Maxwell v. Zenith Limestone Co.

1930 OK 161, 286 P. 879, 142 Okla. 286, 1930 Okla. LEXIS 130
CourtSupreme Court of Oklahoma
DecidedApril 8, 1930
Docket19237
StatusPublished

This text of 1930 OK 161 (Maxwell v. Zenith Limestone Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maxwell v. Zenith Limestone Co., 1930 OK 161, 286 P. 879, 142 Okla. 286, 1930 Okla. LEXIS 130 (Okla. 1930).

Opinion

FOSTER, O.

J. H. Maxwell and E. AV. *287 Mead brought this action in the court of common pleas of Tulsa county against the defendant, Zenith Limestone Company, to recover the sum oí $442.98. Plaintiffs’ petition alleges that on the 21st day of July, 1926, the parties entered into two written contracts, copies of which are attached to plaintiffs’ petition. In the first contract the defendant agreed to sell plaintiffs crushed stone at a price of $1.40 per ton, f.o.b. Verdigris, Okla.; and in the second contract agreed to sell and deliver! plaintiffs sand at a price of 90 cents per ton, f.o.b. Verdigris, Okla. Except as to material and price, as above set out, the other provisions of the two contracts were identical and were executed ui>on the same day, and both show upon their face that the crushed stone and sand were to be used by the plaintiffs in the construction of a concrete road known as Federal Project No. 183-tB. The sand and rock were to be delivered between the date of the contract and the 31st day of December, 1926, and were to be shipped as nearly as possible to meet the necessities of the work, except that the defendant was not obliged to ship more than eight cars of crushed stone in one day.

The petition further alleges that the defendant breached the contract, and that it was necessary for plaintiffs to go into the open market and buy stone, and that pursuant thereto it made a contract with the Hughes Stone Company at a price of 25 cents per ton more than it agreed to pay the plaintiffs, thereby sustaining a damage of $2,268-58; that the defendant was entitled to a credit against this amount in the sum of $1,825.60 for stone and sand which it furnished prior to the breach of the contract, leaving a balance of $442.98.

The petition further alleges that it was impossible for plaintiffs to secure crushed stone without at the same time contracting with the same company for the sand necessary to complete the job.

To this petition the defendant filed its answer, admitting the execution of the contracts, alleging that they were distinct and independent, denied a breach thereof, but alleged that on or about the 15th of August, 1926, it was unable for a short time to furnish crushed rock because of a broken shaft in the crushing machine of the defendant, ‘but that the same was repaired within about 30 days, and tender of the remaining part, as provided [by the contract, was made. By way of cross-petition the defendant alleged that it was at all times willing, able, and ready to deliver the sand as provided for in the second contract, and that the plaintiff's refused to accept the sand and the defendant was damaged in the sum of $650. This, together with the amount set out in plaintiffs’ petition, which was due for sand and rock delivered, to wit, $1,825, made a total of $2,475, for which defendant prayed judgment.

At a trial before a jury, the testimony on behalf of the plaintiffs disclosed that they had begun the construction of the road on or about the 15th or 16th of August, 1926; that after the delivery of about 15 cars of rock, the defendant refused to deliver any additional rock, although plaintiffs requested it many times to do so. One of the plaintiffs testified that he went to the office almost every day for ten days or two weeks, and that the defendant continually promised him that he would send additional rock oh tomorrow or the next day. However, the plaintiffs admit that defendant told them the! reason for nondelivery was because a shaft in their crushing machine was broken and that as1 soon as it was repaired delivery would be made, which, as defendant stated, would perhaps be on the next day.

It is apparent from the record, however, that no crushed stone of any kind was delivered from about the 15th of August, 1926, until about the 20th of September, and on or about September 1st the plaintiffs made a contract with the Hughes Stone Company for the delivery of all the crushed rock and sand that was necessary for the completion of the federal project. On or about the 20th of September, the defendant offered to continue the shipping of rock and did ship some eight cars, which was refused-About the 1st of September, plaintiffs notified the defendant not to ship any more sand until further orders, and the record is clear that defendant was never after-wards ordered to ship any. The amount paid by the plaintiffs to the Hughes Stone Company exceeded the amount of the contract between plaintiffs and defendants in the sum as alleged in the petition. The plaintiffs offered to prove that it was impossible for them to buy rock either from the Hughes Stone Company, or from the defendant without also contracting to buy the necessary sand, which testimony was refused by the court.

At the close of plaintiffs’ evidence, the court sustained a demurrer thereto. It was then agreed that defendant had shipped crushed rock and sand in the sum of $1,825, which had not been paid for. - The court then permitted defendant to introduce testi *288 mony on its cross-petition. The defendant’s evidence showed that it was in the commission business of selling sand and rock; that it entered into the contract as above' set out for the sale of sand, and that approximately ti,(luO tons of sand were necessary for the completion of the road which the plaintiffs were building, and for which the sand was to be used-; that the defendant furnished some 2,800 tons, leaving approximately 4,000 tons which were not purchased from the defendant, but were purchased by the plaintiffs e.sewhere; that defendant’s commission on the sand was' $8.50 per carload of 50 tons each. To this testimony there was no material contradiction, and thereupon, at the close of all the testimony, the court instructed a verdict in favor of the defendant for the sum of $2,108.57, and from this judgment plaintiffs appeal.

Several assignments of error are made, but the two questions presented by this appeal are, in substance, as follows:

First. Whether or not the court was justified in eonc.uding that the plaintiffs had not established their cause of action, or the right to recover damages from the defendant.

Second. Whether or not under the record the defendant was entitled to a judgment for damages on his cross-petition for breach of the contract.

; It is first contended by the plaintiffs that the-burden is upon the defendant to prove its affirmative aeiense, and by sustaining the demurrer to plaintiffs’ testimony, the court held, in substance, that it was the duty of the plaintiffs to show that the contract was not performed by reason of the broken shaft. Plaintiffs contend that the record is silent as to any affirmative defense, since the defendant introduced no testimony.

The contract for the delivery of the crushed stone provided that “all orders and contracts are accepted subject to contingencies of (manufacture and shipping, and other causes beyond seller’s control-” It is defendant’s contention that this- provision in the contract was sufficient to relieve the defendant from delivery of rock, where it is shown that the reason for the nondelivery was a broken shaft in the crushing machine. With this contention we agree. We think that the broken shaft in the crushing machine would be such a contingency as was intended by the contract. Certainly, it would be an event which would come without design, forethought, or expectation on behalf of the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunter v. Murphy
1926 OK 619 (Supreme Court of Oklahoma, 1926)
Oklahoma City v. Coombs
1927 OK 163 (Supreme Court of Oklahoma, 1927)
Prentice v. Freeman
1919 OK 249 (Supreme Court of Oklahoma, 1919)
Border v. Carrabine
1909 OK 216 (Supreme Court of Oklahoma, 1909)
Russell v. Koller
1918 OK 412 (Supreme Court of Oklahoma, 1918)
Harris v. First Nat. Bank of Bokchito
1908 OK 99 (Supreme Court of Oklahoma, 1908)
Duffey v. Scientific American Compiling Department
1912 OK 96 (Supreme Court of Oklahoma, 1912)
Smith v. Colson
1912 OK 216 (Supreme Court of Oklahoma, 1912)
Renas v. Green
1923 OK 83 (Supreme Court of Oklahoma, 1923)
Stuart v. Edwards
1921 OK 388 (Supreme Court of Oklahoma, 1921)
Checotah v. Hardridge
1911 OK 365 (Supreme Court of Oklahoma, 1911)
Detroit Edison Co. v. Main Island Creek Coal Co.
295 F. 781 (Fourth Circuit, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
1930 OK 161, 286 P. 879, 142 Okla. 286, 1930 Okla. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maxwell-v-zenith-limestone-co-okla-1930.