Mayor of Worcester v. Boston & Albany Railroad

213 Mass. 567
Massachusetts Supreme Judicial Court·Decided February 25, 1913·Published·Cited by 3 cases

Opinion

Morton, J.

By St. 1900, c. 387, as supplemented and amended by St. 1902, c. 508, St. 1903, c. 115, and St. 1905, c. 422, provision was made for the abolition of grade crossings in the city of Worcester. By reference, the provisions of St. 1890, c. 428, "An Act to promote the abolition of grade crossings,” and acts in amendment thereof and in addition thereto were incorporated into St. 1900, c. 387, except as otherwise therein provided. St. 1900, c. 387, § 8. The appointment of an auditor to whom from time to time should be submitted “all accounts [569] of expense,” and who should audit the same and make report thereon to the court was thus provided for. St. 1890, c. 428, § 7. The questions in this case,* arise upon the forty-eighth report of an auditor so appointed. They relate to certain items submitted by the Boston and Albany Railroad Company. The material facts relating to these items as found by the auditor are briefly as follows.

Amongst other things required of the Boston and Albany Railroad Company by the decree of the Superior Court confirming the report of the commissioners was the construction by it of “suitable retaining walls and masonry” for the railroads and tracks affected by the proposed changes. In the performance of the work thus imposed upon it the Boston and Albany Railroad Company entered into contracts for the construction of concrete masonry. The prices contracted for and paid by it and for which it claimed to be allowed as items of expense were based on the use of certain definite proportions of cement, sand and stone, the last to be either broken stone or screened gravel.

The contracts were entered into about the middle of June, 1911, and at that time the contractors had not sufficient facilities to screen the gravel required, and the Boston and Albany Railroad Company through its chief engineer permitted the use of unscreened or “run of bank” gravel until a sufficient screening plant could be installed. “Run of bank” gravel was used in the concrete masonry up to August 7, when the use of broken stone was begun, and continued till a screening plant was completed and placed in operation on September 13. Neither of the contributing parties knew of the contracts, if that is material, or of the use of “run of bank” gravel before August 7. The use of “rim of bank” gravel resulted in a product somewhat inferior in quality and less in cost to the contractors than the concrete called for by the contracts. The difference in cost between the material for the concrete contracted for and that furnished fairly represented the difference in value between the concrete contracted for and that furnished, and the auditor found such difference to be $3,489.46, of which the proportion of the Commonwealth, and the New York, New Haven, and Hartford Railroad Company and the city of [570] Worcester is $2,063.93; and they contend now, as they did before the auditor, that it is not a proper item of expense and should not be allowed. The auditor so found and ruled subject to various objections and exceptions on the part of the Boston and Albany Railroad Company, and the correctness of that ruling is the principal question before us. There are one or two subsidiary matters to which we will refer later.

The auditor found that the Boston and Albany Railroad Company had not been guilty of any dishonesty or bad faith towards any of the other parties to the proceedings; that the masonry provided by it was amply sufficient in kind and amply strong and sufficient in quality for the purposes for which it was intended with a suitable margin for safety; that the price agreed to be paid for it was reasonable if not low; that the variance from the contract was not intended to be permanent but merely as a temporary expedient to hasten the beginning and completion of the masonry contracted for; and that taking the entire work done under the contracts and determining the loss or gain with reference to that part of the work in which the unscreened gravel was used, the contractors made no profit as the result of the use of the unscreened gravel.

He also found that at the time when the railroad company allowed “run of bank” gravel to be substituted for screened gravel no circumstances existed which made such substitution necessary; that when consenting to the variance from the contract it failed to protect the contributing parties from paying for an inferior and less costly material the price contracted to be paid for the material specified in the contract, and that it allowed the substitution to be continued for a time and an amount of masonry to be furnished under the contract as varied which called upon the contributing parties to pay a substantial sum more than the concrete was worth; and that it did not exercise reasonable care and diligence to protect the interests of the contributing parties.

The Boston and Albany Railroad Company contended that, the auditor having found that there was no dishonesty or bad faith on its part and that the masonry was suitable for the purpose for which it was required, it was entitled as matter of law to have the actual cost of the work done by it allowed. But the auditor ruled [571] in effect that, while the railroad company could construct or contract for any kind or quality of concrete masonry that was suitable for the purpose for which it was required, it could not contract for one kind or quality at a fair and proper price and subsequently, without reasonable cause, permit the substitution of an inferior and less costly kind of masonry at the same price, but was bound, as regarded the contributing parties, to use reasonable care and diligence in seeing that the material furnished was worth the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Mayor of Worcester v. Boston & Albany Railroad, 213 Mass. 567 (Mass. 1913).

213 Mass. 567 (Mayor of Worcester v. Boston & Albany Railroad) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Town of Oxford v. Oxford Water Co.
463 N.E.2d 330 (Massachusetts Supreme Judicial Court, 1984)
Koshland v. Columbia Insurance
130 N.E. 41 (Massachusetts Supreme Judicial Court, 1921)
Mayor of Worcester v. Boston & Albany Railroad
225 Mass. 548 (Massachusetts Supreme Judicial Court, 1917)