Mayor of Baltimore v. Chesapeake & Potomac Telephone Co.

48 A. 465, 92 Md. 692, 1901 Md. LEXIS 128
Court of Appeals of Maryland·Decided February 20, 1901·Published·Cited by 6 cases

Opinion

Page, J.,

delivered the opinion of"the Court:

These parties have been twice before this Court — once in 89 Md. 689, and again in 90 Md. 642. It is unnecessary for the consideration of the questions involved in this appeal, to refer to these cases further than to say that by the first, it was *694 held that Ordinance No. 41 created a valid and subsisting grant which, having been sanctioned by the Legislature of the State, the Mayor and City Council are powerless to destroy or change ; and that by the second, the telephone companies having complied with the terms and provisions of Ordinance No. 41, were entitled upon the case as then presented, to an injunction against the interference by the city with the construction of its conduits, subject,- however, to the right-and power of the city to adopt reasonable regulations, etc.

After the cause was remanded for the -Second time the city, through its counsel, filed a supplemental answer, and it is conceded the only questions now before us are those which arise upon the issues it tenders. The substance of the supplemental answer may be thus briefly summarized. The defendants allege: 1st. That the Ordinance No. 41, if accepted as a contract, “was based primarily upon the consideration, that the telephone companies, for the privileges' granted, were to remove within the period of two years from the date of the approval of the ordinance ” as rapidly as conduits were constructed and cables laid therein, all poles under their control standing upon any street along which any conduit is constructed and cables laid ; and that said poles should not be replaced, except in so far as such poles “are necessary,” for the purpose of making distribution of and connection with the wires “ forming part or parts of any such cable; ” 2nd. That the complainant companies “have not removed any of the poles,” but to the contrary, “they have to-day in fact more poles in the city along the same streets and alleys where their conduits have been laid, than they had at the time of the passage of the ordinance ;” 3rd. That the primary consideration upon which the privileges set out in the ordinance were granted was to obtain the removal of the overhead wires; yet the complainants have not performed their part of the contract, by failing to remove such poles, it being “now well settled” that no poles or overhead wires are necessary for distribution or for house to house connection where conduits are laid, and that 4th, the complainants having thus failed to perform its *695 contractual obligations, and in fact having' violated the contract in letter and in spirit, cannot now undertake to ask the interference of the Court to protect them against the action of the city, authorities in refusing to permit them to lay further conduits.

It is proper to state that it appears by the map filed among the proceedings that all of the conduits referred to in the bill and mentioned in the petition to the City Commissioner lie beyond the central part of the city and are not within those districts, which were called by the counsel at the argument the “congested." parts of the city. The counsel for the city at the argument stated also that the city did not insist that the companies should, under the terms of the contract, be required to remove all the poles in streets devoted to residences and where many wires were not required; but only in the central or business parts of the city, where many telephones are used, and therefore many wires required ; that the requirements of the contract, as well as of public interest, demand that the companies should remove all poles in the “congested” parts of the city, it being proved that the distribution from the conduit by poles has now become obsolete and entirely unnecessary. The contention thus presented involves the inquiry whether the companies have performed the obligations imposed on them by the ordinance, and if they have not, whether notwithstanding, they are entitled to the relief prayed for in the bill.

As to the latter branch of the inquiry, it cannot be questioned that when the companies asked the intervention of the Court to enable them to enjoy the privileges of the contract, it is incumbent upon them to show that they have performed everything that the contract requires to be done on their part. This follows from the application of a plain principle of equity, that one party shall not be bound when the other isjnot bound, and is a well-settled rule of equity. O'Brien v. Pentz, 48 Md. 562; Duvall v. Myers 2 Md. Ch. 402.

It being incumbent, therefore, for the appellees to show, that they have performed what they agreed to perform, if it should appear that they have failed to remove such poles as by a *696 proper construction of their contract they had agreed to remove, they would not be in a position to ask the intervention of the Court to enable them to exercise further privileges under the ordinance.

Free access — add to your briefcase to read the full text and ask questions with AI

Mayor of Baltimore v. Chesapeake & Potomac Telephone Co., 48 A. 465, 92 Md. 692, 1901 Md. LEXIS 128 (Md. 1901).

48 A. 465 (Mayor of Baltimore v. Chesapeake & Potomac Telephone Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Baltimore Steam Co. v. Baltimore Gas & Electric Co.
716 A.2d 1042 (Court of Special Appeals of Maryland, 1998)
Lucky Stores, Inc. v. Board of Appeals
312 A.2d 758 (Court of Appeals of Maryland, 1973)
Springloch Area Citizens Group v. Montgomery County Board of Appeals
251 A.2d 357 (Court of Appeals of Maryland, 1969)
Neuman v. Mayor of Baltimore
246 A.2d 583 (Court of Appeals of Maryland, 1968)
Chicago, Indianapolis & Louisville Railway Co. v. Baugh
94 N.E. 571 (Indiana Supreme Court, 1911)
Rexroth v. Holloway
90 N.E. 87 (Indiana Court of Appeals, 1909)