of such costs to be paid by the property owners is not divulged, how the Board ascertained the actual amount of benefit to each property involved is not disclosed nor is the report in any respect informative as to the justification for what is obviously and manifestly an “across the board” reduction of the assessments from those made in the schedule. All the Board states is that “uniformity and justice” required such a reduction. Such ipse dixit neither complies with the order of this Court nor the statutory duties and obligation of the Board.

For some reason or other, this Board has utterly failed to carry out our instructions and those of the court below. Inherent and explicit in such instructions was the requirement that the Board set forth its reasons and the factual basis for the reduction of the assessments and for the placement of a portion of the cost of the project on the Township; such requirement the Board has not met. If a hearing is necessary, as we deem it to be, at which both the Township and the property owners may present factual data to support their respective positions such a hearing must be held and, after such hearing, the Board should then file a report which clearly and expressly sets forth why it determines that a portion of the costs of the project should be placed on the Township and how it determines the amount of benefits to be assessed against each property involved. The unsupported and unexplained conclusion that “uniformity and justice” require a placement of a portion of the costs on the Township and an “across the board” reduction of the assessments against the property owners is clearly insufficient.

Most recently, the United States Supreme Court, in U.S. v. Merz, 376 U.S. 192, 11 L. Ed. 2d 629, 84 S. Ct. *173 639 (1964), in commenting on the kind of a report to be filed by a commission appointed, under Rule 71A(h), Federal Rules of Civil Procedure, to ascertain “just compensation” in eminent domain proceedings, stated: “Conclusory findings are alone not sufficient, for the commission’s findings shall be accepted by the court ‘unless clearly erroneous’; 4 and conclusory findings . . . are normally not renewable by that standard, even when [the Court] reads the record, for it will have no way of knowing what path the commissioners took through the maze of conflicting evidence. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catholic Cemeteries Ass'n of the Diocese of Pittsburgh, Inc. v. Township of Pine
794 A.2d 435 (Commonwealth Court of Pennsylvania, 2002)
Hampden Township v. Brackbill
301 A.2d 420 (Commonwealth Court of Pennsylvania, 1973)
Pittsburgh National Bank v. Equitable Gas Co.
220 A.2d 12 (Supreme Court of Pennsylvania, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
199 A.2d 438, 414 Pa. 168, 1964 Pa. LEXIS 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccandless-township-appeal-pa-1964.