Mayflower Farms v. Tech-Mark, Inc.

666 P.2d 1384, 64 Or. App. 121, 37 U.C.C. Rep. Serv. (West) 25, 1983 Ore. App. LEXIS 3258
CourtCourt of Appeals of Oregon
DecidedAugust 3, 1983
DocketA7906-02619; CA A22716
StatusPublished

This text of 666 P.2d 1384 (Mayflower Farms v. Tech-Mark, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayflower Farms v. Tech-Mark, Inc., 666 P.2d 1384, 64 Or. App. 121, 37 U.C.C. Rep. Serv. (West) 25, 1983 Ore. App. LEXIS 3258 (Or. Ct. App. 1983).

Opinion

*123 RICHARDSON, P. J.

Defendant appeals and plaintiff cross-appeals from the trial court’s judgment awarding damages to plaintiff in this action arising out of defendant’s breach of a contract to construct and install components of a cold storage room for plaintiffs use in its ice cream business. We affirm.

Through exchanges of correspondence in January and February, 1977, the parties agreed that defendant would install the components at plaintiffs Spokane, Washington plant for $46,612. Defendant also agreed to obtain approval of the installation from the Washington Department of Labor and Industries (DLI). No delivery date was specified, but there was evidence, and the trial court as the trier of fact found, that defendant was made aware that plaintiff needed the facility in time for the summer ice cream season. Defendant’s performance was delayed, principally because of unanticipated difficulty in receiving DLI approval. In early May, 1977, plaintiffs attorney wrote a demand letter to defendant that the trial court found “gave notice to defendant that defendant was not in compliance with the contract terms and threatened legal action.” There was oral communication to the same effect during the same general time period.

On July 17, 1977, plaintiff filed a breach of contract action against defendant in Washington. 1 Settlement negotiations were unsuccessful. Plaintiff took the position that it would pay defendant nothing until the action was resolved, and defendant refused to perform unless the action was dismissed with prejudice. In October, 1977, defendant’s attorney demanded assurances of performance from plaintiff as a condition of further performance by defendant. None was received. In the meantime, the necessary DLI approval had been received in August, 1977. Although plaintiff obtained a bid for a cold room from another contractor later in the year, it did not accept that bid. It did not build a substitute facility until the spring of 1978, and that facility differed materially from the one plaintiff had contracted for with defendant.

*124 In this action, plaintiff alleged that defendant breached the contract by failing to comply with DLI requirements and by failing to construct and install the cold room within a reasonable time. Defendant counterclaimed, alleging that plaintiff breached the contract

“* * * in that it frustrated defendant’s performance by the imposition of terms and conditions upon defendant’s performance which were not part of the contract and by refusing to perform its part of said contract until such terms and conditions were met by the defendant.
* * * *
“As a result of plaintiffs breach of contract, defendant was unable to timely complete performance of its contract and defendant was damaged in the amount of $20,000.”

The trial court awarded plaintiff damages equal to “the difference between the contract price and the cost of obtaining a reasonable substitute facility” and incidental and consequential damages for certain labor costs plaintiff incurred as a result of defendant’s nonperformance. The court ruled against defendant on the counterclaim.

The court applied Article 2 of the Uniform Commercial Code (UCC) of Washington as the governing law 2 and found that July 17,1977, “was a reasonable time on or before which [defendant] should have completed its performance.” It then concluded that “timely performance * * * was a condition * * * rather than a covenant.” The court also concluded that plaintiffs declarations after that date that it would not pay defendant until the litigation between the parties was resolved did not constitute an anticipatory repudiation. Defendant challenges both conclusions by its first and second assignments of error, respectively.

Defendant argues that the effect of the court’s conclusion that timely performance was a condition, notwithstanding the absence of an express provision to that effect or of a specified time for performance in the contract, “was to strip [defendant] of all of its rights and entitled [plaintiff] to treat its *125 obligations with impunity — in a word, a forfeiture as to [defendant].” Defendant also contends that the court’s characterization of the nonperformance as a breach of a condition rather than of a covenant led to the further erroneous conclusion that plaintiff was not in anticipatory breach. According to defendant, it was able to perform after receiving the DLI approval in August, 1977, and the rights and obligations of the parties were not completely obviated by defendant’s failure to complete performance by July 17, although the failure to perform by that date may have been a breach of a covenant. Therefore, plaintiffs declared refusal to pay pending the outcome of its lawsuit was an anticipatory repudiation, RCWA 62A.2-610, and plaintiffs refusal to give “adequate assurance of due performance” in response to defendant’s demand gave defendant the right to suspend its performance. RCWA 62A.2-609.

Although defendant agrees that the UCC is applicable, its argument supporting its first assignment relies on Washington cases and other authority espousing the general principle that implied conditions and time of the essence requirements are disfavored. We think the UCC provisions relating to reasonable time for performance and to buyers’ remedies are more relevant here than the considerations relating to whether nonperformance is a breach of an implied condition or of a covenant. RCWA 62A.2-309(1) provides:

“The time for shipment or delivery or any other action under a contract if not provided in this Article or agreed upon shall be a reasonable time.”

RCWA 62A.2-711U) provides:

“Where the seller fails to make delivery or repudiates or the buyer rightfully rejects or justifiably revokes acceptance then with respect to any goods involved, and with respect to the whole if the breach goes to the whole contract (RCW 62A.2-612), the buyer may cancel and whether or not he has done so may in addition to recovering so muoh of the price as has been paid
“(a) ‘cover’ and have damages under the next section as to all the goods affected whether or not they have been identified to the contract; or
“(b) recover damages for non-delivery as provided in this Article (RCW 62A.2-713).”

*126 See also RCWA 62A.1-204. 3

A second difficulty with defendant’s argument is that it sometimes refers to the performance that the trial court concluded was a condition to be the securing of DLI approval.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jarstad v. Tacoma Outdoor Recreation, Inc.
519 P.2d 278 (Court of Appeals of Washington, 1974)
Falk v. Amsberry
626 P.2d 362 (Oregon Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
666 P.2d 1384, 64 Or. App. 121, 37 U.C.C. Rep. Serv. (West) 25, 1983 Ore. App. LEXIS 3258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayflower-farms-v-tech-mark-inc-orctapp-1983.