May v. Barton's Pump Service, Inc.

153 S.W.3d 469, 2004 Tex. App. LEXIS 473, 2004 WL 76341
CourtCourt of Appeals of Texas
DecidedJanuary 16, 2004
Docket07-02-0210-CV
StatusPublished
Cited by16 cases

This text of 153 S.W.3d 469 (May v. Barton's Pump Service, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
May v. Barton's Pump Service, Inc., 153 S.W.3d 469, 2004 Tex. App. LEXIS 473, 2004 WL 76341 (Tex. Ct. App. 2004).

Opinion

OPINION

PHIL JOHNSON, Chief Justice.

Jimmy May appeals from a judgment against him for the amount due on a contract for services and materials. By 11 issues he challenges the (1) legal and factual sufficiency of the evidence, (2) trial court’s refusal to allow an expert witness to testify and (3) trial court’s refusal to submit a proposed jury instruction. We affirm.

BACKGROUND

In 1999 and for some years prior to that time, appellant Jimmy May owned approximately 68.49 acres of land southwest of the City of Lubbock. He formulated a plan to subdivide the acreage into commercial and residential lots and sell them. As part of his development plan, May sought to convert an old irrigation well on the property to a water source for a privately owned public water supply system (the water system) which would serve the subdivision lots. May was a professional engineer and developed a plan for the water system which he submitted to the Texas Natural Resource Conservation Commission (TNRCC) for approval. He also took a copy of his water system drawing to appellee Barton’s Pump Service, Inc. May and Dale Barton, one of the principal owners of Barton’s, agreed that Barton’s would perform work on the irrigation well which Barton’s did. The result was not to May’s satisfaction and May did not pay Barton’s bill.

May sued Barton’s alleging various theories of liability, including violation of the Texas Deceptive Trade Practices Act, 1 breach of contract, breach of implied warranty of good workmanship, negligent misrepresentation and negligence. The bases for May’s claims were that after Barton’s worked on the well, the well did not comply with TNRCC requirements for a public water supply system, the well was damaged and the well’s water production was severely decreased.

Barton’s denied liability and counterclaimed to recover its unpaid bill.

The evidence conflicted sharply as to what May and Dale Barton agreed to. May contended that the agreement was for Barton’s to (1) modify the irrigation well in accordance with May’s schematic drawing, (2) bring the well into compliance with TNRCC regulations, and (3) concrete the outside of the 16" well casing from the surface to the top of the water bearing formation. If Barton’s had done so as agreed, May contended, the amount of wa *473 ter produced by the well would not have been reduced and the well would have supplied May’s planned privately-owned public water system.

Barton’s maintained that it properly performed the work it agreed to do and for which it billed May. Barton’s denied that it agreed to perform work as contended by May, including bringing the well into compliance with TNRCC regulations. Barton’s asserted that it agreed to do the work described in a written estimate dated December 27, 1999. That work only included inserting an 8" PVC liner inside the existing 16" well casing, placing gravel between the liner and the 16" casing, and placing a concrete cap on the well site.

May’s modification plan did not include inserting a liner into the existing well casing, placing gravel inside the existing casing, and merely placing a concrete cap on the well at the surface.

The case was submitted to a jury by 18 questions. The jury effectively found that May and Dale Barton agreed as Barton’s contended, and not as May contended. By its answers to Jury Questions, the jury failed to find that Barton’s: (Question 1) engaged in a misleading or deceptive act or practice on which May relied to May’s damage; (Question 2) engaged in an unconscionable action or course of action which was a producing cause of damages to May; (Question 8) failed to comply with a warranty which was a producing cause of damages to May; (Question 5) agreed with May that Barton’s would follow May’s drawing, bring the well into compliance with TNRCC regulations and concrete the outside of the 16" well casing from the surface to the top of the water bearing formation; (Question 15) made a negligent misrepresentation on which May justifiably relied; and (Question 16) actions were negligence and a proximate cause of the damages. In response to other questions, the jury found (Question 10) Barton’s and May agreed that Barton’s would do work on May’s well as described in Barton’s estimate dated December 27, 1999 and that May would pay the reasonable charges for such work; (Question 11) May failed to comply with the agreement referenced in Question 10; (Question 18) Barton’s damages were $5,533.83; (Question 14) attorney’s fees for Barton’s were $23,000 for preparation and trial, $7,500 for appeal to the Court of Appeals and $5,000 for appeal to the Supreme Court of Texas; and (Question 16) May’s negligence was a proximate cause of the damages. The jury also failed to find that May’s failure to comply with the agreement between Barton’s and May was excused (Question 12).

May challenges (1) the factual sufficiency of the evidence to support the jury’s answers against him on his theories of liability and contractual excuse (Questions 1,2,3,5,12,15,16); (2) both the legal and factual sufficiency of the evidence to support the jury’s answers in favor of Barton’s theory of liability (Questions 10,11,16); (3) the legal and factual sufficiency of the evidence as to Barton’s attorney’s fees for appeal to the Court of Appeals and the Supreme Court of Texas (Question 14); (4) the trial court’s exclusion of May’s expert witness Tucker Rudder; and (5) the trial court’s refusal to submit a proposed instruction as to excuse for May’s failure to comply with the agreement submitted via Question 10.

We will address the issues, in general, as they are grouped by May.

ISSUES ONE, TWO AND THREE-FACTUAL INSUFFICIENCY

Issues one, two and three assert that the jury’s negative answers to certain of the Jury Questions on which May had the burden of proof are against the great *474 weight and preponderance of- the evidence. Issue one challenges the jury’s refusal to find, in response to Questions 1, 2 and 3 that Barton’s violated the deceptive trade practices act. Issue two addresses the jury’s negative answer to Question 12, which presented May’s position that Barton’s made a false representation to induce May to enter into an agreement in the first instance. Issue three presents the same assertion to the jury’s failure to find, in response to Question 15, that Barton’s made a negligent misrepresentation. Such challenges are' factual sufficiency challenges to adverse jury answers to questions on which the challenging party had the burden of proof. See Chang v. Nguyen, 76 S.W.3d 635, 637 n. 1 (Tex.App.-Houston (14th Dist.) 2002, no pet.); W. Wendell Hall, Standards of Review in Texas, 29 St. Mary’s L.J. 351, 487 (1998).

When considering factual sufficiency challenges to a jury’s verdict, courts of appeals must consider and weigh all of the evidence, not just evidence which supports the verdict. See Maritime Overseas Corp. v. Ellis, 971 S.W.2d 402, 406-07 (Tex.1998); Ortiz v. Jones, 917 S.W.2d 770, 772 (Tex.1996); Lofton v. Texas Brine Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
153 S.W.3d 469, 2004 Tex. App. LEXIS 473, 2004 WL 76341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/may-v-bartons-pump-service-inc-texapp-2004.