Mayborn v. Continental Casualty Co.

137 N.E.2d 793, 73 Ohio Law. Abs. 369, 2 Ohio Op. 2d 274, 1953 Ohio Misc. LEXIS 342
CourtTrumbull County Court of Common Pleas
DecidedAugust 11, 1953
DocketNo. 58918
StatusPublished

This text of 137 N.E.2d 793 (Mayborn v. Continental Casualty Co.) is published on Counsel Stack Legal Research, covering Trumbull County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayborn v. Continental Casualty Co., 137 N.E.2d 793, 73 Ohio Law. Abs. 369, 2 Ohio Op. 2d 274, 1953 Ohio Misc. LEXIS 342 (Ohio Super. Ct. 1953).

Opinion

[370]*370OPINION

By BIRRELL, J.

The Plaintiff, L. L. Mayborn in this case, secured a contract with the U. S. Government for the construction of “damtenders” dwellings at Mosquito and Berlin Dams, which is dated May 5th, 1949. Previous to making his bid for this contract, he had submitted copies of the specifications to various contractors, including Defendant William M. Bushnell, for the construction of the plumbing work required under said contract. Bushnell had given him a written bid for the construction of such plumbing at $6,500.00. After receiving the notice that he had been awarded the general contract Mayborn advised Bushnell of such fact and that Bushnell’s was the lowest bid for doing the plumbing work. He therefore requested Bushnell to enter into a sub-contract. Dispute was had between Mayborn and Bushnell as to the extent of the plumbing work, Bushnell claiming that he should not be required to do any excavating or back-filling other than within five feet of the building, Mayborn claiming that the plumbing work included both excavating and back-filling. On the refusal of Bushnell to sign a contract including excavating and back-filling, Mayborn secured an employee of Bushnell to sign the contract, and without further discussion with Bushnell on this particular point urged Bushnell to enter upon the job and proceed with the plumbing work which Bushnell did. At the same time Mayborn continued with the excavating and back-filling.

Bushnell’s bid on the sub-contract included the requirement that bond in the amount of $6,500.00 be furnished. Although Bushnell proceeded with the work, he delayed the giving of bond until he desired the payment of a substantial amount ($2,500.00) on the contract. May-born had already paid Bushnel on the contract some $710.04 but refused to make further payment until bond was furnished. On August 6th„ the parties, with Bushnell’s attorney, met at the office of W. C. Gamble, agent for Defendant Continental Casualty Company of Chicago, and a bond was prepared, signed and presented to Mayborn whereupon May-born paid the $2,500.00 to Bushnell, and the contract continued. It appeared that Mayborn had been advised by the Government engineer on the job to secure a bond from his sub-contractor, and had urged Bushnell from tlie beginning to furnish a bond which Bushnell had delayed doing. After the bond was given the work on the contract continued and further substantial payments were made to Bushnell.

The contract required completion within 180 days from May 26th, 1949, which term would expire November 22nd., 1949. Delays on the part of Bushnell in completing various items of his work and in failing to do certain parts thereof in accordance with specifications, which delinquencies were pointed out by the Government engineers, caused May-born to fear that his completion of the contract would be delayed beyond the due date, and subject him to the penalty of $25.00 per day provided [371]*371in the contract for failure to complete the job on time. This fear caused Mayborn to urge Bushnell to complete his work more rapidly, and ultimately caused Mayborn on October 25th to cancel Bushnell’s contract, secure another plumber and go forward with the completion of the job.

Notice of the delinquencies of Bushnell was given to Continental Casualty Company as early as August 31st., 1949, which Company denied liability upon their bond, and refused to take over and complete the contract. This notice, the conferences and refusal, all occurred before Mayborn himself dismissed Bushnell and undertook the completion of Bushnell’s sub-contract.

This lawsuit was brought for the purpose of securing judgment against Bushnell and enforcing the liability for his delinquencies against the Bonding Company. The pleadings, among other matters, raise three points:

Who was the sub-contractor heretofore referred to as Defendant “Bushnell.”

What was the contract between Plaintiff and said sub-contractor.

Should the bond which had been written to “United States of America” instead of to “Mayborn” be reformed as requested in the petition to change the obligee from the United States of America to Mayborn.

With reference to the identity of the sub-contractor during the period of this contract Defendant “Bushnell,” used various names, or forms of names, in his proceedings all of which are set forth in the pleadings. There is no dispute that some sort of contract was entered into and was partially performed by the person known as “William M. Bushnell.” William M. Bushnell claims and admits in his Answer that he was operating as the president of a corporation known as “The William M. Bushnell Plumbing and Heating Company.” Proof was offered in evidence of the incorporation of such a company under date of December 31st, 1948, and it appears that such a company was in existence at the date of the offering of the bid to Mayborn by Bushnell, which bid was signed “William Bushnell, pres. Bushnell Plumbing and Heating Company” although not on corporation stationery. When Mayborn prepared his contract which he requested Bushnel to sign, this contract was prepared to “William Bushnell” but signed by the employee of Bushnell as “William Bushnell Plumbing Company, by Byron E. Mills,” which signature (whether valid or not) was accepted by Mayborn without objection. The first checks of Mayborn to Bushnell, including the check of August 8th., for $2,500.00 were written to William Bushnell. After the bond was given the checks of September 15th., for $1,500.00 was written to William Bushnell Plumbing Company, and the last check of October 10th was written to William Bushnell and the Trumbull Plumbing Company. The Bond of Continental Casualty Company was written to the corporation under the name of “William M. Bushnell Company.”

The carelessness of the parties with respect to title and proper designation of the capacity in which Bushnell appeared is very evident. There is no dispute respecting the fact that there was a contract, and that there was only one Corporation operated by Bushnell. This corporation was entitled “The William M. Bushnell Plumbing and Heating Company.” [372]*372The attorney for Bushnell, in the preparation of Bushnell’s bond, saw fit to give the name as “The William M. Bushnell Company,” indicating likewise to the Bonding Company that the Corporation which gave the Bond and which had the contract was incorporated March 2nd, 1949. The check of August 8th for $2,500.00 was deposited in a so-called “special account” in The Union Savings and Trust Company bank under the name of “William Bushnell Plumbing and Heating Company, special account.”

While there had been some misunderstanding apparently among the directors of the Corporation, and while the corporation had taken away from Bushnell the power to make withdrawals from the corporation account, it would appear that Bushnell still understood that he was transacting his business in the capacity of the Corporation. As far as the Plaintiff is concerned he was doing business with the man named “William M. Bushnell;” whether as an individual, or as president of a corporation known as “The William M. Bushnell Plumbing and Heating Company,” or as President of a corporation known as the “William Bushnell Company” was not important to the Plaintiff. It is proper, however to designate “Bushnell” in his rightful capacity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snell v. Insurance Co.
98 U.S. 85 (Supreme Court, 1878)
Griswold v. Hazard
141 U.S. 260 (Supreme Court, 1891)
Great Atlantic & Pacific Tea Co. v. Engel Realty Co.
2 So. 2d 425 (Supreme Court of Alabama, 1941)
Sacramone v. Dematteo
68 A.2d 167 (Supreme Court of Connecticut, 1949)
Wilson MacHinery & Supply Co. v. Fidelity & Casualty Co. of New York
110 S.W.2d 1075 (Court of Appeals of Kentucky (pre-1976), 1937)
Archer v. . McClure
81 S.E. 1081 (Supreme Court of North Carolina, 1914)
Gayle v. Hudson
10 Ala. 116 (Supreme Court of Alabama, 1846)
Bell v. Tanguy
46 Ind. 49 (Indiana Supreme Court, 1874)
Standard Oil Co. v. Century Indemnity Co.
105 F. Supp. 284 (N.D. Alabama, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
137 N.E.2d 793, 73 Ohio Law. Abs. 369, 2 Ohio Op. 2d 274, 1953 Ohio Misc. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayborn-v-continental-casualty-co-ohctcompltrumbu-1953.