Maxant v. Chicago Screw Co.

171 Ill. App. 481, 1912 Ill. App. LEXIS 678
CourtAppellate Court of Illinois
DecidedJune 17, 1912
DocketGen. No. 16,371
StatusPublished

This text of 171 Ill. App. 481 (Maxant v. Chicago Screw Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maxant v. Chicago Screw Co., 171 Ill. App. 481, 1912 Ill. App. LEXIS 678 (Ill. Ct. App. 1912).

Opinion

Mr. Justice Baker

delivered the opinion of the court.

May 29, 1909, the plaintiffs, defendants in error here, ordered the defendant to make for them 5,000 screws and 1,500 sets of button dies from patterns to be furnished by plaintiffs. The samples were delivered to defendant June 23rd. The evidence is conflicting as to the time when the dies were to be furnished, but from it the trial court might properly find that they were to be furnished, at the latest, in nine weeks from the time the samples were delivered, and therefore that they were to be furnished by September 1. Some days after the order was given the defendant demanded that plaintiff pay in advance on the order $250, and the defendant made such payment June 12. Nothing was said as to the place of delivery. In September and October the plaintiffs made repeated demands that the defendant furnish the dies, and October 4 notified the defendant by letter that they considered the order cancelled and requested the return of the money paid in advance.

Whether there was an agreement to extend the time of performance'to November 5 was another controverted question. Gorman, a salesman for the defendant, testified that Maxant, one of the plaintiffs, told him about October 5 that if the dies were furnished by November 5 it would be satisfactory to the plaintiffs, and Maxant testified that he made no such statement to Gorman. On this evidence the court might properly find that the time of performance was not extended.

The defendant was not ready to deliver the dies until November 5.

We think that from the evidence the court might properly find that this was an unreasonable delay and constituted such a breach of the contract by the defendant as gave the plaintiffs the right" to cancel the contract and recover the money advanced by them to defendant thereon.

The judgment is for the amount of money so ad-' vanced, and is affirmed.

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
171 Ill. App. 481, 1912 Ill. App. LEXIS 678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maxant-v-chicago-screw-co-illappct-1912.