Maya v. Priola Construction Corp.

128 So. 3d 1009, 12 La.App. 3 Cir. 1027, 2013 La. App. LEXIS 400, 2013 WL 811651
CourtLouisiana Court of Appeal
DecidedMarch 6, 2013
DocketNo. 12-1027
StatusPublished

This text of 128 So. 3d 1009 (Maya v. Priola Construction Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maya v. Priola Construction Corp., 128 So. 3d 1009, 12 La.App. 3 Cir. 1027, 2013 La. App. LEXIS 400, 2013 WL 811651 (La. Ct. App. 2013).

Opinion

GENOVESE, Judge.

1 tThird Party Defendant/Appellant, CFS Enterprises, Inc., d/b/a Custom Frame Specialties (CFS), appeals the judgment of the trial court denying its motion for partial summary judgment and granting the cross-motion for partial summary judgment filed by Third Party Plaintiff/Appel-lee, Priola Construction Company (Priola). For the following reasons, we reverse in part, affirm in part, and remand the matter for further proceedings.

FACTUAL AND PROCEDURAL BACKGROUND

In August 2009, Priola was hired as the general contractor to construct a branch bank for the Whitney National Bank on Country Club Drive in Lake Charles, Louisiana (Whitney Bank Project). Priola entered into a construction subcontract with CFS to perform the framing work on the Whitney Bank Project. CFS then entered into a construction subcontract with Felipe Dominguez to perform the framing work on the Whitney Bank Project. Felipe Dominguez employed Jose Pilio Morales and Peter Arellano. An accident occurred on the Whitney Bank Project resulting in serious injury to Arellano and the death of Morales.

In June 2010, Plaintiffs, Rosaría Duran Maya, individually and on behalf of Daya-na Michelle Morales Duran and Maria [1011]*1011Jose Morales Duran, minors, and Peter Arellano, filed a Petition for Damages against Priola. Plaintiffs’ petition alleged:

On or about September 15, 2009, Jose Pifio Morales (deceased) and Peter Arel-lano were participating in the construction of a bank building at 1901 Country Club Road, Lake Charles, Louisiana in Calcasieu Parish. As [Priola’s] employees began manually lifting a 1,300 pound wall frame, they called out for help to Morales and Arellano. Morales and Ar-ellano came over and positioned themselves to assist lifting the wall to an overhead height. [Priola’s] employees lost control of the wall at this point[,] and it came crashing down on Morales and Arellano. Specifically, Morales was crushed by the wall. Mr. Arellano suffered a crushed pelvis. Despite being rushed to the hospital, Mr. Morales was later pronounced dead, but not before he | ¿went through agonizing pain en route to the hospital. Mr. Arellano continues to suffer immense pain as a result of a crushed pelvis. After the foregoing! ] events[, Priola] was issued a citation for fault by the U.S. Department of Labor/OSHA.

Plaintiffs asserted that Priola’s “negligence and gross negligence was the proximate cause of [Arellano’s] injuries and [Morales’] death.”

Priola filed a general denial to Plaintiffs’ petition in July 2010. In June 2011, Priola filed a Third Party Demand against CFS, asserting contractual defenses and indemnification. According to Priola, prior to the September 15, 2009 accident, it had entered into a written construction subcontract with CFS to perform the framing work on the Whitney Bank Project. Said construction subcontract included an indemnity clause. According to Priola, “[p]ursuant to Article 7 of the contract, [CFS] agreed to notify and hold harmless Priola from all damages, losses or expenses from any claims or damages for bodily injury. The indemnification was to extend to claims resulting from performance of the contract at issue.”

In January 2012, CFS filed a motion for partial summary judgment which asserted that “[b]ased on the facts, the evidence, and the applicable law, Priola has no viable claim for contractual indemnity, and as such, partial summary judgment is proper.” According to CFS, the sentence in the indemnity clause which declared that “indemnification shall extend to claims resulting from performance of this subcontract and shall apply only to the extent that the claim or loss is caused in whole or in part by any negligent act or omission of sub-contractor or any of its agents, employees, or sub-contractors!,]” rendered Priola’s claim for indemnity invalid. CFS also argued that this court’s holding in Boykin v. PPG Industries, Inc., 08-117 (La.App. 3 Cir. 6/18/08), 987 So.2d 838, writs denied, 08-1635, 08-1640 (La.10/31/08), 994 So.2d 537, supported its position that it did not owe [sindemnity to Priola based on the language of the indemnity clause and Louisiana’s comparative fault law.

In March 2012, Priola responded by filing a cross motion for partial summary judgment also on the issue of indemnity. Priola sought a judgment declaring that CFS owed it indemnity based on the interpretation of Article 7 of the construction subcontract. Priola argued that the language of the indemnity clause is analogous to that found in Berry v. Orleans Parish School Board, 01-3283 (La.6/21/02), 830 So.2d 283; thus, it is entitled to indemnity from CFS for its own acts of negligence.

A hearing was held on April 2, 2012. The trial court granted Priola’s motion and denied the motion filed by CFS. The trial court signed a judgment on April 24, 2012, [1012]*1012“finding that the indemnification clause at issue requires CFS ... to indemnify Priola ... in accordance with the contents of the indemnification clause subject of the current motions.” CFS appeals.

ASSIGNMENTS OF ERROR

CFS asserts that the trial court erred: (1) “in granting Priola’s motion for summary judgment[;]” and (2) “in denying [its] motion for summary judgment.”

LAW AND DISCUSSION

Standard of Review

The governing jurisprudence relative to a motion for summary judgment and our appellate standard of review thereof has been set forth by our supreme court as follows:

A motion for summary judgment is a procedural device used when there is no genuine issue of material fact for all or part of the relief prayed for by a litigant. Duncan v. U.S.A.A. Ins. Co., [06— 363 (La.l1/29/06) ], 950 So.2d 544, [see La.Code Civ.P.] art. 966. A summary judgment is reviewed on appeal de novo, with the appellate court using the same criteria that govern the trial court’s determination of whether summary judgment is appropriate; i.e. whether there is |4any genuine issue of material fact, and whether the movant is entitled to judgment as a matter of law. Wright v. Louisiana Power & Light, [06-1181 (La.3/9/07), 951 So.2d 1058]; King v. Parish National Bank, [04-337 (La.10/19/04), 885 So.2d 540]; Jones v. Estate of Santiago, [03-1424 (La.4/14/04), 870 So.2d 1002.]

Samaba v. Rau, 07-1726, pp. 3-4 (La.2/26/08), 977 So.2d 880, 882-83 (footnote omitted).

Assignment of Error Number One

In this assignment of error, CFS asserts that the trial court erred in granting Prio-la’s motion for summary judgment relative to the issue of indemnity in the construction subcontract.

Questions of contractual interpretation are questions of law which are subject to a de novo standard of review. Mitchell v. Patterson Ins. Co., 00-612 (La.App. 3 Cir. 12/6/00), 774 So.2d 366. Contracts have the force of law between the parties, and the courts are bound to interpret them according to the common intent of the parties. La.Civ.Code arts. 1983 and 2045. If the words of the contract are clear, unambiguous, and lead to no absurd consequences, the court need not look beyond the contract language to determine the true intent of the parties. La.Civ.Code art. 2046.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berry v. Orleans Parish School Bd.
830 So. 2d 283 (Supreme Court of Louisiana, 2002)
Louisiana Ins. Guar. Ass'n v. Interstate Fire & Casualty Co.
630 So. 2d 759 (Supreme Court of Louisiana, 1994)
Samaha v. Rau
977 So. 2d 880 (Supreme Court of Louisiana, 2008)
Wright v. Louisiana Power & Light
951 So. 2d 1058 (Supreme Court of Louisiana, 2007)
King v. Parish National Bank
885 So. 2d 540 (Supreme Court of Louisiana, 2004)
Soverign Ins. Co. v. Texas Pipe Line Co.
488 So. 2d 982 (Supreme Court of Louisiana, 1986)
Jones v. Estate of Santiago
870 So. 2d 1002 (Supreme Court of Louisiana, 2004)
Mitchell v. Patterson Ins. Co.
774 So. 2d 366 (Louisiana Court of Appeal, 2000)
Murphy's Lease & Welding Service, Inc. v. Bayou Concessions Salvage, Inc.
780 So. 2d 1284 (Louisiana Court of Appeal, 2001)
Boykin v. PPG Industries, Inc.
987 So. 2d 838 (Louisiana Court of Appeal, 2008)
Duncan v. USAA Ins. Co.
950 So. 2d 544 (Supreme Court of Louisiana, 2007)
Edwards v. Larose Scrap & Salvage, Inc.
52 So. 3d 1009 (Louisiana Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 3d 1009, 12 La.App. 3 Cir. 1027, 2013 La. App. LEXIS 400, 2013 WL 811651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maya-v-priola-construction-corp-lactapp-2013.