M.B. Claff, Inc. v. Massachusetts Bay Transportation Authority

797 N.E.2d 426, 59 Mass. App. Ct. 669, 2003 Mass. App. LEXIS 1107
CourtMassachusetts Appeals Court
DecidedOctober 17, 2003
DocketNo. 00-P-1679
StatusPublished
Cited by4 cases

This text of 797 N.E.2d 426 (M.B. Claff, Inc. v. Massachusetts Bay Transportation Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.B. Claff, Inc. v. Massachusetts Bay Transportation Authority, 797 N.E.2d 426, 59 Mass. App. Ct. 669, 2003 Mass. App. LEXIS 1107 (Mass. Ct. App. 2003).

Opinion

Cowin, J.

We address the question of the validity and implementation of G. L. c. 79, § 37,1 providing for the payment of interest on judgments in eminent domain cases in light of those provisions of the United States Constitution and the Massachusetts Declaration of Rights2 that require the payment of just compensation when private property is taken for public use. While we have recently had occasion to consider the subject, see Roberts v. Worcester Redev. Authy., 53 Mass. App. Ct. 454 (2001), the posture of that case did not invite exploration of the merits. We deal with them now.

That an appropriate payment of interest during the period between a taking and payment by the government therefor is an element of “just compensation” is firmly established. Seaboard Air Line Ry. v. United States, 261 U.S. 299, 306 (1923). We conclude that G. L. c. 79, § 37, to the extent that it fixes an interest rate at the date of taking that is substantially lower than [671]*671market rates that prevail before the property owner is compensated, deprives that property owner of just compensation. However, this principle is not self-executing. Because a proper level of interest is an element of the compensation due the property owner, the burden of establishing what the interest should be must be shouldered by that owner. The plaintiff not having proved this portion of the case, we sustain the decision of the Superior Court judge to award only the statutory rate of interest.

1. Background. The material facts and relevant prior proceedings are not disputed. On December 30, 1993, the defendant recorded an order of taking of a portion of the plaintiff’s real property in Brockton. The defendant made a pro tanto payment of $80,000, and the plaintiff, dissatisfied with the pro tanto payment, on February 14, 1996, commenced a timely action for assessment of damages under G. L. c. 79. The plaintiff’s complaint contained no allegation that the statutory rate of interest calculable under G. L. c. 79, § 37, was inadequate, and there was no evidence or argument at trial addressed to what that interest rate should be. The case proceeded to trial, and the plaintiff on June 16, 1999, obtained a jury verdict in the amount of $700,000.

On June 24, 1999, the parties filed a pro tanto stipulation reflecting that the plaintiff had already received $80,000. On July 7, 1999, judgment for the plaintiff in the amount of $620,000 was entered. To this judgment, the clerk added interest in the amount of $252,552.32, thereby committing two mistakes (but equitably apportioning the mistakes one to each side). The amount represented a calculation of interest at twelve percent per annum, rather than at the rate called for by G. L. c. 79, § 37, which the parties agree would have been 3.61 percent per annum. In addition, interest was accrued only from February 14, 1996, the date of commencement of the action, rather than from December 30, 1993, the date of taking. On August 4, 1999, the defendant filed a notice of appeal with respect to the interest calculation. The plaintiff did not appeal. The defendant’s appeal was never entered in this court.

On July 28, 2000, the plaintiff filed a “motion for relief from judgment to assess interest in eminent domain action at 7% or, in the alternative, for entry of judgment at statutory rate of [672]*6723.61% and for order to issue execution.” In a separate motion, the plaintiff sought dismissal of the defendant’s still unentered appeal on the ground that the granting of the relief requested by the plaintiff in the motion regarding determination of interest would render that appeal moot. The defendant assented to that portion of the motion seeking 3.61 percent interest from the date of taking, but objected to the awarding of interest at a higher rate. On August 8, 2000, the judge ordered that interest be added to the judgment at a rate of 3.61 percent from the date of taking, denied the plaintiff’s request for a higher interest rate, and dismissed the defendant’s appeal as moot. An amended judgment entered. The plaintiff appealed from that portion of the amended judgment limiting the interest rate to 3.61 percent. The defendant satisfied the undisputed portion of the judgment by means of a payment in December, 2000.

It is not disputed that throughout the period between the date of taking and the entry of the amended judgment, then from the amended judgment to the date of payment, coupon issue yields on fifty-two week United States Treasury bills averaged at a rate higher than 3.61 percent. In connection with its motion seeking a seven percent interest award, the plaintiff presented to the judge documents showing that those yields fluctuated from a low of 3.61 percent to a high of 7.34 percent.3

2. Just compensation. “Persons whose property is taken for public use by a governmental entity are constitutionally entitled to just or reasonable compensation for their property.” Verrochi v. Commonwealth, 394 Mass. 633, 636 (1985). As is frequently the case, this accepted principle is accompanied by difficulties in its application. One such difficulty arises from the practical reality that the owner and the government frequently dispute the amount that will satisfy the requirement of “just compensation.” This results in often protracted delays during which the owner no longer has use of his property but has yet to receive full pay[673]*673ment therefor.4 The delay in this case of approximately seven years between the date of taking and payment by the government of the judgment assessing damages is not unique.

A delay in receiving payment obviously reduces the value of that payment to the owner. Accordingly, the right of the owner to receive interest to compensate him for the loss of use of the funds is an aspect of his right to receive just compensation. “Where the [government] condemns and takes possession of land before ascertaining or paying compensation, the owner is not limited to the value of the property at the time of the taking .... Interest at a proper rate is a good measure by which to ascertain the amount so to be added.” See Seaboard Air Line Ry. v. United States, 261 U.S. at 306; Woodworth v. Commonwealth, 353 Mass. 229, 232 (1967).

The Legislature may, with G. L. c. 79, § 37, being an example, provide by statute for the payment of interest. However, it is against the backdrop of applicable constitutional principles that the Legislature acts. The rate selected by the Legislature may, or may not, be sufficient to satisfy the constitutional requirement of just compensation. If not, the Legislature cannot constitutionally have the last word on the subject. In this regard, treatment of the subject differs substantially from treatment of ordinary tort or contract damages, where the Supreme Judicial Court has characterized interest as “a matter of legislative grace.” Verrochi v. Commonwealth, 394 Mass. at 636. By contrast, interest on eminent domain judgments is “a matter of constitutional right.” Ibid. While a statutory interest rate may be applied if “reasonable and judicially acceptable,” see Miller v. United States, 620 F.2d 812, 837 (Ct. Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berish v. Bornstein
21 Mass. L. Rptr. 530 (Massachusetts Superior Court, 2006)
Casella v. Groton-Dunstable Regional School District
20 Mass. L. Rptr. 506 (Massachusetts Superior Court, 2006)
M.B. Claff, Inc. v. Massachusetts Bay Transportation Authority
808 N.E.2d 238 (Massachusetts Supreme Judicial Court, 2004)
Liberty Square Development Trust v. City of Worcester
808 N.E.2d 245 (Massachusetts Supreme Judicial Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
797 N.E.2d 426, 59 Mass. App. Ct. 669, 2003 Mass. App. LEXIS 1107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mb-claff-inc-v-massachusetts-bay-transportation-authority-massappct-2003.